ibl lapp cooling lines
play

IBL - LAPP Cooling lines 1. Design and production status 2. - PowerPoint PPT Presentation

IBL - LAPP Cooling lines 1. Design and production status 2. Installation 3. Schedule LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore


  1. IBL - LAPP Cooling lines 1. Design and production status 2. Installation 3. Schedule LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore Todorov, Tamer Yildizkaya 1 2014-02-06 Pierre Delebecque

  2. Design and production status 2 2014-02-06 Pierre Delebecque

  3. Design and production status PP1 region 3 2014-02-06 Pierre Delebecque

  4. Design and production status PP1 region 4 2014-02-06 Pierre Delebecque

  5. Design and production status Splitting box region 5 2014-02-06 Pierre Delebecque

  6. Design and production status Splitting box region 6 2014-02-06 Pierre Delebecque

  7. Design and production status Stainless steel cooling lines production  Production tooling (bending) under construction  First final lines to be tested on the mockup Bending system for the PP1 region First bent samples 7 2014-02-06 Pierre Delebecque

  8. Design and production status Isolators Production  Metallic sleeves delivered to Microcertec  Bent Pipes delivered to Microcertec  Isolator should be delivered before end of february.  Last EB qualification : Leak tests are OK, CO2 cycling is in work, metalurgical analysis is in work , final welding planned begining of march.  Setups for tests are almost ready 8 2014-02-06 Pierre Delebecque

  9. Installation 9 2014-02-06 Pierre Delebecque

  10. Installation – Transportation and assembly  « Ambroise » mockup was tested in the pit  Installation tests to be carried on begining of march 10 2014-02-06 Pierre Delebecque

  11. Schedule  February :  Isolator production / brazing  Final bending tools developments and first lines tested on the mockup  Installation tools final design and orders  March  Last isolator EB welding  Final bending of the 28 cooling lines and tests  Installation tools mounting and tests  April  Lines assembly on the installation tools and first orbital welding tests  Final orbital welding at CERN and test  May  Begining of may : sets ready for installation  Installation in the pit official date may 29 th 11 2014-02-06 Pierre Delebecque

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend