FY2018 RESULTS BRIEFING We respect, care and deliver ZIMPLATS - - PowerPoint PPT Presentation

fy2018 results briefing
SMART_READER_LITE
LIVE PREVIEW

FY2018 RESULTS BRIEFING We respect, care and deliver ZIMPLATS - - PowerPoint PPT Presentation

FY2018 RESULTS BRIEFING We respect, care and deliver ZIMPLATS LOCATION AND OPERATIONS We respect, care and deliver AT A GLANCE 0 Fatalities 271 000 Pt Oz Produced 2018 US$3 million US$166 million Profit before tax Profit after tax 3


slide-1
SLIDE 1

We respect, care and deliver

FY2018 RESULTS BRIEFING

slide-2
SLIDE 2

We respect, care and deliver

ZIMPLATS LOCATION AND OPERATIONS

slide-3
SLIDE 3

We respect, care and deliver

AT A GLANCE…

2018

3

0 Fatalities

US$3million

Profit after tax

271 000

Pt Oz Produced

US$166million

Profit before tax

slide-4
SLIDE 4

We respect, care and deliver

SUMMARY OF RESULTS

4

8.8 million Fatality free shifts ROM Tonnes 6 801 000 Tonnes Milled 6 570 000 Pt 271 000 Oz Head Grade 3.24 g/t 14% Revenue US$582.5m (5%) Operating cost US$1 290/ Pt oz. 64% Profit before tax US$166m Tax expense US$163.3m 248% Cash generated US$195m

Nameplate 6 200 000

slide-5
SLIDE 5

We respect, care and deliver

REVENUE CONTRIBUTION BY METAL 2009 TO 2018

5

Platinum 55% Palladium 19% Gold 7% Rhodium 4% Nickel 11% Other 4%

2012 2012

Platinum 49% Palladium 27% Gold 6% Rhodium 4% Nickel 10% Other 4%

2015 2015

Platinum 38% Palladium 35% Gold 6% Rhodium 7% Nickel 9% Other 5%

2018 2018

Platinum 68% Palladium 11% Gold 7% Nickel 12% Other 2%

2009 2009

slide-6
SLIDE 6

We respect, care and deliver

DEPRESSED PLATINUM PRICES

6

200 400 600 800 1 000 1 200 1 400 1 600 1 800 US$/oz

Platinum

200 400 600 800 1 000 US$/oz

Palladium

300 600 900 1 200 1 500 1 800

US$/oz

Gold

5 000 10 000 15 000 20 000 25 000 30 000 US$/ton

Nickel

slide-7
SLIDE 7

We respect, care and deliver

OPERATIONS

7

slide-8
SLIDE 8

We respect, care and deliver Fatality-free shifts 8.8 million Lost-time injuries 3 Total injuries 8 Fatal injury frequency rate Lost-time injury frequency rate 0.19 Total injury frequency rate 0.52

ZERO HARM

SAFETY SUMMARY

8

slide-9
SLIDE 9

We respect, care and deliver

OUR SAFETY JOURNEY

9 154 84 43 38 43 38 20 18 14 6 8 11 20 19 17 10 19 11 12 8 3 3 20 40 60 80 100 120 140 160 180 FY08 FY09 FY10 FY11 FY12 FY13 FY14 FY15 FY16 FY17 FY18 TI LTIs

TI – Total injuries LTI – Lost time injuries

365 days LTI free

slide-10
SLIDE 10

We respect, care and deliver

ENVIRONMENTAL PERFORMANCE

10

Zero Major environmental non- conformances Ongoing water recycling programmes for production 2% reduction in amount of water extracted from dams and underground Ongoing programmes to manage fresh water consumption Progressive land rehabilitation programmes in place

slide-11
SLIDE 11

We respect, care and deliver

METAL PRODUCTION

Ngezi Concentrator

Metal FY2018 FY2017 Variance Platinum (oz) 271 000 281 000 (4%) Palladium (oz) 223 000 233 000 (4%) Gold (oz) 29 000 29 000

