heavy metal hazardous
play

Heavy Metal Hazardous Waste Disposal Site Octavius V Catto School - PowerPoint PPT Presentation

Delineation, Remediation and Redevelopment of a Heavy Metal Hazardous Waste Disposal Site Octavius V Catto School Redevelopment Project Camden, New Jersey J. Stuart Wiswall, P.G., LSRP Keating Environmental Management, Inc. Community


  1. Delineation, Remediation and Redevelopment of a Heavy Metal Hazardous Waste Disposal Site Octavius V Catto School Redevelopment Project Camden, New Jersey J. Stuart Wiswall, P.G., LSRP Keating Environmental Management, Inc.

  2. • Community Revitalization Effort Involving the Collaboration of Public/Private/Regulatory Stakeholders • Redevelopment of a Failing Apartment Complex with a Community Park • Utilized the Triad Approach for Site Assessment Key Elements • Remediation of a Former Pond Used for of the Project Hazardous Waste Disposal and Filled Wirh Historic Fill • On-site Stabilization of Hazardous Waste Prior to Off-site Disposal • Engineering and Institutional Controls Employed to Manage Residual Contamination

  3. 3 Site History and Setting

  4. 4 1898 Topographic Map

  5. 1940 Aerial Photograph

  6. 1963 Aerial Photograph Adjacent Pigment Manufacturing Site

  7. 1967 Aerial Photograph Apartment Complex Constructed

  8. 8 E 2005 Abandoned Manufacturing Plant

  9. 9 Site Plan

  10. 10 E 2009 Building G – Upper Pond Area

  11. 11 E 2009 Building S On Edge of Buried Pond

  12. 12 2009 Repaired Settlement Cracks

  13. 13 Remedial Objectives

  14. 14 Remedial Objectives • Remove Hazardous Waste • Protect Groundwater Quality • Eliminate Direct Exposure Pathway

  15. 15 Site Characterization

  16. 16 Triad Approach • Systematic Project Planning • Dynamic Work Plan • Real Time Measurement Technologies • GPR/EM • Downhole Conductivity Probe • X-Ray Fluorescence • On-site Laboratory

  17. 17 GPR/EM Survey

  18. 18 Downhole Conductivity Probe

  19. 19 Typical Conductivity Log In From Pond 10000 1000 Peat/Sand Historic Fill Conductivity (mS/m) 100 Sludge 10 1 0 5 10 15 20 25 Depth (feet)

  20. Limits of Historic Fill And Pond Pond Sludge

  21. Identified Contaminants of Concern • Historic Fill  Benzo(a)anthracene (46 mg/kg), Lead (6,700 mg/kg), Zinc (21,000 mg/kg) • Sludge  Lead (47,000 mg/kg total, 130 ug/L TCLP) • Ground Water • Arsenic (18 ug/L), Cadmium (12 ug/L), Chromium (330 ug/L), Lead (67 ug/L), Cyanide (1,570 ug/L)

  22. Contaminants of Concern • TCLP analysis; lead leached above the toxic characteristic hazardous waste threshold in some sludge samples • SPLP Analysis: Potential for lead and arsenic to leach from fill above GWQS

  23. 23 Remedial Approach • Excavate/Stockpile Historic Fill • Dewater Pond, Treat Groundwater and On-site Infiltration • Excavate Sludge, Stabilize, Off-site Disposal • Install Clean Soil Buffer, Place Historic Fill, Install Clean Soil Cap • Establish Ground Water Classification Area and Deed Notice

  24. 24 S Remediation

  25. 25 Remediation Steps • Building Decontamination and Removal • Foundation Removal • Excavation/Stockpiling of Historic Fill from Pond Area • Excavation and Stabilization of Sludge • Install Clean Soil Buffer • Replace Historic Fill • Install Cap • Establish CEA

  26. 26 February 2005

  27. 27 Removing Foundations

  28. 28 Bottles in Foundation Concrete

  29. 29 Dewatering Wells Installed

  30. 30 Water Treatment System

  31. 31 Historic Fill Excavation From Pond

  32. 32 RRetaining Wall

  33. 33 Paint Waste in Historic Fill

  34. 34 Historic Fill Stockpile

  35. 35 Pond Sludge Layer

  36. 36 Excavating Sludge

  37. 37 Sludge Treatment Area

  38. 38 A Part of the Treatment Area

  39. 39 Pigment Layering in Sludge

  40. 40 Pond Bottom

  41. 41 Confirmation Sampling of Pond Bottom

  42. 42 Placing Clean Soil Buffer

  43. 43 Waste Stabilization • Stabilization Chemical - Inorganic Mixture of Magnesium Oxide and Calcium Phosphate • Attempt to use phosphoric acid-based product unsuccessful; Reaction generated H2S • Pre-remediation bench testing to determine treatment ratio for lead • Composite sampling of each waste pile to determine lead concentration • Product delivered in bulk and mixed with excavator • Post treatment composite sampling to verify results

  44. 44 Chemical Delivery

  45. 45 Mixing Chemical

  46. 46 Treatment Near Completion

  47. 47 Non-Hazardous Waste Transported Off Site

  48. 48 Placing Fill in Excavation

  49. 49 Separation Fabric between Fill and CAP

  50. 50 Stockton Station Park

  51. 51 Questions?

  52. 52 THANK YOU Contact Information Name: Stuart Wiswall, P.G., LSRP Keating Environmental Management, Inc. Phone: 484-876-2197 E-mail: swiswall@kempartners.com

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend