HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019 - PowerPoint PPT Presentation

HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019 Hill Street 2 Greene Street State Street N Project Lim imits 3 Project Criteria Road Improve road surface for traffic usage Cross-section 11 foot min.


  1. HOOVER, GREENE, & HILL PROJECT PUBLIC MEETING January 17, 2019

  2. Hill Street 2 Greene Street State Street N Project Lim imits

  3. 3 Project Criteria ▪ Road ✓ Improve road surface for traffic usage ✓ Cross-section – 11 foot min. travel lanes ✓ Bike lanes – 5 foot wide on Hoover ✓ ADA ramps – Update where needed ✓ Crosswalks – Update markings and signing ▪ Utilities ✓ Water main – Upgraded from 6-inch to 12-inch ✓ Storm sewer – Increase detention storage ✓ City Fiber Conduit

  4. 4 Project Im Improvements ▪ Hill (Adams to Fifth) ✓ Water main upgrade ✓ Road resurfacing ▪ Greene (Hill to Keech) ✓ Stormwater enhancements ✓ Road resurfacing ▪ Hoover (Main to State) ✓ Water main upgrade ✓ Stormwater enhancements ✓ Road resurfacing ▪ Selected sidewalk ramps/crosswalks improvements

  5. 5 Project Funding ▪ Part of Capital Improvement Plan (CIP) ▪ Funding Sources ✓ Water Funds ✓ Road Resurfacing Funds ✓ Allen Creek Storm Water Funds ✓ Possible U-M participation

  6. 6 Project Schedule ▪ March/April 2019 - Contractor selection ▪ Late April/Early May 2019 - Start work ▪ End August 2019 - Substantially complete

  7. 7 Proposed Uti tility Work – Hil ill Greene Street N

  8. 8 Proposed Road Work – Hill Greene Street N

  9. 9 Proposed Uti tility Work – Greene N

  10. 10 Proposed Road Work – Greene N

  11. 11 Proposed Uti tility Work – Greene & Keech N

  12. 12 Proposed Road Work – Greene & Keech N

  13. 13 Proposed Uti tility Work - Hoover N

  14. 14 Proposed Road Work - Hoover N

  15. 15 Proposed Uti tility Work - Hoover N

  16. 16 Proposed Road Work - Hoover N

  17. 17 Proposed Uti tility Work - Hoover N

  18. 18 Proposed Road Work - Hoover N

  19. 19 Maintenance of f Traffic – Primary ry Detours Estimated Duration: 4 months Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Elbel IM Building Admin Serv Bldg Ferry Field SC36

  20. 20 Maintenance of f Traffic – Hoover Closure Estimated Duration: 4 Weeks Traffic Detour for Hoover Closure Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Hoover Closure Elbel WB Hoover CLOSED Total Closure WB Hoover CLOSED IM Building EB Hoover OPEN Admin Serv Bldg Ferry Field SC36

  21. 21 Maintenance of f Traffic – Hill Closure Estimated Duration: 3 weeks Traffic Detour for EB Hill Traffic Detour for WB Hill Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Total Hill Closure Closure Elbel Admi IM Building Admi n Serv n Serv Bldg Bldg Ferry Field SC36

  22. 22 Maintenance of f Traffic – Hill/Fifth Closure Estimated Duration: Weekend Traffic Detour for EB Hill Traffic Detour for WB Hill Traffic Detour for WB Hoover Traffic Detour for NB Greene/EB Keech Total Closure Hill Closure Elbel IM Building Admi Admi n Serv n Serv Bldg Bldg Ferry Field SC36

  23. 23 23 Questions & Contact Chris Wall, PE CWall@a2gov.org (734) 794-6000 ext. 43661

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.