IGT114: Mod Title: Extending the data available to Suppliers under K24.3(l) Proposer: Colin Blair, Scottish Power Panel Date: 18 July 2018 Why change? Market Intelligence Service (MIS) background RP0 RP1 RP2 RP3 No system or process


  1. IGT114: Mod Title: Extending the data available to Suppliers under K24.3(l) Proposer: Colin Blair, Scottish Power Panel Date: 18 July 2018

  2. Why change? – Market Intelligence Service (MIS) background RP0 RP1 RP2 RP3 No system or process Use existing systems. New central switching New central switching The Ofgem Switching changes. Address matching to service (core data). service and market No Improvement to improve reliability. Enduring reliability intelligence services. Programme set out 4 reform reliable switching. Key Process changes improvement to data Enduring reliability packages: 21 day switch. (harmonised where quality. improvement, and possible) to deliver 3 Harmonised and improved access to to 7 day switch. simplified next day broader range of 1. Do nothing switching process. switching data. Harmonised and 2. Enhance existing simplified next day 3. CSS switching process. 4. CSS and MIS ➢ As a result of the consultation Ofgem refined option 2 and the new option became 2A, and determined that the industry was best placed to develop and fund the MIS services ➢ Ofgem then asked Xoserve and Gemserv to take forward the MIS initiative

  3. Why change? – MIS governance background Gas representation established under the Data Services Contract Change Management Committee

  4. Why change? – Use case background  JMDG developed use case for Supplier access to gas and electricity data via API  Purpose to support Suppliers in:  Provide quotation services to customer  Improve the quality of the switch request into UK Link  Improved creation of customer account on Supplier records  JMDG recommended service to MIS Programme Board  MIS Programme Board agreed and approved  MIS Programme Board (gas) sponsoring UNC modification to give effect to use case delivery  Modification required to permit release of data to Suppliers

  5. Options  Prepared along same lines as Modification 106S: Provision of access to Domestic Consumer data for Suppliers  Commercial arrangements same as developed under Modification 106S  Extension of data items and to non-domestic data  Mod limits permission to Suppliers, not PCW or TPI

  6. Solution Amend IGT UNC text to permit release of data to Suppliers

  7. Recommended Steps  The Proposer recommends that this modification should be:  Subject to self-governance  Workgroup assessment to develop the modification for 2 months

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.