IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

IH 2 H 20 IMPROVEME EMENTS

New Interchange at CR 1250

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried out by TxDOT pursuant to 23 U.S.C. 327 and a Memorandum of Understanding dated December 16, 2014, and executed by FHWA and TxDOT.

slide-2
SLIDE 2

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Introductions

  • Gene Powell – Public Information Officer (TxDOT)
  • Robert Ornelas, P.E. – TP&D Director (TxDOT)
  • Gabriel Ramirez, P.E. – Advanced Planning Engineer (TxDOT)
  • Paul Aparicio, P.E., - Project Manager (TxDOT)
  • Brad Kwaterski, P.E. – Project Manager (AECOM)
  • Other TxDOT Staff

2

slide-3
SLIDE 3

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Agenda

3

Introductions Proposed Improvements Why is Project Needed? Environmental Considerations Next Steps Public Comment 1 2 3 4 5 6

slide-4
SLIDE 4

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

4

Project Description

  • Construction Limits:

– FM 1788 to LP 250 (Approx. 5 miles)

  • Project Description

– Construct interchange at CR 1250 – Reconfigure ramps near FM 1788 and LP 250 to accommodate new CR 1250 interchange – Reconstruct frontage roads from FM 1788 to LP 250

  • Funding

– $19.84M total authorized funding

4

slide-5
SLIDE 5

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Project Overview – Proposed Improvements

5

Begin Construction End Construction

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

slide-6
SLIDE 6

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

CR1 CR1250 I Interc rchange

6

  • Construct IH-20 bridge over CR 1250
  • Extend CR 1250 to southern frontage road and widen
  • Improve access to CR 1250

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

slide-7
SLIDE 7

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Ramps Ne Near F FM 1 1788 788

7

MIDL DLAND D IN INTERNATIONAL A AIR IR & & SPA PACE P PORT

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

slide-8
SLIDE 8

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Ramps Ne Near F FM 1 1788 788

8

  • Relocate existing WB exit ramp to FM 1788 and existing EB entrance ramp from FM 1788
  • Construct two entrance ramps and two exit ramps
  • Construct auxiliary lane between ramps on frontage roads (open to traffic in future)
  • Reconstruct frontage roads to include curb and gutter

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

slide-9
SLIDE 9

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

MIDL DLAND D IN INTERNATIONAL A AIR IR & & SPA PACE P PORT

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

Ramps Ne Near L LP 250 250

9

slide-10
SLIDE 10

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Ramps Ne Near L LP 250 250

10

LEGEND Mainlane Frontage Rd Cross Street Bridges Ramps

  • Relocate existing WB entrance ramp from LP 250 and existing EB exit ramp to LP 250
  • Construct two entrance ramps and two exit ramps
  • Construct auxiliary lane between ramps on frontage roads (open to traffic in future)
  • Reconstruct frontage roads to include curb and gutter
slide-11
SLIDE 11

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

11

Why is Project Needed? – Insufficient access to/from industrialized area serviced by CR 1250 on IH 20. – IH 20 freight and commuter traffic congestion at IH 20/LP 250 intersection and IH 20/FM 1788 intersection.

11

slide-12
SLIDE 12

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Regional Compatibility

  • City of Midland’s Tall City

Tomorrow Plan

  • CR1250 as a future major

arterial

12

slide-13
SLIDE 13

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

13

Midland - Tall City Tomorrow Comprehensive Plan

13

slide-14
SLIDE 14

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

14

Midland - Tall City Tomorrow Comprehensive Plan

14

FM 1788 CR 1250 LP 250

slide-15
SLIDE 15

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Natural Environment

  • Waters of the U.S./wetlands
  • Water quality
  • Vegetation
  • Wildlife
  • Threatened and endangered species

Human Environment

  • Community impacts
  • Bike/pedestrian considerations
  • Parks
  • Traffic noise
  • Air quality
  • Cultural resources

Environmental Considerations

Environmental Study: NEPA requires environmental analysis of a project’s impact on natural and human environment if federal funds are to be used.

15

slide-16
SLIDE 16

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

Next Steps

16

slide-17
SLIDE 17

IH-20 Improvements – New Interchange at CR 1250 – CSJ 0005-14-084 January 29, 2019

17

Questions and Comments

Commen ents m mus ust be be recei eceived ed or

  • r postmarked

ed b by Febr ebrua uary 1 13, 3, 20 2019. 9.

  • Submit comments at today’s meeting
  • Submit in writing to:

Texas Department of Transportation Attn: Gabriel Ramirez, P.E. 3901 East Highway 80 Odessa, TX 79761

  • Submit by email to Gabriel.Ramirez@txdot.gov