Industry Briefing Agenda Welcome address Minister Dean Nalder, - - PowerPoint PPT Presentation

industry briefing agenda
SMART_READER_LITE
LIVE PREVIEW

Industry Briefing Agenda Welcome address Minister Dean Nalder, - - PowerPoint PPT Presentation

Industry Briefing Agenda Welcome address Minister Dean Nalder, MLA Project Overview Project Director - Ray Seman Geotechnical and Tunnelling Geotechnical Manager - Eric Hudson-Smith Procurement and Commercial Delivery Manager - Dave Thomas


slide-1
SLIDE 1

Industry Briefing

slide-2
SLIDE 2

Agenda

Welcome address Minister Dean Nalder, MLA Project Overview Project Director - Ray Seman Geotechnical and Tunnelling Geotechnical Manager - Eric Hudson-Smith Procurement and Commercial Delivery Manager - Dave Thomas Q&A Session

slide-3
SLIDE 3

Industry briefing: purpose

  • The briefing heralds the start of the procurement

process for the $2 billion Forrestfield-Airport Link.

  • Provides insight to the projects planning,

purpose and contract details.

  • Leads into industry engagement to fulfil the aim
  • f appointing main contractor in 2016.
  • Interactive Q&A session with presenters.
  • All material will be available online post-event.
slide-4
SLIDE 4
  • Hon. Dean Nalder,

MLA. Minister for Transport, Finance.

slide-5
SLIDE 5

Project Overview

slide-6
SLIDE 6

Location and Scope

  • 8km twin bored tunnels through soft

ground conditions

  • Tunnelling beneath Swan River and
  • perating Perth Airport
  • Cross passages and egress shafts
  • Rail infrastructure and operating

systems

Three new stations

  • Airport West Station
  • Consolidated Airport Station
  • Forrestfield Station
slide-7
SLIDE 7

Three new stations; two underground

slide-8
SLIDE 8

Timing

  • Industry Briefing

Perth, November 14, 2014

  • Expressions of Interest called

Early 2015

  • Requests for Proposal released

Mid 2015

  • Contract award

Mid 2016

  • Trains running

2020

Procurement, contract award, construction, completion

Delivery Model

Single contract for Design and Construct

  • Responsibility for commissioning
  • Elements of maintenance
  • Excludes rollingstock (trains and buses)
slide-9
SLIDE 9

Concept of operations

  • Standard rail treatments with overhead AC traction power
  • Current rollingstock
  • Known technologies and control systems

Business as usual Integration

  • Rail extension required to integrate with broader suburban

system

  • Consider next generation of signalling and communications

technology

slide-10
SLIDE 10

Tunnels and rail

  • Internal diameter – 6.2m
  • Nine cross passages, three with egress shafts to ground level
  • Waterproofing
  • Rigid Conductor Rail for overhead traction power

Twin bored tunnels, new track to Forrestfield

Rollingstock

  • Included in project budget - not supplied by contractor
  • Forrestfield Line serviced by existing rollingstock
slide-11
SLIDE 11

Stations

  • Platform lengths to accommodate 6 car trains
  • Anticipate island platforms at each station
  • Integration concepts subject to consultation

Station features

  • Airport West Station - shallow underground

station, bus interchange and parking for 500-1,000 cars.

  • Consolidated Airport Station - deeper station,
  • n Commonwealth land, constructed with Perth

Airport works.

  • Forrestfield Station - at grade station with

stowage, bus interchange and parking for up to 2,500 cars.

Airport indicative design 2020 Concept design only Concept design only

slide-12
SLIDE 12

Perth Airport

  • Executive, technical and approvals

working groups

  • Developing Heads of Agreement

Current matters

  • Land access during construction and
  • perations
  • Approvals processes including the

Commonwealth authorities

  • Interaction with planned airport works

Future considerations

  • Use of tunnel and station spoil material
  • Interface with airport security and

emergency services

Relationship

slide-13
SLIDE 13

Forrestfield

  • Service relocations
  • Supply of construction power
  • Road reconfigurations

Early works

Bayswater

  • Optic fibre to East Perth
slide-14
SLIDE 14
  • Main site at Forrestfield
  • Additional areas at Bayswater, Brearley Ave and on Airport land.
  • Less constrained outside Airport

Site availability

Work underway

  • Utility survey throughout
  • Preparation of a 3D model

Utilities

slide-15
SLIDE 15
slide-16
SLIDE 16

Current team

  • PTA project staff: 40 in total
  • Technical Advisors: Various consultancies - local and

international multidisciplinary

  • Legal Advisor: State Solicitor’s Office and Allens Linklaters
  • Probity Auditor: Braxford Consultancy
  • Reference Design
  • Scope of Works and

Technical Criteria

  • Regulatory approvals

Current activities

  • Land acquisition
  • Project Deed
  • Airport processes
slide-17
SLIDE 17

Buy local application

  • Will apply to main contract
  • More information see: State Supply Commission website

