GEORGINA ISLAND Roads Upgrade and Drainage Project Presentation to - - PowerPoint PPT Presentation
GEORGINA ISLAND Roads Upgrade and Drainage Project Presentation to - - PowerPoint PPT Presentation
GEORGINA ISLAND Roads Upgrade and Drainage Project Presentation to The Community March 4, 2014 Introduction C.C. Tatham & Associates Ltd. (CCTA) retained by Georgina Island First Nation (GIFN) to provide professional engineering
2
Introduction
C.C. Tatham & Associates Ltd. (CCTA) retained by Georgina Island First Nation (GIFN) to provide professional engineering services for upgrading of approximately 10 km of roads;
Introduction
Project includes:
Assessment of existing roadway conditions;
Chief Joseph Snake Road, Loon Road, Bear Road and Root Road;
LVM Inc. providing geotechnical advice.
Sidewalk recommendations; Cost estimates; Drainage improvements; Life cycle analysis; Recommendations for cost effective reconstruction options;
3
Drainage Overview
Regrading and culvert replacement to provide uniform unobstructed ditches will improve surface drainage;
Chief Joseph Snake Road, Bear Road and Root Road
Drainage Review
Drainage outlets are blocked or missing, restricting flow;
Existing ditching is poorly defined, shallow and overgrown;
Drainage concerns between Chief Joseph Snake Road, Turtle Road and the lake related to low topography and maintenance needs;
Outlet improvement at campground on Bear Road.
4
Road Overview
5
Road Overview
Ditching exists only on southwest side, poorly defined and overgrown;
Loon Road
Install a French drain on northeast side to collect road surface runoff, discharging to southwest ditch;
Regrade southwest ditch to a uniform positive grade.
6
Geotechnical Evaluation
Thorough evaluation of current roadway conditions:
LVM Investigation
Roadway distresses;
Granular base/subbase/surface treatment depths;
Road structure materials.
Distresses related to:
Relatively flat road profiles;
Proximity to wetlands;
Undefined outlets and high lake levels relative to road ditches and road bases;
Existing road structure is shallow, substandard granular material;
Concluded existing pavements are well beyond their functional service lives and major rehabilitation is required.
7
Rehabilitation Options
Place 100 mm granular material over existing pavement (utilizing material
quarried on site if available);
Rehabilitation Method - Foamed Asphalt Stabilization
Pulverize granular material and existing road structure to depth of 225
mm;
Stabilize pavement surface with expanded (foamed) asphalt to depth of
150 mm;
Double layer surface treatment; Regrade all ditches and replace driveway
and road cross culverts.
8
Rehabilitation Options
Full depth excavation;
Other Rehabilitation Options and Lifecycle Analysis
Pulverize asphalt; Mechanical reinforcement. Considers initial capital cost plus 20 years of maintenance; Full depth reconstruction has highest capital cost and 2nd highest
maintenance cost with crack sealing and repaving in year 15;
Pulverizing has lowest capital cost and highest maintenance cost with
annual spray patching and surface treatment in years 8 and 16;
Foamed asphalt stabilization has 2nd lowest capital cost and lowest
maintenance cost with surface treatment in years 10 and 20;
Foamed asphalt stabilization is the most cost effective.
9
Cost Estimates
Foamed Asphalt Stabilization $ 5,560,000;
Construction Cost Estimates
Includes 10% contingency; Includes all drainage improvements within roadway; Assumes imported granular material, may be reduced by use of on-site
quarries;
Does not include sidewalk costs; Does not include outlet cleaning/improvements.
10
Sidewalk
Sidewalk
1.5 m widening of south bound lane of road; Low traffic volumes and speeds minimize safety concerns; Delineation of the walkway by line painting; Winter maintenance completed by existing snow removal equipment; Does not alter the established drainage patterns; Does not require work beyond the right-of-way; Estimated construction cost approximately $392,000.
11
Sidewalk
12
Summary
Foamed asphalt stabilization with double surface treatment;
Summary
Most cost effective rehabilitative method to provide adequate structural
capacity and meet functional service life expectations;
Rehabilitates existing road structure and minimizes placement of new
granulars, thereby reducing costs;
Double surface treatment for hard surfacing is a cost effective alternative
to hot mix asphalt and provides more flexibility during movement of the subgrade due to frost actions and spring thaw;
Existing granular quarry material may be suitable for this rehabilitation
method and result in further cost savings.
13
Next Steps
GIFN confirm preferred solution and construction schedule (2014/2015);
Next Steps
Liaison with agencies (MNR, DFO, LSRCA); Survey drainage outlets; Assess quality and quantity of island quarry material; Prepare final design and tender documents; Circulate to invited contractors for tendering; Contract award and construction.
14