Inquiry into the High Incidence
- f Power Outages
for the City of Yellowknife
1
Inquiry into the High Incidence of Power Outages for the City of - - PowerPoint PPT Presentation
Inquiry into the High Incidence of Power Outages for the City of Yellowknife 1 AGENDA Introductions North of 60 electrical systems Yukon Electrical Ltd. Northland Utilities (NWT) Ltd. Northland Utilities (YK) Ltd.
1
Introductions North of 60 electrical systems
Yukon Electrical Ltd. Northland Utilities (NWT) Ltd. Northland Utilities (YK) Ltd.
Reliability Indices Definitions
SAIFI, SAIDI, CAIDI
North of 60 Comparisons Reliability Indices NUL Reliability Indices Answers to PUB questions December 12, 2012 Summary
2
38 years of service All in the North
Extensive experience in the operations and
Will be doing the overview this morning
4
23 years of service Extensive experience in the operation of
22 years of service Background in Developing Standards, design
7 years of service Provides design work and estimates for
Does all NUL schematic drawings (MicroStation &
Keeps the statistical records on system
Hydroelectric Grid Multiple source
Diesel backup
Yukon Energy Corp.
Breakers
Auto Reclose
Taltson hydroelectric grid
NTPC Operated
Diesel backup
NUL Operated
Breakers
Auto Reclose
Snare hydroelectric grid
NTPC Operated
Bluefish hydroelectric
NTPC Operated
Diesel back up
NTPC Operated
Breakers
Non Auto Reclose
SAIFI – System Average Interruption Frequency Index
The average number of interruptions per customer
SAIDI – System Average Interruption Duration Index
The system average interruption duration for customers
CAIDI – Customer Average Interruption Duration Index
The average duration of a interruption, for customers who
Table 1.0
SAIFI SAIDI CAIDI
UNPLANNED PLANNED LOSS OF SUPPLY OVER ALL UNPLANNED PLANNED LOSS OF SUPPLY OVER ALL UNPLANNED PLANNED LOSS OF SUPPLY OVER ALL 2010
Yukon Electrical Ltd. 0.25 0.17 1.74 2.16 0.32 0.45 1.12 1.89 1.26 2.61 0.64 0.88 Northland Utilities (NWT) Ltd. 1.82 0.28 2.76 4.86 0.33 0.42 1.35 2.1 0.18 1.49 0.49 0.43 Northland Utilities (YK) Ltd. 1.09 0.12 8.89 10.1 0.48 0.35 5.73 6.56 0.44 2.97 0.64 0.65 CEA Rural Utilities 7.06 2.55 2.77
2011
Yukon Electrical Ltd. 0.88 0.28 3.2 4.36 0.75 0.72 3.85 5.32 0.85 2.56 1.2 1.22 Northland Utilities (NWT) Ltd. 0.12 0.2 11.59 11.91 0.12 0.56 3.83 4.51 0.99 2.8 0.33 0.38 Northland Utilities (YK) Ltd. 1.58 0.27 15.37 17.22 1.83 0.25 5.77 7.85 1.15 0.94 0.38 0.46 CEA Rural Utilities 7.53 2.98 2.53
2012
Yukon Electrical Ltd. 0.92 0.11 0.94 1.97 1.4 0.27 0.53 2.2 1.53 2.37 0.56 1.12 Northland Utilities (NWT) Ltd. 2.43 0.9 9.5 12.83 2.71 1.83 2.86 7.4 1.12 2.04 0.3 0.58 Northland Utilities (YK)
1.76 0.09 15.46 17.31 1.15 0.52 8.15 9.82 0.65 5.86 0.53 0.57 CEA Rural Utilities - NOT AVAILABLE AT THIS TIME
Table 2.0
Total Outag es SAIFI SAIDI CAIDI
UNPLANNED PLANNED LOSS OF SUPPLY OVERALL UNPLANNED PLANNED LOSS OF SUPPLY OVERALL UNPLANNED PLANNED LOSS OF SUPPLY OVERALL
2009/2010 57 0.27 0.05 9.40 9.72 0.30 0.22 3.72 4.24 1.13 4.11 0.40 0.44 2010/2011 100 2.22 0.13 13.07 15.42 1.82 0.22 7.88 9.92 0.82 1.71 0.60 0.64 2011/2012 118 ** 1.84 0.23 18.83 20.90 1.30 0.20 8.28 9.78 0.70 0.89 0.44 0.47 Average 78.50 1.44 0.14 13.77 15.35 1.14 0.21 6.63 7.98 0.88 2.24 0.48 0.52
** Feb 2012 helicopter crash not included
Table 3.0
Cause Number of Outage Events (Feb 2012 helicopter not included) Overall Cause Percentages
2009/2010 2010/2011 2011/2012
Unknown/Other 6 15 16 13% ** Outage Planned 12 25 29 25% ** Supply Lost 16 27 38 29% ** Tree Contact
0.4% Lightning 1
Defective Equipment 9 5 7 8.0% Weather
0.4% Adverse Environment
Human Element 1 2
Foreign Interference 12 24 26 22% **
57 100 118 275 Total Outages During 2009/10, 2010/11, & 2011/12 Total Number of Power Outages
…In the incidence of outages measured by number?
There was an increase in the number of outages year to year
2010 – 57 outages
41 not including loss of supply
2011 – 100 outages
73 not including loss of supply
2012 – 118 outages
80 not including loss of supply
(February 2012 helicopter crash not included)
…In the incidence of outages measured by impacted customers?
There was an increase in the number of customers impacted year to year
2010 – 77,508 customers
2,558 not including loss of supply
2011 – 122,997 customers
18,743 not including loss of supply
2012 – 166,645 customers
16,494 not including loss of supply
(February 2012 helicopter crash not included)
…In the incidence of outages measured by duration?
There was a increase from year to years in the total duration
2010 – 33,835 customer hours
4,155 not including loss of supply
2011 – 79,136 customer hours
16,270 not including loss of supply
2012 – 77,942 customer hours
11,934 not including loss of supply
(February 2012 helicopter crash not included)
5
Operations & Maintenance System Improvements Fuse Co-ordination Plan Breaker to Breaker Protection
25kV Conversion Project – Completed in 2012 Wildlife Protection Program – Completed by 2013 Monthly meetings with NTPC – Ongoing
5
5
5
Positive effect on customers Duration of outages will be lessened in future years.
This would offer a true reflection of the Yellowknife
5
7