generator interconnection procedures
play

Generator Interconnection Procedures Stephen Rutty Manager, Grid - PowerPoint PPT Presentation

Decision on Improvements to the Generator Interconnection Procedures Stephen Rutty Manager, Grid Assets Board of Governors Meeting General Session September 9, 2010 The ISO oversees the interconnection of generators to the transmission grid.


  1. Decision on Improvements to the Generator Interconnection Procedures Stephen Rutty Manager, Grid Assets Board of Governors Meeting General Session September 9, 2010

  2. The ISO oversees the interconnection of generators to the transmission grid.  ISO is required to ensure safe and reliable generator interconnections.  Currently two processes:  Small generator interconnection procedures (SGIP) 20 MW and less  119 active SGIP projects – 2,223.85 MW  Large generator interconnection procedures (LGIP) greater than 20 MW  179 active LGIP projects – 44,724.4 MW Slide 2

  3. The ISO experienced a recent surge in interconnection requests for small generators (20 MW or less). Annual ISO SGIP Interconnection Requests  The state’s renewable portfolio Projects per Year standard goals will continue to 100 drive dramatic increases 90 80  Same problems experienced with Number of Projects 70 the former serial LGIP process 60  Serial one at a time study process 50 overwhelmed and backlogged 40 30  Impacts of small and large projects 20 must be considered together 10 0 2007 2008 2009 2010 YTD Year Slide 3

  4. The ISO led a collaborative stakeholder process to explore issues and develop solutions. Solution Development Final proposal balances diverse Solution Refinement Issues Gathering stakeholder interests February March April May June July August September  Three in-person stakeholder meetings  Four in-person and fifteen teleconference volunteer working group meetings  Three rounds of stakeholder written comments Slide 4

  5. The primary issues identified through the process are addressed in the proposal.  Provides cost and timing certainty to interconnection customers;  Accommodates any number of requests in a scalable study process;  Considers interdependencies of small and large generator interconnection requests;  Provides options for qualified projects to be studied quickly; and  Provides small generators enhanced opportunities for deliverability assessment. Slide 5

  6. The proposal combines SGIP and LGIP into a unified generator interconnection procedure (GIP).  Annual cluster study track  Provides a shorter timeline than current LGIP and similar to SGIP  Approximately 420 calendar days  Network upgrades shared proportionately with cost certainty  Alternative independent study process track  Qualifying projects may apply any time of year  Approximately 240 calendar days  Project responsible for network upgrades  Modified fast track  Increased size from current 2MW to 5MW  Relaxed screening criteria Slide 6

  7. Key proposal elements: Current Procedures Proposed Element Combined GIP SGIP LGIP Study Process Serial Cluster Cluster   Deliverability Assessment Volumetric Per individual Tiered Study Deposit ($50K plus $1K per study estimates ($100K or $250K) MW capped at $250K) Financial Security At start of After each study After each study phase Postings construction phase Alternatives to Cluster Study  Independent Study Process Track   Fast Track Slide 7

  8. Stakeholders support major aspects of proposal but concerns remain. Issue ISO Response Study timelines still too long Proposal will allow a project to be studied more quickly than current serial process. Cost allocation Project upgrade costs are shared proportionately and equitably within a cluster and are capped. Independent study eligibility Proposal strikes the right balance without criteria undermining the benefits of the cluster approach. Data availability ISO committed to make information more available. No tariff change required to implement. PTO’s have committed to hold a stakeholder Wholesale Distribution Access Tariff (WDAT) impacts process for the WDAT. Slide 8

  9. Management recommends approval of the proposed generator interconnection procedures.  The proposed reforms provide:  A more effective and streamlined interconnection process for both small and large generation  Greater certainty on cost and schedule  Enhanced opportunities for small generators to have full deliverability  Proposal will enable more timely processing of interconnection requests to meet the state’s renewable portfolio standard goals. Slide 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend