Honolulu Authority for Rapid Transportation STAFF - - PDF document
Honolulu Authority for Rapid Transportation STAFF - - PDF document
Honolulu Authority for Rapid Transportation STAFF SUMMARY TITLE: STAFF CONTACT: DATE: Vector Control Installation Contract In-Tae Lee, Deputy Director May 16, 2019 of Design & Engineering Type: Goal Focus Area Reference
Honolulu Authority for Rapid Transportation
STAFF SUMMARY
TITLE:
Vector Control Installation Contract
STAFF CONTACT: In-Tae Lee, Deputy Director
- f Design & Engineering
DATE: May 16, 2019 Type: Goal Focus Area Reference Notes
Action/Approval
Project Delivery Livability/Land Use
Information
Service Delivery Partnerships
Follow-up
Resource Stewardship Agency Admin.
- 1. Purpose:
- To seek Board of Directors approval to fund the design and installation of the Vector Control System for the guideway including all
stations.
- Provide a safe working environment; protect HART’s facilities, and HART’s Safety Hazard Analysis resulting in dense accumulation of
Guano, exposing workers to a potential health hazard.
- 2. Background/Justification
- In May 2011, recommendations were made to control bird/ rodent access to the guideway inner cavities and at stations to prevent
birds from perching over areas frequently used by passengers. However, no budget was set aside.
- In January 2019, HART’s Safety performed a Hazard Analysis for birds entering and roosting in the guideway cavity resulting in dense
accumulation of Guano, exposing worker to a potential health hazard.
- An Executive Decision Document was written and approved in March 2019, requesting approval to the vector measures on HRTP.
- 3. Board Authority
HART Board is required to approve all new contracts over $1M. The total value of the proposed new CPP is $1,390,500.00.
- 4. Procurement Background
These actions will create a new CPP.
- 5. Financial/Budget Impact
The budget for the new CPP will be funded from allocated Westside contingency.
- 6. Policy Impact
Not Applicable
- 7. Public Involvement
Not Applicable
- 8. Alternatives
Do not install vector intrusion and harm workers.
- 9. Exhibits
PowerPoint Presentation
Vector Control Installation Contract
Board of Directors Meeting May 16, 2019 Honolulu, Hawaiʻi
Purpose
- To seek Board approval to fund the design and installation of the Vector
Control System for the guideway including all stations.
- Provide safe working environment.
- Protect HART’s facilities.
- HART’s Safety Hazard Analysis resulting in dense accumulation of Guano,
exposing workers to a potential health hazard.
2
Background
- In May 2011, recommendations were made to control bird/rodent access to the
guideway inner cavities and at stations to prevent birds from perching over areas frequently used by passengers. However, no budget was set aside.
- In January 2019, HART’s Safety performed a Hazard Analysis for birds entering and
roosting in the guideway cavity resulting in dense accumulation of Guano, exposing workers to a potential health hazard.
- An Executive Decision Document was prepared and approved in March 2019,
requesting approval to implement the vector control measures on HRTP.
3
4
WOFH
ROC
KHG Airport City Center
Project Map 20 Miles – 21 Stations
Nesting in Guideway Box Girder
5
Guano in WOFH Box Girder
6
7
Cost Overview
Rough Order of Magnitude (ROM) costs as follows:
Westside Guideway and Stations (WOFH & KHG)
$ 698,000
Airport Guideway and Stations
$ 290,400
P3 City Center Guideways
$ 402,100
Total Contract Value
$ 1,390,500
Note: Funding will be allocated from Westside contingency for the total contract value.
Recommendation
Approve the funding to design and install the Vector Control System for the guideway including all stations for a total of $1,390,500.00.
8
Questions?
9