GOLD PROJECT IN AFRICA 1 Forward-looking Disclaimer 2 2 - - PowerPoint PPT Presentation

| TSX-V: ORG DEVELOPING A LEADING GOLD PROJECT IN AFRICA 1 Forward-looking Disclaimer 2 2 Highlights 3 Corporate Overview 212M 16.6% 13M 15.3% $67M 10.6% 5.0% 6.1% 4 Management 5 Directors 6 About Sudan


slide-1
SLIDE 1

1

DEVELOPING A LEADING GOLD PROJECT IN AFRICA

| TSX-V: ORG

slide-2
SLIDE 2

2 2

Forward-looking Disclaimer

slide-3
SLIDE 3

3

Highlights

slide-4
SLIDE 4

4

Corporate Overview

212M 16.6% 13M 15.3% $67M 10.6% 5.0% 6.1%

slide-5
SLIDE 5

5

Management

slide-6
SLIDE 6

6

Directors

slide-7
SLIDE 7

7

About Sudan

Block 14 Gold Project

slide-8
SLIDE 8

8 8

Political Development in Sudan

slide-9
SLIDE 9

9

15%

CORPORATE TAX

7%

ROYALTIES

Gold Project

70% 10% 20% Block 14

slide-10
SLIDE 10

10

Concession 1,000Km2

Block 14

slide-11
SLIDE 11

11

Water Extraction Permit 980km2

  • Supports Mill

Throughput

6.0Mtpa

Permitted Water Source

slide-12
SLIDE 12

12

Resources & Reserves

Block 14 79.9 1.30 3,342 18.5 1.2 711 77.4 1.07 2,657 2.5 2.36 197

slide-13
SLIDE 13

13

0.3 136.8 0.94 1.40 4,133 6,137 40.3 0.8 1.4 1,007 1,76 6 0.4 113.2 1.06 1.50 3,868 5,451 30.3 0.9 1.4 896 1,395 0.5 94.6 1.18 1.60 3,603 4,864 23.4 1.1 1.5 797 1,123 0.6 79.9 1.30 1.70 3,342 4,358 18.5 1.2 1.6 711 936 0.7 67.7 1.42 1.80 3,088 3,913 14.9 1.3 1.6 636 789 0.8 57.7 1.53 1.90 2,847 3,519 12.2 1.5 1.7 571 677 0.9 49.3 1.65 2.00 2,619 3,169 10.1 1.6 1.8 512 584 1.0 42.3 1.77 2.10 2,405 2,853 8.4 1.7 1.9 461 508 1.1 36.4 1.88 2.20 2,204 2,570 7.1 1.8 1.9 415 444 1.2 31.4 2.00 2.29 2,017 2,315 6.0 1.9 2.0 375 390

Resources Estimate at Various Cut-Offs

slide-14
SLIDE 14

14

Feasibility Study Highlights

*For Details, Please See Feasibility Study Presentation on Orca’s Website

Block 14

slide-15
SLIDE 15

15

Au Price

Sensitivity Analysis

$1,200 $333 21.2 $1,250 $403 24.2 $1,350 $543 30.0 $1,450 $682 35.7 $1,550 $822 41.1 $1,650 $962 46.5 $1,750 $1,101 51.8 $1,850 $1,241 57.0

slide-16
SLIDE 16

16

Mine Site

slide-17
SLIDE 17

17 17

(9) (0.26) 237 6.94 15 0.44 311 9.12 59 1.72 6 0.18 88 2.57 707 20.69 72 2.11 5 0.14 783 22.94

Operating Costs

slide-18
SLIDE 18

18 EG2.2:3m at 8.73g/t

Liseiwi GSRC595: 24m at 3.89g/t GSRC596: 10m at 15.32g/t GSRC599: 8m at 12.80g/t

Wadi Doum Resource GSS Resource

Azurag: 20m at 1.53g/t

Priority Target

20km

Target

B14 Exploration Licence Extension Area 1,000km2

GSN: 20m at 9.90g/t

10km

Area 3A: 20m at 9.90g/t

Exploration Upside

slide-19
SLIDE 19

19

Investment Summary

slide-20
SLIDE 20

20

Appendix

slide-21
SLIDE 21

21

1.2 Moz inferred mineral resources at Koné deposit Poised to grow Drilling recommenced May 2020 C$8 Million in cash Well-capitalized significant treasury and quality shareholders Strong track record

  • f discovering mines that get built

4,243 km2 Portfolio of gold properties in Côte d’Ivoire is a new private West African-focused mineral exploration company formed by combining assets

  • f Orca Gold and Avant Minerals.
slide-22
SLIDE 22

22

GS GSS Main in & E & East t Zo Zones es

GSS Main & East Zones

slide-23
SLIDE 23

23

Resource Model for GSS

slide-24
SLIDE 24

24

High-Grade

Satellite Deposit: Wadi Doum

slide-25
SLIDE 25

25

Resource Model for Wadi Doum

slide-26
SLIDE 26

26

ORCAGOLD.COM