IBL - LAPP Cooling lines 1. Design and production status 2. - - PowerPoint PPT Presentation

ibl lapp cooling lines
SMART_READER_LITE
LIVE PREVIEW

IBL - LAPP Cooling lines 1. Design and production status 2. - - PowerPoint PPT Presentation

IBL - LAPP Cooling lines 1. Design and production status 2. Installation 3. Schedule LAPP team Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore


slide-1
SLIDE 1

Pierre Delebecque 2014-02-06

1

IBL - LAPP Cooling lines

LAPP team

Jacky Ballansat, Jean-Philippe Baud, Patrick Baudin, Pierre-Yves David, Pierre Delebecque, Sabine Elles, Nicolas Massol, Thibaut Rambure, Theodore Todorov, Tamer Yildizkaya

  • 1. Design and production status
  • 2. Installation
  • 3. Schedule
slide-2
SLIDE 2

Pierre Delebecque 2014-02-06

2

Design and production status

slide-3
SLIDE 3

Pierre Delebecque 2014-02-06

3

Design and production status

PP1 region

slide-4
SLIDE 4

Pierre Delebecque 2014-02-06

4

Design and production status

PP1 region

slide-5
SLIDE 5

Pierre Delebecque 2014-02-06

5

Splitting box region

Design and production status

slide-6
SLIDE 6

Pierre Delebecque 2014-02-06

6

Splitting box region

Design and production status

slide-7
SLIDE 7

Pierre Delebecque 2014-02-06

7

Stainless steel cooling lines production

Design and production status

  • Production tooling (bending) under construction
  • First final lines to be tested on the mockup

First bent samples Bending system for the PP1 region

slide-8
SLIDE 8

Pierre Delebecque 2014-02-06

8

Production

  • Metallic sleeves delivered to Microcertec
  • Bent Pipes delivered to Microcertec
  • Isolator should be delivered before end of february.
  • Last EB qualification : Leak tests are OK, CO2 cycling is in work,

metalurgical analysis is in work , final welding planned begining of march.

  • Setups for tests are almost ready

Isolators

Design and production status

slide-9
SLIDE 9

Pierre Delebecque 2014-02-06

9

Installation

slide-10
SLIDE 10

Pierre Delebecque 2014-02-06

10

Installation – Transportation and assembly

  • « Ambroise » mockup was tested in the pit
  • Installation tests to be carried on begining of march
slide-11
SLIDE 11

Pierre Delebecque 2014-02-06

11

Schedule

  • February :
  • Isolator production / brazing
  • Final bending tools developments and first

lines tested on the mockup

  • Installation tools final design and orders
  • March
  • Last isolator EB welding
  • Final bending of the 28 cooling lines and tests
  • Installation tools mounting and tests
  • April
  • Lines assembly on the installation tools and

first orbital welding tests

  • Final orbital welding at CERN and test
  • May
  • Begining of may : sets ready for installation
  • Installation in the pit official date may 29th