fy 2019 fy 2020 capital budget approval
play

FY 2019 & FY 2020 Capital Budget Approval May 14, 2018 CPC - PowerPoint PPT Presentation

FY 2019 & FY 2020 Capital Budget Approval May 14, 2018 CPC AGENDA General Fund Dept Capital Budget 2 Action Item : Approve the FY19 & FY20 Proposed Capital Budget for recommendation to the Board of Supervisors Admin Code Section


  1. FY 2019 & FY 2020 Capital Budget Approval May 14, 2018

  2. CPC AGENDA General Fund Dept Capital Budget 2  Action Item : Approve the FY19 & FY20 Proposed Capital Budget for recommendation to the Board of Supervisors  Admin Code Section 3.21: CPC reviews the Capital Budget to ensure it aligns with recommendations in Capital Plan

  3. CAPITAL BUDGET FY19 & FY20: Funded & Unfunded Projects 3 SEE BUDGET HANDOUTS

  4. CAPITAL BUDGET Proposed Budget Highlights 4  Record Level of GF commitment proposed to help address City’s significant capital priorities and backlog  2-Year General Fund Investment: $306.5M  $148.9M funded in FY19 and $157.6M funded in FY20  2-Year Other Sources Investment: $226.4M  TOTAL 2-Year Proposed Investment: $533.0M

  5. CAPITAL BUDGET Jefferson Streetscape Phase II 5 As of the last budget presentation on 4/30, City stakeholders were developing a funding proposal for  Phase II of the Jefferson Streetscape project. The proposed funding for this project is shown below. FY19 Dept Funding Source As presented Contribution to Revised on 4/30 Jefferson St. DPW SB1 Local Partnership Competitive Program Grant - 6.8 - MTA - 2.0 - CTA - 1.4 - PRT - 0.3 - DPW Increased RMRA projection - 1.5 - DPW Stair and Wall Replacement Program 2.7 0.2 2.5 DPW Towable Generators 0.2 0.2 - DPW Infill Sidewalks 0.3 0.3 - DPW Operations Yard Improvements 0.3 0.1 0.2 DPW UN Plaza 1.2 0.6 0.6 DPW Earthquake Evaluations 0.2 0.2 - TOTAL 13.6 FY19 GF bottom-line increases to $148.9M as a result of additional RMRA funding 

  6. CAPITAL BUDGET Other changes since 4/30 6 FY19 FY20 As As Dept Project presented Change Revised presented Change Revised on 4/30 on 4/30 CPP Capital Projects Contingency 1.3 (0.2) 1.1 1.7 (0.1) 1.6 DPW Street Structure Repair Program 2.7 0.2 2.9 DPW Infill Sidewalks 0.3 (0.3) - Shown on previous slide DPW UN Plaza - 0.3 0.3 DPW Earthquake Evaluations 0.2 (0.2) - DPW General Capital (Facilities Maintenance) 0.4 0.1 0.5 0.4 0.1 0.5 WAR Davies Elevator - 0.4 0.4 - - - WAR Opera House Elevator 0.2 (0.2) - - - - WAR Opera House Roof Replacement 0.5 (0.1) 0.4 4.1 0.1 4.2 WAR Facilities Maintenance 0.5 - 0.5 0.5 (0.1) 0.4 TOTAL - - No net change to GF bottom-line 

  7. CAPITAL BUDGET FY19 & FY20 Proposed Capital Budget Overview 7 2-Year $ in millions FY19 Budget FY20 Budget Request Total General Other General Other General Other 2-Year 2 –Year Expenditure Category Fund Sources Fund Sources Fund Sources GF Total TOTAL ADA: Facilities 3.7 0.2 1.7 0.0 2.0 0.2 3.7 3.9 ADA: Public Right of Way 21.1 0.0 7.8 0.0 8.0 0.0 15.8 15.8 Critical Enhancement 126.2 145.4 25.0 114.1 32.6 31.3 57.7 203.1 Facility Renewal 280.5 25.7 36.6 17.4 35.8 8.2 72.4 98.1 Street Resurfacing 102.6 12.2 46.4 7.4 50.7 4.8 97.1 109.3 Streets and ROW Renewal 20.7 18.7 11.0 16.6 7.0 2.1 18.1 36.8 Routine Maintenance 27.2 1.7 13.0 1.3 13.4 0.3 26.4 28.0 Other 12.9 3.0 6.6 3.0 7.1 0.0 13.7 16.7 Critical Project Development 52.5 19.6 0.8 11.4 0.9 8.2 1.7 21.3 TOTAL 647.5 226.4 148.9 171.2 157.6 55.2 306.5 533.0 Proposed FY19 and FY20 Capital Budget corresponds to high scenario as presented on 4/30 (with an  additional $1.5M of RMRA funding)

  8. CAPITAL BUDGET Proposed Budget Overview – ALL FUNDING SOURCES 8 FY19 Proposed Budget FY20 Proposed Budget (Total = $320.1M) (Total = $212.8M)

