integration of res to the wr grid
play

Integration of RES to the WR grid 02 nd Sept, 2015 Taj Lands End, - PowerPoint PPT Presentation

Welcome to Presentation on Integration of RES to the WR grid 02 nd Sept, 2015 Taj Lands End, Mumbai Todays Topic Injection of Renewable power on a large scale and its effect on the stability of the grid and operational cycle of conventional


  1. Welcome to Presentation on Integration of RES to the WR grid 02 nd Sept, 2015 Taj Lands End, Mumbai

  2. Todays Topic Injection of Renewable power on a large scale and its effect on the stability of the grid and operational cycle of conventional thermal power plants

  3. Agenda • Installed capacity – Statistics • Variation in RES • Forecasting tools • Regulatory mechanism • Impact on load generation balance • Impact on Transmission system • Impact on Deviation Settlement Mechanism (DSM) • Impact on Thermal generation units

  4. RE in Maharashtra Grid Cumulative Proposed capacity as on Expansion as per Renewable Energy Source 31.03.2015 in State RE policy MW 2015 Wind 4442 5000 Small-Hydro 284 400 Bagasse based co-gen 1000 1440 Biomass power project 200 300 Industrial Waste 32 200 Solar 329 7500 Total 6669 14400 Source- MEDA and GoM Policy

  5. RE in Maharashtra Grid Cumulative capacity as on 31.03.2015 in MW 32, 1% 329, 5% Wind 200, 3% Small-Hydro Bagasse based co- 1414, 21% gen Biomass power 4442, 66% project 284, 4% Industrial Waste Solar Total 6669MW

  6. RE in Maharashtra Grid Proposed Expansion as per State RE policy 2015 32, 1% 329, 5% Wind 200, 3% Small-Hydro Bagasse based co-gen 1414, 21% Biomass power project 4442, 66% Industrial Waste 284, 4% Solar

  7. Growth of Installed Capacity of Renewable Energy in MP Fig in MW BioMass Growth Year Wind Solar Hydro Total Growth % +Bio gas MW 2010-11 278.60 0.00 3.95 80.70 363.25 2011-12 308.90 2.50 12.65 80.70 404.75 41.50 11.42 2012-13 324.50 32.13 13.85 80.70 451.18 46.43 11.47 2013-14 346.90 320.51 21.90 80.70 770.01 318.84 70.67 2014-15 844.35 421.65 24.4 80.7 1371.1 601.09 78.06 2015-16 901.35 561.65 39.4 80.7 1583.1 212 15.46 upto Jul 15

  8. Year wise Actual Injection of RE Generators in MP Fig in MU BioMass+ % Year Wind Solar Hydro Total Bio gas Growth 2010-11 267.81 0.0 2011-12 328.01 0.00 5.54 227.38 560.93 560.93 2012-13 576.19 11.86 15.12 228.05 831.22 270.29 2013-14 515.63 242.86 37.67 289.95 1086.11 254.89 2014-15 604.85 609.15 78.31 208.15 1500.46 414.35 2015-16( upto 669.504 267.4 40.803 26.15 1003.857

  9. Total Installed Capacity in Gujarat as on July 31 2015 and % of RES component As on 31st July 2015 % Growth Sr. in RES State % of RES wrt No. Conventional RES w.r.t. total IC previous year 1 Gujarat 24,148 4,802 17% 8%

  10. Total Installed Capacity in Western Region from 2012-13 to 2014-15 and % of RES component

  11. Pattern of RES in GUJ

  12. RE – Characteristics & Grid integration issues : • Uncertainty, Variability and Intermittency: The generation of RE resources are weather dependent – output is variable 02.07.2015 05.07.2015 Wind 16.06.2015 09.06.2015 Solar

  13. RE – Characteristics & Grid integration issues : • Uncertainty, Variability and Intermittency: Maximum variation in wind energy generation in MUs on two consecutive days: More than 1600 MW Wind variation in a day

  14. RE – Seasonal Availability High wind availability in monsoon period – low domestic and agriculture consumption 9000 2000 1800 8000 1600 7000 Wind energy generated (MUs) 1400 Energy catered (MUs) 6000 1200 5000 1000 4000 Low 800 3000 Demand High 600 High Wind 2000 Demand 400 Low Wind 1000 200 0 0 APR MAY JUNE JULY AUG SEP OCT NOV DEC JAN FEB MAR Energy cattered 2010-11 Energy cattered 2011-12 Energy cattered 2012-13 Wind generation 2010-11 Wind generation 2011-12 Wind generation 2012-13 Energy cattered 2013-14 Wind generation 2013-14 Energy cattered 2014-15 Wind generation 2014-15

  15. Contribution of wind energy to state demand State Demand and Wind - FY 2014-15 14000.0 12000.0 10000.0 8000.0 6000.0 Wind (Mus) 4000.0 State Catered 2000.0 Energy in Mus 0.0 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

  16. Wind- Monthly Variation Wind Monthly Variation- FY 2014-15 1200.0 1000.0 800.0 600.0 Wind (Mus) 400.0 200.0 0.0 Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar

  17. Wind- Hourly Variation MW Hourly variation - 27 June 2015 in MW 2500 2000 1500 MW 1000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

  18. Wind- Hourly Variation 2500 Hourly variation - 6 July 2015 in MW 2000 1500 MW 1000 500 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

  19. Solar- Hourly Variation 300 Daily variation - Solar 4 March 2015 MW 250 200 150 MW 100 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

  20. Solar- Hourly Variation 250 Daily variation - Solar 4 April 2015 MW 200 150 MW 100 50 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

  21. Sakri Solar- Hourly Variation 130 Hourly variations - Sakri Solar 120 110 100 90 80 70 1-May-15 60 21-May-15 50 22-May-15 40 30 20 10 0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24

  22. Solar Forecasting Performance 8.5 MW 1 st March 2013 1.8 1.6 Actual MW 1.4 Forecast MW 1.2 1 0.8 0.6 0.4 0.2 0 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61

  23. Wind- Deviations from forecast Wind farm - % Deviations from Schedule 1 March 2013 80.0% 60.0% Chavneshwar Andra Lake 40.0% 20.0% 0.0% 1 3 5 7 9 11 13 15 17 19 21 23 25 27 29 31 33 35 37 39 41 43 45 47 49 51 53 55 57 59 61 63 65 67 69 71 73 75 77 79 81 83 85 87 89 91 93 95 -20.0% -40.0% -60.0% -80.0%

  24. RE – Grid integration issues : Operational (Guj) • Variation in Wind Generation : impact Variation in wind generation No of Days No of Days No of Days in MW 2012-13 2013-14 2014-15 more than 1000 MW 60 82 94 more than 500 MW 252 267 257 less than 500 MW 113 98 108 Wide variation of 1000-1200 MW generation in a day from renewable sources in a day is quite common.

  25. CERC (Terms and Conditions for Tariff determination from Renewable Energy Sources) Regulations, 2012 dated Dated: 06.02.2012 Regulation : 11. Despatch principles for electricity generated from Renewable Energy Sources: (1) All renewable energy power plants, except for biomass power plants with installed capacity of 10 MW and above and non-fossil fuel based cogeneration plants, shall be treated as ‘MUST RUN’ power plants and shall not be subjected to ‘merit order despatch’ principles.

  26. CERC (IEGC) Regulations, 2010. Must run provision Regulation 5.2 (u) : Special requirements for Solar/ wind generators System operator (SLDC/ RLDC) shall make all efforts to evacuate the available solar and wind power and treat as a must-run station. However, System operator may instruct the solar /wind generator to back down generation on consideration of grid security or safety of any equipment or personnel is endangered and Solar/ wind generator shall comply with the same. For this, Data Acquisition System facility shall be provided for transfer of information to concerned SLDC and RLDC

  27. Central Electricity Regulatory Commission (Deviation Settlement Mechanism and related matters) (Second Amendment) Regulations, 2015, Dated 07Aug 2015: to come into force with effect from 1 st November, 2015

  28. Scheduling of RE energy  RRF (Renewable Regulatory Fund) mechanism was introduced by CERC from July 2013, however subsequently it was suspended due to implementation issues.  CERC has now issued a ‘Framework for Forecasting, Scheduling & Imbalance Handling for Renewable Energy (RE) Generating Stations based on wind and solar at Inter-State Level ’, however the same is applicable only to CTU connected wind and solar generations.  CERC is also in process of preparing a model for state embedded generators.  State Regulator has exempted all RE generators from scheduling.

  29. Roadmap for forecasting and scheduling  Identify a lead generator/coordinating agency at pooling station level.  Ensure infrastructure for telemetry and forecasting  Static data of wind turbines under pilot, like turbine capacity, type, MSL, hub height, lat/long power curve etc  Appoint a forecasting agency equipped with required resources and forecasting tools  Establish a protocol for data and information exchange with SLDC  Daily monitoring of schedules vs actual for assessment of forecasting accuracy . .. Let us work together and make a start to move forward ..!.

  30. Generation forecasting  All generation and load forecasting at SLDC takes place at 15 min time blocks over a day.  Declared generation capacity has to be matched with forecasted load.  Thus generation is planned i.e. scheduled as required for meeting the load.  Certain generation like irrigation/drinking water linked hydro and RE is classified as must absorb i.e. ‘MUST RUN’.  On account of this, conventional generation is regulated on Merit Order Dispatch Principles, based on forecasted availability of small hydro and RE generation.

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend