Geary Bus Rapid Transit July 18, 2018 1 Geary corridor: looking - - PowerPoint PPT Presentation

geary bus rapid transit
SMART_READER_LITE
LIVE PREVIEW

Geary Bus Rapid Transit July 18, 2018 1 Geary corridor: looking - - PowerPoint PPT Presentation

Geary Bus Rapid Transit July 18, 2018 1 Geary corridor: looking east 2 The Geary corridor: 54,000 riders/day 3 Weve been busy making major improvements New low-floor buses More frequent service Safety enhancements Red lanes downtown 4


slide-1
SLIDE 1

1

Geary Bus Rapid Transit

July 18, 2018

slide-2
SLIDE 2

2

Geary corridor: looking east

slide-3
SLIDE 3

3

The Geary corridor: 54,000 riders/day

slide-4
SLIDE 4

4

We’ve been busy making major improvements

New low-floor buses Safety enhancements More frequent service Red lanes downtown

slide-5
SLIDE 5

5

And our customers are noticing

“38 bus improved immensely within the last 3 years” “Thank you for the bus lanes!”

I like the new buses. They have more room and are cleaner.

“I like the new buses. They have more room and are cleaner.”

slide-6
SLIDE 6

6

But, more is needed

High ridership is a blessing and a curse

  • More frequent service  harder

to prevent bus bunching

  • Geary riders sometimes still

experience crowded buses, uneven wait times and inconsistent travel times SF’s longest High-Injury Corridor

  • Geary travelers are eight times

more likely to be hit by traffic than the city average

slide-7
SLIDE 7

7

Major project features

Dedicated bus lanes Better bus stops Smarter traffic signals New signals + crosswalks Calming the “expressway” Pedestrian bulbs, median refuges

slide-8
SLIDE 8

8

Alternatives Evaluated

slide-9
SLIDE 9

9

Bus-Only Lane Configuration (Hybrid Alternative, as amended by SFCTA Board)

slide-10
SLIDE 10

10

Example: O’Farrell at Leavenworth - Before

slide-11
SLIDE 11

11

Example: O’Farrell at Leavenworth - After

Dedicated bus lanes Better bus stops

slide-12
SLIDE 12

12

Example: Geary at Buchanan - Before

slide-13
SLIDE 13

13

Example: Geary at Buchanan - After

Calming the “expressway” Pedestrian bulbs, median refuges New signals + crosswalks Dedicated bus lanes

slide-14
SLIDE 14

14

Example: Geary at 17th Ave - Before

slide-15
SLIDE 15

15

Example: Geary at 17th Ave - After

Dedicated bus lanes New signals + crosswalks

Pedestrian bulbs, median refuges

slide-16
SLIDE 16

16

Extensive outreach process

  • 4 major rounds of outreach
  • Public meetings
  • 250+ meetings w/ 65+

stakeholder groups

  • 33 Citizens Advisory

Committee meetings

  • Multi-lingual

communications

  • Corridor surveys
  • OWL Visualization kiosks
  • Flyering at bus stops
  • Web, email, social media

updates

  • Newspaper ads
  • Corridor postings
  • Ambassadors at bus stops
slide-17
SLIDE 17

17

We Heard You!

Changes made between Draft EIR/EIS and Final EIR 1 - Retention of Local and Express bus stops at Spruce/Cook (No Rapid stop) 2 - Retention of the Webster Street pedestrian bridge 3 - Addition of more pedestrian crossing improvements Changes made at SFCTA Board Meeting on January 5, 2017 4 - Retention of Collins Street local bus stops 5 - Retention of Laguna Street Rapid bus stops Changes made at SFCTA Board meeting on June 27, 2017 6 - Shift in WB transition from center-running to side-running from 27th to 28th Avenue

1 2 4 5 6

slide-18
SLIDE 18

18

Environmental Review Timeline

  • November 2008: Scoping
  • October/November 2015: Draft EIR/EIS
  • December 2016: Release of Final EIR
  • January 2017: SFCTA certify EIR and adopt

LPA

  • June 2017: SFCTA LPA Amendment
  • Today: SFMTA Board CEQA findings and

LPA approval

  • Later 2017: Final EIS and Record of Decision
slide-19
SLIDE 19

19

Project Phasing and Next Steps

Phase 2 Phase 1

Complete federal environmental process. Following completion, immediate next steps:

– Phase 1: Outreach on design details, then SFMTA Board legislation – Phase 2: Kick-off preliminary engineering

slide-20
SLIDE 20

20

Cost estimate

Cost Notes Phase 1 – fully funded $65 million

  • Includes coordinated utility upgrades

not related to BRT Phase 2 – will seek $100 million Small Starts grant. $235 million

  • Center-running bus only lanes
  • High amenity stations
  • Bus and ped bulbs, stops, and signals
  • Vehicles for increased service
  • Utility relocation related to BRT
  • Mixed flow lane re-surfacing
  • Masonic area bike lane and median

modifications Total $300 million

slide-21
SLIDE 21

21

Actions Requested

  • 1. Approve the Geary Bus Rapid Transit Project
  • 2. Adopt CEQA findings, including
  • Statement of Overriding Considerations
  • Mitigation, Monitoring and Reporting Program
  • 3. Concur with designation of Locally Preferred

Alternative

  • 4. Authorizing Director of Transportation to

continue to obtain otherwise necessary approvals and carry out the actions to implement Geary BRT Project