  9. CAPITAL BUDGET Non-General Capital Funding Sources 9 2-Year Funding Source Dept Receiving Funds FY19 FY20 Total Capital Planning Fund DEM, DPH, FIR, POL, PRT, REC, SHF 12.7 8.2 20.9 IPIC ART, DPW, GSA, MTA, REC 59.7 14.7 74.4 Developer Funded DPW 0.5 1.0 1.5 State / Federal DPW, REC 32.5 6.9 39.4 Other DPW, GSA 5.7 5.7 Library Preservation Fund LIB 23.5 15.1 38.7 OCII Revenue PRT 9.8 9.8 Bond Revenue REC 0.6 0.6 Golf Fund REC 0.4 0.4 0.7 Marina Fund REC 3.2 2.2 5.4 Open Space Fund REC 22.7 6.7 29.4 TOTAL 171.2 55.2 226.4 • $ in millions

  10. CAPITAL BUDGET Proposed Budget Overview – GF ONLY 10 FY19 Proposed Budget FY20 Proposed Budget (Total = $148.9M) (Total = $157.6M)

  11. CAPITAL BUDGET Expenditure by Dept – FY19 GF ONLY 11 Critical ADA: ADA: Public Critical Facility Street ROW Routine DEPT Other Project TOTAL Facilities Right of Way Enhancement Renewal Resurfacing Renewal Maintenance Development AAM 0.5 0.6 0.3 1.4 0.3 0.9 0.2 1.4 ART CPP 1.2 0.6 1.8 1.8 1.8 DEM DPH 3.2 4.5 3.4 11.1 7.8 4.7 0.5 46.4 11.0 4.1 4.8 0.3 79.5 DPW DT 3.9 0.8 4.6 2.2 0.2 2.4 FAM FIR 1.2 1.2 2.4 8.0 5.8 0.6 14.4 GSA HSA 0.8 0.8 JUV 0.4 0.0 0.4 0.8 LIB MOD 1.2 1.2 MTA PLN 0.1 1.0 0.2 1.2 POL PRT 0.5 1.7 11.3 1.0 0.5 15.1 REC SCI 0.7 0.3 0.1 1.1 0.6 5.3 0.6 6.5 SHF WAR 1.0 0.5 1.5 1.7 7.8 25.0 36.6 46.4 11.0 12.9 6.6 0.8 148.9 TOTAL

  12. CAPITAL BUDGET Expenditure by Dept – FY20 GF ONLY 12 Critical ADA: ADA: Public Critical Facility Street ROW Routine DEPT Other Project TOTAL Facilities Right of Way Enhancement Renewal Resurfacing Renewal Maintenance Development AAM 0.5 0.1 0.3 0.9 0.8 0.6 0.2 1.6 ART CPP 1.6 0.6 2.2 DEM DPH 1.0 4.9 3.5 9.3 8.0 0.8 1.1 50.7 7.0 4.3 5.0 0.3 77.2 DPW DT 0.5 0.8 1.3 0.0 2.6 0.2 2.8 FAM FIR 2.3 1.2 3.6 25.7 6.9 0.6 33.2 GSA HSA 0.2 0.2 JUV 0.2 0.5 0.7 LIB MOD 1.3 1.3 MTA PLN 0.1 0.2 0.2 0.4 POL PRT 0.5 3.4 9.7 1.0 0.5 15.0 REC SCI 0.4 0.3 0.7 1.8 0.6 2.4 SHF WAR 0.3 4.2 0.4 4.9 2.0 8.0 32.6 35.8 50.7 7.0 13.4 7.1 0.9 157.6 TOTAL

  13. CAPITAL BUDGET Recent vs. Proposed funding levels – GF ONLY 13 Proposed 2-Year Capital Budget FY14 FY15 FY16 FY17 FY18 FY19 FY20 Expenditure Category Budget Budget Budget Budget Budget Proposed Proposed ADA: Facilities 7.4 4.0 2.3 3.2 1.7 2.0 5.4 ADA: Public Right-of-Way 2.5 5.6 5.5 5.8 7.8 8.0 6.4 Critical Project Dev* 12.9 11.0 0.8 0.9 Facility Renewal 12.0 15.0 23.6 27.0 36.4 36.6 35.8 Routine Maintenance 14.6 10.7 10.8 11.6 12.8 12.9 13.4 ROW Infrastructure Renewal 1.4 5.9 7.6 13.4 14.8 11.0 7.0 Street Resurfacing 41.5 47.0 48.5 43.1 46.4 50.7 Critical Enhancements/Other 30.9 18.0 20.6 29.9 26.4 31.6 39.7 TOTAL 81.7 114.1 119.1 138.1 142.4 148.9 157.6 $ in millions, excludes non-General Fund sources *Critical Project Development has been funded by the revolving Capital Planning Fund from FY16 onwards

  14. Questions & Comments 14 onesanfrancisco.org

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend