Green Line Extension Project GLX Community Working Group Monthly Meeting 1 November 6, 2018 Agenda I. Safety & Introduction II. GLX-PMT Update III. GLX-C Construction & Design Update IV. Conclusion GLX Community Working Group


slide-1
SLIDE 1

1

GLX Community Working Group Monthly Meeting November 6, 2018

Green Line Extension Project

slide-2
SLIDE 2

2

GLX Community Working Group Monthly Meeting November 6, 2018

I. Safety & Introduction II. GLX-PMT Update

  • III. GLX-C – Construction & Design Update
  • IV. Conclusion

Agenda

slide-3
SLIDE 3

3

GLX Community Working Group Monthly Meeting November 6, 2018

GLX-MBTA Update

Terry McCarthy, MBTA

Safety & Introduction

slide-4
SLIDE 4

4

GLX Community Working Group Monthly Meeting November 6, 2018

General Update

  • GLX General Public Meeting – January 2019
  • CWG 2019 Meeting Schedule
  • Union Square Station Design Status
  • Latest Schedule for Bridge Closures
  • Ongoing Maintenance of Traffic/Bus Operations Planning
  • December 4, 2018, Holiday Gathering?
slide-5
SLIDE 5

5

GLX Community Working Group Monthly Meeting November 6, 2018

US2 Development

slide-6
SLIDE 6

6

GLX Community Working Group Monthly Meeting November 6, 2018

CWG Meeting Schedule 2019

Month/Day/Year Time

January 8, 2019 8:30 AM to 10:00 AM February 5, 2019 4:00 PM to 5:30 PM March 5, 2019 8:30 AM to 10:00 AM April 2, 2019 4:00 PM to 5:30 PM May 7, 2019 8:30 AM to 10:00 AM June 4, 2019 4:00 PM to 5:30 PM July 2, 2019 8:30 AM to 10:00 AM August 6, 2019 4:00 PM to 5:30 PM September 3, 2019 8:30 AM to 10:00 AM October 1, 2019 4:00 PM to 5:30 PM November 5, 2019 8:30 AM to 10:00 AM December 3, 2019 4:00 PM to 5:30 PM

slide-7
SLIDE 7

7

GLX Community Working Group Monthly Meeting November 6, 2018

  • SomerStreets Monster Mash Up Tabling Session On Somerville Ave.

– Sunday, Oct. 14 (between Union Square & Park Street)

Local Outreach

slide-8
SLIDE 8

8

GLX Community Working Group Monthly Meeting November 6, 2018

MBTA / GLX Regional Outreach

* Note: College Avenue Bridge traffic may be restricted at times but will remain open during construction.

slide-9
SLIDE 9

9

GLX Community Working Group Monthly Meeting November 6, 2018

MBTA / GLX Regional Outreach

  • Local Cites and State Delegation – Cut Through Traffic Issues
  • Reboot Your Commute
  • Public outreach within Essex, Suffolk, and Middlesex Counties
  • 96 Neighboring City/Town Municipalities
  • 84 Media Outlets
  • 29 Hospitals and Medical Facilities
  • 26 Colleges/Universities
  • In Process Chamber of Commerce and Large Employers Database
slide-10
SLIDE 10

10

GLX Community Working Group Monthly Meeting November 6, 2018

Mass DOT Highway Division - District 4

  • VMS Boards
  • HOC – Overhead Signs from NH Border
  • Apple & Google Database Updates – Detour

Information

  • Shared Outreach Efforts
  • Temporary Diverted Truck Traffic Efforts

MBTA / GLX Regional Outreach

slide-11
SLIDE 11

11

GLX Community Working Group Monthly Meeting November 6, 2018

MassDOT & Regional Coordination

  • Tobin Bridge ongoing Work
  • Chelsea Off Ramp Work Spring 2019
  • Alford St. Bridge Oct. 2018 – May 2019
  • North Washington St. Bridge – Spring 2019
  • Encore Casino Opening June 2019
slide-12
SLIDE 12

12

GLX Community Working Group Monthly Meeting November 6, 2018

GLX-C Construction Update

Jeff Wagner & Mike Shea

Safety & Introduction

slide-13
SLIDE 13

13

GLX Community Working Group Monthly Meeting November 6, 2018

Safety

– GLXC All Hands Safety Meeting on Oct. 30

Project Status

slide-14
SLIDE 14

14

GLX Community Working Group Monthly Meeting November 6, 2018

Safety

– Safety Recognition

Project Status

slide-15
SLIDE 15

15

GLX Community Working Group Monthly Meeting November 6, 2018

New Equipment for Safe, Less Disruptive Operations (Shea)