Encourages engagement with local industry

Further resources

During contract

  • Design review
  • Commercial support
  • Other specialist advisors

Contract award

  • Technical review
  • Commercial risk
slide-18
SLIDE 18

Geotechnical and Tunnelling

slide-19
SLIDE 19

Likely phases of geotechnical investigations

A staged program is underway

slide-20
SLIDE 20

Phase 2 Geotechnical Scope

  • Over 400 boreholes, cone penetrometer tests and test pits at around 50m spacing,

including barge drilling in Swan River

  • Spoil reuse study
  • Geophysics trial
  • Pump testing, long term groundwater level monitoring in aquifers
  • Laboratory testing including abrasion and frozen soil testing
  • Collection of foundation information on existing facilities
slide-21
SLIDE 21

Phase 2 Geotechnical Scope, continued

  • Geological and hydrogeological models of route
  • Preliminary assessment of construction impacts on nearby facilities (e.g. deep

foundation element construction, aquifer drawdown and excavation)

  • Ground gas monitoring
  • Review of man-made obstructions to tunnelling

Dulles International Airport, 2005-2008: TBM settlement trough

slide-22
SLIDE 22

Preliminary geotechnical findings

  • Geological model – Common Perth units and Ascot Formation

(calcareous sand to calcarenite cobbles)

  • Dewatering and recharge (Leaky aquifer system)
  • Minor ground movement and low levels of associated impact are

likely, provided good practice and no major incidents occur during critical works stages

  • 1M m3 spoil - potentially suitable for re-use
  • Comprehensive baseline and construction monitoring

Modelling, monitoring and groundwater

slide-23
SLIDE 23

Ground Conditions- near Consolidated Airport Station

Current as at 11 November, 2014

slide-24
SLIDE 24

Ground Conditions- across Swan River valley

Current as at 11 November, 2014

slide-25
SLIDE 25

Aquifer behaviour

Leaky aquifer system

slide-26
SLIDE 26

Environmental investigation phases

Ongoing studies:

  • Detailed Site Investigation - Acid Sulphate Soils and soil and

groundwater quality

  • Baseline environmental monitoring
  • Private bore survey
  • Heritage survey

Preliminary site investigation complete

slide-27
SLIDE 27
  • No significant contamination expected in bulk excavations
  • All geological unit are Potentially Acid Sulphate Soils (PASS) to varying

degrees

  • Potential nearby off-site sources of groundwater contamination are being

investigated

  • Nearby sensitive environmental receptors identified

Preliminary environmental findings

slide-28
SLIDE 28

Likely construction methods

  • Bored Tunnelling – Slurry vs EPB

TBM.

  • Diaphragm Walls - Stations and

dives

  • Stations - top down, bottom up

Tunnel boring machine

slide-29
SLIDE 29

Likely construction methods

  • Dewatering, recharge and

monitoring borefields

slide-30
SLIDE 30

Likely construction methods

  • Ground improvement – Jet

grouting, deep/cutter soil mixing

slide-31
SLIDE 31

Likely construction methods- cross passages

slide-32
SLIDE 32

Likely construction methods- ground freezing

slide-33
SLIDE 33

Risk management strategies

Ground Conditions

  • Thorough, staged investigations and

reporting by PTA

  • Involvement of prospective and actual

tenderers in scoping

  • Full disclosure of data
  • Ground Condition Risk Register
  • Geotechnical Interpretive Report

Planning, reporting and scoping

Dulles International Airport, 2005-2008

slide-34
SLIDE 34

Risk management strategies

Ground movement impacts

  • Preliminary studies by PTA - drawdown

and ground movement impacts

  • Baseline monitoring of critical

infrastructure by PTA (inSAR, laser scan, tower)

  • Instrumentation and Monitoring Plan
  • Ground Movement Impact Plan

Investigate and monitor

Perth Airport control tower

slide-35
SLIDE 35

Procurement and Commercial

slide-36
SLIDE 36

Main Works contract

  • lump sum, ‘design & construct’ (D&C) contract
  • purpose-built deed

Form of contract

  • tunnels, station boxes, all civils works
  • tunnel and station fit out and services
  • track
  • rail systems (e.g. signalling, communications, power)
  • some maintenance

Includes all major works

2016 Site works commence 2019 Tunnelling complete 2020 Rail line

  • pens

2017 Tunnelling commences

Note

  • advertised through Tenders WA website
  • State does not intend to contribute to bid costs
slide-37
SLIDE 37

Early Works contracts

To be delivered in advance of the Main Works contract

  • relocation of some significant utilities
  • construction power connection at Forrestfield

Additionally

  • communications link from Bayswater Junction to CBD
slide-38
SLIDE 38

Timetable – Main Works

Procurement timetable

slide-39
SLIDE 39

Typical D&C contract

Risk allocation

slide-40
SLIDE 40

Procurement

Maintenance scope

  • Tunnel infrastructure
  • Tunnel services
  • Station infrastructure
  • Station services

PTA has engaged Braxford Consultancy as Probity Auditor:

Gary Gliddon, Managing Director (08) 6389 2090 / gary@braxford.com

Probity

Airport indicative design 2020 Concept design only Concept design only

slide-41
SLIDE 41

Next steps

Market sounding – to test the project

  • to be undertaken shortly

Data room – early release of data

  • restricted to potential main bidders

EOI release – getting ready

  • January 2015
slide-42
SLIDE 42

Q&A Session

  • Reece Waldock
  • Ray Seman
  • Eric Hudson-Smith
  • Dave Thomas
slide-43
SLIDE 43

Contact

w: forrestfieldaiportlink.wa.gov.au e: connect@forrestfieldairportlink.wa.gov.au p: 13 62 13