Indonesia - North Sumatra Block A update 23 June 2010 Forward - - PowerPoint PPT Presentation
Indonesia - North Sumatra Block A update 23 June 2010 Forward - - PowerPoint PPT Presentation
Indonesia - North Sumatra Block A update 23 June 2010 Forward looking statements This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events
June 2010 | Page 1
Forward looking statements
This presentation may contain forward-looking statements and information that both represents management's current expectations or beliefs concerning future events and are subject to known and unknown risks and uncertainties. A number of factors could cause actual results, performance or events to differ materially from those expressed or implied by these forward-looking statements.
June 2010 | Page 2
North Sumatra Block A (NSBA)
- Established hydrocarbon province
- Existing undeveloped discoveries
- Under-explored
- Rehabilitation opportunities
16.66% Japex 41.67% Premier 41.67% (op.) Medco
June 2010 | Page 3
Summary
PSC Extension
- Significant progress made in securing Aceh local government approval, expect
Central Government approval in Q3
Gas Development – Alur Siwah / Alur Rambong / Julu Rayeu
- Facilities – EPCI documents prepared for tender, award expected Q1 2011
- Drilling – rig secured, detailed well planning underway
- Gas Transportation – pursuing Right of Way sharing with ExxonMobil
- The Operator (Medco) plans First Gas at the end of 2012. Alur Rambong is planned
to have a full year of production in 2013 with Alur Siwah following 6 months into the year
Contingent Resources
- Work-overs on old oil fields successfully executed in 2009
- Currently evaluating results and forward programme
- Internal evaluation (screening studies) undertaken for Kuala Langsa
- Exploratory discussions with Operator and 3rd parties
Exploration Programme
- Matang-1 proposed for 2011
- 2nd Exploration well likely in 2012
June 2010 | Page 4
PSC extension – MOA with Aceh
- Under the Autonomy agreement between Central Government and Aceh, the
Regional Government needs to approve any PSC award or extension in Aceh
- MOA between Aceh Governor and Medco – signed 5th April
- 1% of total revenue from production each year to be used for Community
Development – as per law 2006/11
- Local Government Company to participate in 3rd Party pipeline project
- Aceh to support Extension of the PSC to the JV, with the above terms to be
incorporated in to the PSC
- Aceh Parliament (DPR) verbally endorsed terms of the MOA on 17th May, as
announced by Aceh DPR Head, Pak Hasbi Abdullah. Waiting on formal approval
- With formal approval from Aceh, Medco expects Central Government approval
to be forthcoming in Q3
June 2010 | Page 5
Gas development – gas sales
- Pupuk Iskandar Muda (PIM) – Fertilizer production
- 2 x Fertilizer plants each requiring c 55 BBtu/d of gas
- GSA signed in December 2007
- 223 Tbtu reserves at 110 BBtu/d (PIM obliged to take excess TCQ)
- $6.50 mmbtu, profit share when Urea above $425/tonne
- PLN – Electricity
- New Power generation plant to be built close to Alur Rambong field
- GSA signed in April 2008
- 85 Tbtu at 15 BBtu/d
- $5.30 mmbtu, 3% annual escalation
- Initial delivery expected to be at 5 bbtu/d, ramping up to 15 bbtu/d
June 2010 | Page 6
Gas development – overview
Field Development
- Alur Siwah 10-12 wells
- Alur Rambong 2 wells
- Julu Rayeu 6 wells (fuel gas)
- Central Process Facility (CPF)
with condensate separation, plus H2S and CO2 removal
- 140 MMscf/d export to:
- PIM – 110 bbtu/d
- PLN – 5-15 bbtu/d
- 2000-3000 bcpd
- Gas Export Pipeline to SLS-A
and Power plant
- Gas transportation cost from
SLS-A to PIM, paid by PIM
- Separate condensate line from
CPP to PT Arun
June 2010 | Page 7
Gas development – status
Land Acquisition
- Good progress made - acquisition survey complete, land largely in plantation areas simplifying
purchase process
- Options for CPP location.
- Permits requested – Expect to be granted when Aceh formally endorses PSC
Facilities
- Tender documents prepared for facilities EPCI
- Two Development options carried in the tender:
- 1. Alur Rambong FG at 55bbtu/d followed by Alur Siwah at 110bbu/d after 6 months
- 2. Alur Rambong FG at 55bbtu/d followed by Alur Siwah at 55 bbtu/d after 6 months, then
ramping up to 110 bbtu/d after a further 18 months
(Essentially option 2 defers installation of one of the acid gas removal plants. Decision to be made once commercial bids received).
Drilling
- Detailed well planning underway for first phase of development drilling
- Medco secured PT Antareja Resources Rig-8
- Long Lead drilling tangibles contacts ready to award
- Preparing tender documents for drilling services – to be tendered in Q3
June 2010 | Page 8
Contingent resources – oil fields
- Work-over of 6 wells (5 producers & 1 water injector)
successfully completed
- Wire-line logs run in two wells – movable oil interpreted,
Tu-33 tested at 25 bopd
- Demonstrated:
- Wells can be worked over and produced
- Strong and positive relationship with the local
community, extremely important as a precursor to the gas development
- Going Forward:
- Focus continues to be on gas project but meanwhile
the Operator is evaluating results to-date and formulating further work programmes – including gathering additional data in current wells, considering additional work-overs and some infill drilling
June 2010 | Page 9
Contingent resource – Kuala Langsa gas field
- Giant Gas Field Discovered in 1992
- c.10 Tcf of Gas in Place – the one well
drilled to date recovered around 80% CO2 in the gas test.
- Screening studies undertaken to develop
and sequestrate CO2
- Exploratory development discussions with
- perator and approaches from third parties
Kuala Langsa -1
TD 3756 m
E W S N
Peutu Carbonate
- ver basement
- Lwr. Baong Interval
Bend in Line
Top Peutu Fm. Depth C.I.=50 metres
2500m GWC -3511m
June 2010 | Page 10
Exploration
- Under-explored area – last exploration well
in 1978
- Deep Gas Potential – backfill PIM Gas Sale
from Alur Siwah
- Matang-1 - proposed for 2011
- Potential 2012 wells
- Peudawa Rayeu
- Terumbu Peutouw
- Kuala Langsa
- All the above appraise existing discoveries
- Operator now working on shallower oil-
prone intervals to develop further exploration opportunities
June 2010 | Page 11
Exploration – Matang prospect
Matang-1 - Proposed for 2011
- Reservoir Peutu Carbonates (Alur Siwah,
Arun) – target reefs
- Gas proven by Pergidatit-1
- Main risk is reservoir quality
- Area
15,731 acres
- Depth to crest
2370 mss
- Column height
145 m
- Reserves range
113 – 240 – 440 bcf
- Operators number 400 – 715 – 1330 bcf
- Development Concept is for minimal surface
facilities tied back to Alur Siwah for processing and export to PIM
818 Matang 818 W E
2.5 Km 2.5 Km NSBA PSC: Top N4 Carbonate Depth Blue areas interpreted as reef build-ups
June 2010 | Page 12
North Sumatra Block A (NSBA)
- Established hydrocarbon province
- Existing undeveloped discoveries
- Under-explored
- Rehabilitation opportunities
16.66% Japex 41.67% Premier 41.67% (op.) Medco
June 2010 | Page 13 www.premier-oil.com