  • Rhodium (oz)

24 000 25 000 (4%) Ruthenium (oz) 21 000 22 000 (5%) Iridium (oz) 10 000 11 000 (9%) Silver (oz) 50 000 48 000 4% Nickel (t) 5 000 5 000

  • Copper (t)

4 000 4 000

  • Cobalt (t)

87 67 30%

11

slide-12
SLIDE 12

We respect, care and deliver

FINANCIALS

12

slide-13
SLIDE 13

We respect, care and deliver

CASH UTILISATION FY2002 – FY2018 (US$6 BILLION)

13

US$1.6 billion US$2.5 billion

slide-14
SLIDE 14

We respect, care and deliver

CASH UTILISATION FY2018 (US$627 MILLION)

14

slide-15
SLIDE 15

We respect, care and deliver

ABRIDGED INCOME STATEMENT

15

Sales revenue

  • Metal prices

Gross profit

  • Revenue

Profit before tax

  • Higher gross

profit

Taxation

  • Change in rate

to 25.75%

  • Higher profits

2018 2017 Variance US$ millions % Revenue 583 513 14 Cost of sales ( 368) ( 366) 1 Gross profit 215 146 47 Profit before tax 166 101 64 Taxation ( 163) ( 55) (196) Current income tax ( 65) ( 51) ( 27) Corporate tax: ( 20) ( 10) ( 50) Additional profits tax: ( 43) ( 40) ( 8) Withholding tax ( 2) ( 1) ( 50) Deferred income tax ( 98) ( 5) ( 1 860) Profit after tax 3 46 ( 93) Cash operating cost per Pt oz (US$) 1 290 1 226 (5) Gross revenue per 4E oz (US$) 1 075 922 17 Gross margin (%) 37 28 9

slide-16
SLIDE 16

We respect, care and deliver

CONTRIBUTION TO THE FISCUS

16

15 53 42 96 113 97 47 62 86 131 20 40 60 80 100 120 140 FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018 CONTRIBUTION TO THE FISCUS (US$M)

slide-17
SLIDE 17

We respect, care and deliver

CAPITAL PROJECTS

17

MUPANI MINE DEVELOPMENT

slide-18
SLIDE 18

We respect, care and deliver

CAPITAL PROJECTS

BIMHA MINE REDEVELOPMENT

  • US$101m project

budget

  • US$29.9m spent

in FY2018

  • Attained design

capacity in April 2018

  • US$66.2m -

project expenditure to date MUPANI MINE DEVELOPMENT

  • US$264m project

budget

  • US$28.7m spent

in FY2018

  • US$37.8m -

project expenditure to date STAY IN BUSINESS CAPITAL

  • US$31.2 million

spent on replacement of trackless mining machinery (TMM) in FY2018.

  • US$46.2 million

spent on routine stay-in-business capital projects

18

US$136 million spent on capital projects

slide-19
SLIDE 19

We respect, care and deliver Total Headcount 6 500 Employee Housing Strategy in place

OUR PEOPLE

19

slide-20
SLIDE 20

We respect, care and deliver

EMPLOYEE WELLNESS

20

HIV/AIDS

  • HIV/AIDS

programmes continue to run for staff, their families and the community. MENTAL HEALTH

  • Mental health

programme now in its second year NCDs

  • Continued focus on

NCDs management Occupational Health

  • Occupational health

programmes in place and running effectively

slide-21
SLIDE 21

We respect, care and deliver

COMMITTED TO CREATING SHARED VALUE

HEALTH SPORTS DEVELOPMENT COMMUNITY PROJECT ON ALBINISM LIVESTOCK REVITALISATION EDUCATION

US$6 million

Invested in community development projects in FY2018

PICTURE: CHITSUWA DAM

slide-22
SLIDE 22

We respect, care and deliver

BEFORE

KADOMA GENERAL HOSPITAL REHABILITATION PROJECT

22

DILAPIDATED KITCHEN EQUIPMENT DILAPIDATED LAUNDRY EQUIPMENT POOR WATER RETICULATION

slide-23
SLIDE 23

We respect, care and deliver

AFTER

23

FACILITIES FACELIFT NEW LAUNDRY BLOCK CONSTRUCTED NEW KITCHEN EQUIPMENT NEW LAUNDRY EQUIPMENT

KADOMA GENERAL HOSPITAL REHABILITATION PROJECT

slide-24
SLIDE 24

We respect, care and deliver

COMMUNITY PROJECT ON ALBINISM

24

Campaign launched in partnership with:

  • Ministry of Labour and Social Welfare
  • Ministry of Health and Child Care
  • Friends with Albinism

Key project objectives

  • Awareness raising
  • Promotion of integration
  • Facilitation of distribution of sun protection

materials ( lotions, lip balm, hats) Major project achievements:

  • Effective national awareness campaign
  • Skin cancer screening and treatment
  • Provision of eye tests and spectacles
  • Distribution of sun protection materials (

approximately 1000 beneficiaries)

slide-25
SLIDE 25

We respect, care and deliver

COMMERCIAL LIVESTOCK PROJECTS

25

2017

  • 16 Bonsmara and Tuli

bulls donated to the community for herd improvement.

  • 64 Bucks donated to

the community for improved herd genetics

  • Construction and

rehabilitation of dip tanks 2018

  • 96 project offspring to

date – 47 heifers and 49 bulls

  • Improved animal

health and nutrition

  • Launch of Livestock

Revitalisation ( AI) project in partnership with Zimbabwe Agricultural Society.

  • 200 cattle

inseminated to date in Mat. South

slide-26
SLIDE 26

We respect, care and deliver

DEVELOPING SPORT IN THE COMMUNITY

26

slide-27
SLIDE 27

We respect, care and deliver

PROTECTING OUR COMMUNITY

27

ZRP TURF POLICE STATION CONSTRUCTED BY ZIMPLATS 11KM FENCE ERECTED BY ZIMPLATS ALONG NGEZI SELOUS HIGHWAY

slide-28
SLIDE 28

We respect, care and deliver

EMPOWERMENT

28

Indigenisation Enterprise Development

  • The local enterprises ( LEDs) supply engineering and

technical solutions, protective clothing (work suits and

  • veralls), silica and bricks
  • LEDs turnover for FY2018 - US$43m
  • Employee Share Ownership Trust transaction concluded

in January 2017

  • Zimplats Mhondoro-Ngezi Chegutu Zvimba Community

Share Ownership Trust 10% equity being processed

Local Supplier Development

  • Zimplats continued with its strategy of local supplier

development - 69% of total spend in FY2018

slide-29
SLIDE 29

We respect, care and deliver

LOCAL PROCUREMENT AND SUPPLIER DEVELOPMENT

29 0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

  • 50

100 150 200 250

FY2009 FY2010 FY2011 FY2012 FY2013 FY2014 FY2015 FY2016 FY2017 FY2018

PROPORTION OF LOCAL SPEND EXPENDITURE ($M) Local spend Local spend % of total spend

slide-30
SLIDE 30

We respect, care and deliver

DEVELOPING LOCAL SUPPLIERS

  • TOOL FOR ECONOMIC RECOVERY

Import substitution initiatives

 Partnership to establish a bulk emulsion plant – AEL Zimbabwe  Partnership to set up mine roof support – Grindale Engineering

30

slide-31
SLIDE 31

We respect, care and deliver

LOCAL ENTERPRISE DEVELOPMENT

TELSTONE TRADING

slide-32
SLIDE 32

We respect, care and deliver

LOOKING AHEAD

32

  • 1. Business optimisation
  • Achieving production

volumes

  • Containing costs
  • Preservation of cash

resources

  • Maintaining sustainable

business practices

  • Expansion, diversification

and strategic joint ventures

  • 2. Plans to reline and

improve the existing furnace to improve furnace safety

  • 3. Continued investment in

community projects

  • 4. Support government

efforts and engage them on a multi-stakeholder approach to the national beneficiation facility