Individualized Approach Discussion Muhabbat Ibrohimzoda 1 - - PowerPoint PPT Presentation

individualized approach discussion
SMART_READER_LITE
LIVE PREVIEW

Individualized Approach Discussion Muhabbat Ibrohimzoda 1 - - PowerPoint PPT Presentation

Tajikistan National Mine Action Center under the Government of the Republic of Tajikistan What will it take to get Tajikistan over the 2025 Finish Line? Individualized Approach Discussion Muhabbat Ibrohimzoda 1 Achievements during the


slide-1
SLIDE 1

1

What will it take to get Tajikistan

  • ver the 2025 Finish Line?

Individualized Approach Discussion

Muhabbat Ibrohimzoda Tajikistan National Mine Action Center under the Government of the Republic

  • f Tajikistan
slide-2
SLIDE 2

Achievements during the previous extension period (2010-2018)

Diagram 1: Summary areas released in million square meters (2009 – 2018)

1.29 1.26 1.52 1.82 1.42 0.65 0.25 0.50 0.62 0.59 0.49 0.62 0.52 0.30 0.61 0.50 0.31 0.29 0.16 0.26 0.04 0.05 0.33 0.86 0.77 0.66 0.48 0.40 0.00 0.50 1.00 1.50 2.00 2.50 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 Cleared Reduced Cancelled

2010 Remaining challenge: 14,849,631m² Target for the period 2009-2019:

14,860,000m².

Tajikistan addressed 17,565,639m² for the period 2009-2018 representing progress of (124%) against the target. 7 districts declared ‘mine-free’. During 2010-2018, previously unknown mined areas measuring 10,485,815 m² were identified. The highest rates of released land performed in the period 2010-2014 as a result of deployed mechanical demining assets in the flat areas of Tajik-Afghan border. Landmines & UXO Destroyed Land cleared and reduced 77,846 13,973,190 sqm Land cancelled by non-technical survey Total land released and handed over 3,592,449 sqm 17,565,639 sqm

slide-3
SLIDE 3
slide-4
SLIDE 4

Location of Remaining Hazards to be Cleared by 2025

slide-5
SLIDE 5

Plan to address remaining contamination

Tajikistan has a remaining challenge of 249 hazardous areas measuring 12,098,210m². This includes: ▪ 154 confirmed hazardous areas measuring 7,907,210m² ▪ 41 SHA measuring an estimated 941,000m². ▪ 54 SHA measuring 3,250,000m² (Tajik –Uzbek border) During the extension period Tajikistan will address the following: ▪ 195 CHA&SHA measuring 8,848,210 m² ▪ This target excludes 54 SHA measuring 3,250,000m²

  • n the Tajik-Uzbek border, that will be addressed once

a political agreement has been made. This 2025 goal is based on doubling current capacity. Resources Time 2025 2030

Current resources Required resources

Clearance rate projection based on capacity available in 2019

8.8 7.6 6.3 5.1 3.8 2.5 1.3

  • 1

1 2 3 4 5 6 7 8 9 10 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029

Contaminated area in mln sq. meters

Land release projections based on required versus current capacity Required capacity Based on current resources

slide-6
SLIDE 6

Plan to address the remaining contamination

Unit Organisation Current Capacity NPA MOD Total Deminer 40 50 90 Output 28 28 28 Days per year 130 130 130 Daily output 1120 1400 2 520 Annual Output 145 600 182 000 327 600

Unit Organisation Current Capacity Planned Capacity Planned capacity Total planned NPA MOD Total MOD NPA Total Deminers 40 50 90 100 80 180 Output 28 28 28 28 28 28 days per year 130 130 130 130 130 130 Daily output 1120 1400 2'520 2'800 2'240 5'040 Annual Output (130 days) 145 600 182 000 327 600 364 000 291 200 655 200 Total 327 600 655 200

Annual Milestones (square metres): 2019 1,369,429 2020 1,388,819 2021 1,218,722 2022 1,284,655 2023 1,277,666 2024 1,138,919 2025 1,170,000 Tajikistan has outlined the need for the following annual milestones with current capacities. In order to reach the goal by 2025 Tajikistan would need to double its current capacity

slide-7
SLIDE 7

Current cooperation and assistance and challenges

Year Annual Milestone (square metres) Current national resources (US $) Current international resources (US $) Additional Funding Required for increasing capacity Total 2020 1 388 819 480 000 2 600 000 3 400 000 6 480 000 2021 1 218 722 480 000 2 600 000 1 800 000 4 880 000 2022 1 284 655 480 000 2 600 000 1 800 000 4 880 000 2023 1 277 666 480 000 2 600 000 1 800 000 4 880 000 2024 1 138 919 480 000 2 600 000 1 800 000 4 880 000 2025 1 170 000 480 000 2 600 000 1 800 000 4 880 000 TOTAL 7 478 781 2 880 000 15 600 000 12 400 000 30 880 000

slide-8
SLIDE 8

Remaining confirmed hazard areas to be cleared

Land use of remaining areas

Priorities:

  • Housing, border patrolling routes, agricultural land and livestock farms
  • Water, electricity, sewage, landlines
  • Natural Reserves, territories important for tourism and other national parks and places with

attractive nature 36% 4% 24% 11% 1% 3% 11% 1% 9% Pastureland Agriculture Borderline Wild fruits and wood collection Water supply Fisheries Construction Road Mining (coal, gold)

slide-9
SLIDE 9

Examples of hazardous areas on the Tajik/Afghan border

slide-10
SLIDE 10

Remaining suspected hazard areas to be surveyed

Approximately 41 SHA to be surveyed

  • Area

to be surveyed based

  • n

30 remaining minefield records.

  • Survey is expected to be completed by

2023

slide-11
SLIDE 11

Impacts of the contamination

THE IMPACT OF EXPLOSIVE HAZARDS

CONTAMINATION

25

districts contaminated by mines, cluster munitions and explosive remnants of war

  • ver

Daily life, resettlement for communities after conflict and development impeded

IMPACT

as of May 2019

872

reported casualties from mines, cluster munition and explosive remnants

  • f war

Children 28% Women 9% Men 63%

100 200 300 400 500 600

Men Women Boys Girls

Injured Killed

slide-12
SLIDE 12

An example of landmines Impact to local inhabitants

Abandoned houses in the villages of Sh. Shohin district

slide-13
SLIDE 13

Economic Potential of the area

2km North of Sarighor village is over 20 hectares of apple trees being cultivated and substantial cattle grazing, clearly showing the economic potential of the area.

slide-14
SLIDE 14

Follow-up activity

▪ Concept note for increasing capacity of FSD, Norwegian People’s Aid and Ministry of Defence circulated ▪ Concept note on the re-introduction of Mechanical assets into Tajikistan Mine Action Programme ▪ Work with ISU and UNDP on the initial launch of National Coordination Mechanism: including visit to a contaminated site– July 2019

slide-15
SLIDE 15

Any questions?