  • Lighting improvements

Project Status

slide-16
SLIDE 16

16

GLX Community Working Group Monthly Meeting November 6, 2018

New Equipment for Safe, Less Disruptive Operations

  • Backup alarm improvements

Project Status

slide-17
SLIDE 17

17

GLX Community Working Group Monthly Meeting November 6, 2018

New Products for Safe, Environmentally Friendly Operations

  • Environmentally friendly hydraulic fluid
  • DEF fluid promotes cleaner burning diesel engines
  • Improved noise curtains

Project Status

slide-18
SLIDE 18

18

GLX Community Working Group Monthly Meeting November 6, 2018

Staffing

– 225+ personnel including GLXC and subcontractor staff

Project Status

slide-19
SLIDE 19

19

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

Aerial Survey (Drone Flights)

  • Upcoming Corridor-wide Drone Flights
  • Aerial Survey to aid Design and Construction
  • Result will be Stitched-together Ortho-mosaic

Surface Model

  • Flights will be capturing Aerial Imagery
  • Flights non-capturing personal space /

property images, only rail corridor

slide-20
SLIDE 20

20

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Example of Drone Capabilities

Aerial Survey (Drone Flights)

slide-21
SLIDE 21

21

GLX Community Working Group Monthly Meeting November 6, 2018

Station Designs – College Ave. Station

Project Status

slide-22
SLIDE 22

22

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

  • College Ave. Station
slide-23
SLIDE 23

23

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

  • College Ave. Station
slide-24
SLIDE 24

24

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

  • College Ave. Station
slide-25
SLIDE 25

25

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

Drainage Package 11 (DP11)

  • DP 11 released for construction
  • 11 miles of new stormwater drainage will be added along the alignment
  • New system designed with 75+ year service life
  • Project will utilize existing stormwater drainage system
  • 4 main stormwater drainage tie ins to municipal systems: Cambridge, Somerville

& Medford (2)

slide-26
SLIDE 26

26

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

Drainage Line

slide-27
SLIDE 27

27

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Design

Drainage Line

slide-28
SLIDE 28

28

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Track Shift

  • 7,500’ track placed between Lowell and Washington St. (NH 2 Interim Track)
  • 3,000’ track between Walnut St. and Washington St. (NH 1)
  • 15,500 tons of ballast

Play Video IMG 2889

slide-29
SLIDE 29

29

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Track Shift

  • New Rail Line (Walnut St. to McGrath Hwy.)

April 2018 October 2018

slide-30
SLIDE 30

30

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Track Shift

  • New Rail Line (School St. looking north)

October 2018 April 2018

slide-31
SLIDE 31

31

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Walls

  • Wall removal along Gilman St. (between Walnut & McGrath Hwy.)
  • Construction fence will be installed
  • Drainage and retaining wall work to follow
slide-32
SLIDE 32

32

GLX Community Working Group Monthly Meeting November 6, 2018

Construction Support

  • Multi-Purpose Machine (MPM) coming to GLX project after use on project in

Ontario, Canada

  • Will be on GLX project for next 2 years

Project Status

slide-33
SLIDE 33

33

GLX Community Working Group Monthly Meeting November 6, 2018

Project Status

Trash Removal

  • With track shift trash removal will continue along east side of alignment
  • Additional trash removal on west side of alignment will not progress until 2020

because of fall protection and operating rail line safety requirements

slide-34
SLIDE 34

34

GLX Community Working Group Monthly Meeting November 6, 2018

Broadway Bridge Closure Update

Bridge Demolition & Construction

  • Now targeting start date of late February to Mid-March 2019 for bridge closure
  • 12 month demolition and construction schedule
slide-35
SLIDE 35

35

GLX Community Working Group Monthly Meeting November 6, 2018

Target Dates: Phase I Closure – April 2019 to November 2019 Phase II Closure – Spring to Fall 2020

Washington St. Bridge Update

slide-36
SLIDE 36

36

GLX Community Working Group Monthly Meeting November 6, 2018

Homans Building

– Targeting late November 2018 including environmental abatement & debris removal

Project Status

Demolition Update

3rd Avenue

– Targeting late November 2018 including environmental abatement & debris removal

Ball Square

– Targeting December for completion of abatement & demolition.

slide-37
SLIDE 37

37

GLX Community Working Group Monthly Meeting November 6, 2018

Discussion

Terry McCarthy, GLXC

slide-38
SLIDE 38

38

GLX Community Working Group Monthly Meeting November 6, 2018

Green Line Extension Project