Future Network Requirements Presenters : Mahesh Narotam, Manager - - PowerPoint PPT Presentation

future network requirements
SMART_READER_LITE
LIVE PREVIEW

Future Network Requirements Presenters : Mahesh Narotam, Manager - - PowerPoint PPT Presentation

Future Network Requirements Presenters : Mahesh Narotam, Manager Portfolio Planning and Optimisation Daniel Andersen, Manager Network Strategy Roslyn Stewart, Senior Portfolio Planning Engineer May 2017 Agenda Background


slide-1
SLIDE 1

Future Network Requirements

May 2017

Presenters:

  • Mahesh Narotam, Manager Portfolio Planning

and Optimisation

  • Daniel Andersen, Manager Network Strategy
  • Roslyn Stewart, Senior Portfolio Planning

Engineer

slide-2
SLIDE 2
  • Background
  • Central Queensland to South Queensland Area
  • North Queensland Area
  • Gold Coast Area
  • Questions

Agenda

slide-3
SLIDE 3

Disclaimer

  • The views outlined in the presentation are

Powerlink’s best view at the time of publication and may be subject to change.

  • While care has been taken to prepare and

provide this information in good faith, Powerlink accepts no responsibility for liability

  • r loss or damage that may be incurred by

persons acting in reliance on this information

  • r assumptions drawn from it.
slide-4
SLIDE 4

Previous feedback received

Powerlink presented the Non-Network Feasibility Study process at the 2016 Transmission Annual Planning (TAPR) Forum. Feedback was received that non-network providers are keen to:

  • Engage and understand Powerlink’s future

requirements (noting it is an iterative two- way learning process)

  • Receive information in a timely manner to

assist with the assessment of potential solutions.

slide-5
SLIDE 5

Current operating environment

Powerlink

Consumer response Emerging technologies Economic

  • utlook

Electricity demand

slide-6
SLIDE 6

Webinar purpose

  • Given these complexities in the external

environment, Powerlink acknowledges the importance of engaging early on with our stakeholders

  • Non-network solutions are a proven and

effective method of managing uncertainty, providing flexibility and improving network utilisation

  • Assists with achieving the right balance

between reliability and cost.

slide-7
SLIDE 7

Avenues for engagement

  • Formal consultation as defined under the

National Electricity Rules (NER):

– Transmission Annual Planning Report (TAPR) – Regulatory Investment Test for Transmission (RIT-T)

  • Powerlink’s Non-Network Feasibility Study

process

  • Forums and webinars
  • Non-Network Engagement Stakeholder Register

(NNESR)

  • Email NetworkAssessments@powerlink.com.au.
slide-8
SLIDE 8
  • Central Queensland to South Queensland Area

(Daniel Anderson)

  • North Queensland Area (Roslyn Stewart)
  • Gold Coast Area (Roslyn Stewart)

Focus areas

slide-9
SLIDE 9

Central Queensland to South Queensland Area

slide-10
SLIDE 10

Central Queensland to South Queensland Area

Description and characteristics

  • The 275kV corridor between Calliope

River (Gladstone) and South Pine (Brisbane) was progressively developed as single circuit feeders in the 1970s and 1980s.

  • Provides an important connection

between generation in the Gladstone region and the load centres in South Queensland, as well as interconnection to NSW.

Calliope River Wurdong Gin Gin Teebar Creek Woolooga Palmwoods South Pine Calvale Larcom Creek Boyne Island Bouldercombe Tarong Rocklea Mt England Blackwall Legend

275kV Transmission line 275kV Substation

Teebar Creek Woolooga Gin Gin Palmwoods South Pine Mt England Blackwall Rocklea Wurdong Calvale Bouldercombe Boyne Island Calliope River Larcom Creek Legend

275kV transmission line 275kV substation

Tarong

slide-11
SLIDE 11

Central Queensland to South Queensland Area

Description and characteristics

  • With varying distances from the ocean,

and localised industrial pollution, these transmission lines are subject to different environmental and atmospheric conditions.

  • Over time, they have experienced

structural degradation at different rates.

