Honolulu Authority for Rapid Transportation STAFF - - PDF document

honolulu authority for rapid transportation
SMART_READER_LITE
LIVE PREVIEW

Honolulu Authority for Rapid Transportation STAFF - - PDF document

Honolulu Authority for Rapid Transportation STAFF SUMMARY TITLE: STAFF CONTACT: DATE: Vector Control Installation Contract In-Tae Lee, Deputy Director May 16, 2019 of Design & Engineering Type: Goal Focus Area Reference


slide-1
SLIDE 1
slide-2
SLIDE 2

Honolulu Authority for Rapid Transportation

STAFF SUMMARY

TITLE:

Vector Control Installation Contract

STAFF CONTACT: In-Tae Lee, Deputy Director

  • f Design & Engineering

DATE: May 16, 2019 Type: Goal Focus Area Reference Notes

Action/Approval

Project Delivery Livability/Land Use

Information

Service Delivery Partnerships

Follow-up

Resource Stewardship Agency Admin.

  • 1. Purpose:
  • To seek Board of Directors approval to fund the design and installation of the Vector Control System for the guideway including all

stations.

  • Provide a safe working environment; protect HART’s facilities, and HART’s Safety Hazard Analysis resulting in dense accumulation of

Guano, exposing workers to a potential health hazard.

  • 2. Background/Justification
  • In May 2011, recommendations were made to control bird/ rodent access to the guideway inner cavities and at stations to prevent

birds from perching over areas frequently used by passengers. However, no budget was set aside.

  • In January 2019, HART’s Safety performed a Hazard Analysis for birds entering and roosting in the guideway cavity resulting in dense

accumulation of Guano, exposing worker to a potential health hazard.

  • An Executive Decision Document was written and approved in March 2019, requesting approval to the vector measures on HRTP.
  • 3. Board Authority

HART Board is required to approve all new contracts over $1M. The total value of the proposed new CPP is $1,390,500.00.

  • 4. Procurement Background

These actions will create a new CPP.

  • 5. Financial/Budget Impact

The budget for the new CPP will be funded from allocated Westside contingency.

  • 6. Policy Impact

Not Applicable

  • 7. Public Involvement

Not Applicable

  • 8. Alternatives

Do not install vector intrusion and harm workers.

  • 9. Exhibits

PowerPoint Presentation

slide-3
SLIDE 3

Vector Control Installation Contract

Board of Directors Meeting May 16, 2019  Honolulu, Hawaiʻi

slide-4
SLIDE 4

Purpose

  • To seek Board approval to fund the design and installation of the Vector

Control System for the guideway including all stations.

  • Provide safe working environment.
  • Protect HART’s facilities.
  • HART’s Safety Hazard Analysis resulting in dense accumulation of Guano,

exposing workers to a potential health hazard.

2

slide-5
SLIDE 5

Background

  • In May 2011, recommendations were made to control bird/rodent access to the

guideway inner cavities and at stations to prevent birds from perching over areas frequently used by passengers. However, no budget was set aside.

  • In January 2019, HART’s Safety performed a Hazard Analysis for birds entering and

roosting in the guideway cavity resulting in dense accumulation of Guano, exposing workers to a potential health hazard.

  • An Executive Decision Document was prepared and approved in March 2019,

requesting approval to implement the vector control measures on HRTP.

3

slide-6
SLIDE 6

4

WOFH

ROC

KHG Airport City Center

Project Map 20 Miles – 21 Stations

slide-7
SLIDE 7

Nesting in Guideway Box Girder

5

slide-8
SLIDE 8

Guano in WOFH Box Girder

6

slide-9
SLIDE 9

7

Cost Overview

Rough Order of Magnitude (ROM) costs as follows:

Westside Guideway and Stations (WOFH & KHG)

$ 698,000

Airport Guideway and Stations

$ 290,400

P3 City Center Guideways

$ 402,100

Total Contract Value

$ 1,390,500

Note: Funding will be allocated from Westside contingency for the total contract value.

slide-10
SLIDE 10

Recommendation

Approve the funding to design and install the Vector Control System for the guideway including all stations for a total of $1,390,500.00.

8

slide-11
SLIDE 11

Questions?

9

slide-12
SLIDE 12