Calliope River Wurdong Gin Gin Teebar Creek Woolooga Palmwoods South Pine Calvale Larcom Creek Boyne Island Bouldercombe Tarong Rocklea Mt England Blackwall Legend

275kV Transmission line 275kV Substation

Teebar Creek Woolooga Gin Gin Palmwoods South Pine Mt England Blackwall Rocklea Wurdong Calvale Bouldercombe Boyne Island Calliope River Larcom Creek Legend

275kV transmission line 275kV substation

Tarong

slide-12
SLIDE 12

Central Queensland to South Queensland Area

Description and characteristics

  • The interconnector’s transfer capability

is highly dependent on the location of generation.

Calliope River Wurdong Gin Gin Teebar Creek Woolooga Palmwoods South Pine Calvale Larcom Creek Boyne Island Bouldercombe Tarong Rocklea Mt England Blackwall Legend

275kV Transmission line 275kV Substation

Teebar Creek Woolooga Gin Gin Palmwoods South Pine Mt England Blackwall Rocklea Wurdong Calvale Bouldercombe Boyne Island Calliope River Larcom Creek Legend

275kV transmission line 275kV substation

Tarong

slide-13
SLIDE 13

Central Queensland to South Queensland Area

Description and characteristics

  • Future changes in generation and load

profiles will impact the transfer capability requirements from Central to Southern Queensland.

  • In its current form, the intraconnector
  • ffers a great deal of flexibility for

possible generation dispatches, seldom imposing any constraints to market

  • peration.

Calliope River Wurdong Gin Gin Teebar Creek Woolooga Palmwoods South Pine Calvale Larcom Creek Boyne Island Bouldercombe Tarong Rocklea Mt England Blackwall Legend

275kV Transmission line 275kV Substation

Teebar Creek Woolooga Gin Gin Palmwoods South Pine Mt England Blackwall Rocklea Wurdong Calvale Bouldercombe Boyne Island Calliope River Larcom Creek Legend

275kV transmission line 275kV substation

Tarong

slide-14
SLIDE 14

Central Queensland to South Queensland Area

Description and characteristics

  • In October 2015, Powerlink engaged

with relevant stakeholders to broaden input and gain feedback on future reinvestment of the CQ-SQ intraconnector.

  • Feedback indicated that Powerlink

adopt an incremental approach to reinvestment such that future alternative options were not eliminated.

Calliope River Wurdong Gin Gin Teebar Creek Woolooga Palmwoods South Pine Calvale Larcom Creek Boyne Island Bouldercombe Tarong Rocklea Mt England Blackwall Legend

275kV Transmission line 275kV Substation

Teebar Creek Woolooga Gin Gin Palmwoods South Pine Mt England Blackwall Rocklea Wurdong Calvale Bouldercombe Boyne Island Calliope River Larcom Creek Legend

275kV transmission line 275kV substation

Tarong

slide-15
SLIDE 15

Central Queensland to South Queensland Area

Future requirements

  • The current reinvestment strategy looks

to balance economic cost whilst preserving a transfer capability that delivers appropriate market benefits.

  • A number of transmission lines will

reach their end of life over the next five to 20 years.

Transmission Line Estimated Reinvestment Period (years)

Palmwoods to South Pine 5-10 Calliope River to Gin Gin 5-10 Calliope River to Wurdong Tee 10-20 Wurdong Tee to Gin Gin 10-20 Gin Gin to Woolooga 10-20 Gin Gin to Teebar Creek 10-20 Teebar Creek to Woolooga 10-20

slide-16
SLIDE 16

North Queensland Area

slide-17
SLIDE 17

275kV & 132kV Transmission Corridor

slide-18
SLIDE 18

NQ Transmission Corridor Network Development

1960s

  • 132kV circuit
  • Collinsville Power Station to Townsville.

Townsville South Clare Collinsville

Clare Collinsville

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend

132kV transmission line 132kV substation

Townsville South

slide-19
SLIDE 19

NQ Transmission Corridor Network Development

1980s

  • 275kV single circuit transmission lines

established between Collinsville and Ross

  • Ross 275/132kV Substation established

with one transformer initially (there are now three).

Ross Townsville South Clare Strathmore Collinsville

Clare Collinsville

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend Strathmore Townsville South

132kV transmission line 132kV substation 275kV transmission line 275kV substation

slide-20
SLIDE 20

NQ Transmission Corridor Network Development

2000 onwards

275kV supply into NQ upgraded

  • New double circuit transmission line

from Strathmore to Ross

  • Two existing single circuit transmission

lines from Strathmore to Ross are paralleled for higher capacity

  • Strathmore 275/132kV Substation

established with one transformer.

`

Ross Invicta Mill Townsville South Clare South King Creek Strathmore Collinsville North

Clare

Legend 132kV transmission line 132kV substation 275kV transmission line

Legend Strathmore

132kV transmission line 132kV substation 275kV transmission line 275kV substation

Invicta Mill King Creek Ross Collinsville North

slide-21
SLIDE 21

NQ Transmission Corridor Network Development

2000 onwards

  • Replacement of original substations at

Clare and Collinsville at adjacent sites

  • Connection of major customers
  • Decommissioning of assets:
  • Collinsville Power Station connections
  • Mackay to Proserpine transmission line.
slide-22
SLIDE 22

NQ Transmission Corridor Network Development

Characteristics

  • 275kV

– provides intra-regional transfers

  • 132kV

– provides back-up supply to Townsville and voltage support to Strathmore / Northern Bowen Basin – provides connections to King Creek, Invicta Mill and Clare South – Not much headroom New generation

  • High-level interest renewable

generation

slide-23
SLIDE 23

NQ Transmission Corridor Network Development

Future network requirements

  • Existing transfer capability is sufficient

and seldom constrains market

  • peration
  • May change with generation mix and

types of loads. Assets reaching end of life

  • 132kV network: 5-10 years
  • 275kV single circuit lines: 10-20 years
  • Near term issue with inland 132kV

circuit. Flexibility to reshape the footprint to respond to evolved requirements

slide-24
SLIDE 24

Gold Coast Area

slide-25
SLIDE 25

Greenbank Loganlea Swanbank E Blackwall Molendinar Mudgeeraba Blackstone Middle Ridge Belmont Cades County Southport Merrimac Nerang Robina Terranora Legend

275kV transmission line 110kV transmission line 275kV substation 110kV substation Energex asset boundary Regional boundary

Surfers Paradise Varsity Lakes Burleigh Heads

Gold Coast Area

  • The main transmission system

supporting power transfers to the Gold Coast consists of the Greenbank to Molendinar and Greenbank to Mudgeeraba 275kV transmission lines.

  • The Molendinar and

Mudgeeraba 275/110kV substations are the major injection points into the area.

Legend Loganlea Cades County Southport Surfers Paradise Belmont Swanbank E Greenbank Merrimac Varsity Lakes Burleigh Heads Mudgeeraba Robina Nerang

Molendinar

Middle Ridge Blackstone Blackwall Terranora

275kV transmission line 110kV transmission line 275kV substation 110kV substation Energex asset boundary Regional boundary

slide-26
SLIDE 26
  • Currently three 275/110kV transformers at Mudgeeraba

Substation

  • With the existing three transformer configuration, there is

no load at risk during the 10 year outlook period

  • Replacement or decommissioning needs to be

considered for one of the transformers in the next three to five years

  • Joint planning would need to be done between Powerlink,

Energex, Transgrid, Essential Energy and Directlink.

Mudgeeraba Third Transformer

slide-27
SLIDE 27
  • Existing transmission network supplying the Gold Coast

has adequate capacity 10 year load outlook and Directlink export capability

  • Any major reinvestment or network reconfiguration

involving these single circuit transmission lines will include consultation with a large number of stakeholders – complex joint planning, community consultation and RIT-T consultation

  • Due to complexity and potential staging requirements, it

has been identified that an optimised end of life strategy should be agreed within three to five years.

Greenbank to Mudgeeraba Transmission Lines

slide-28
SLIDE 28

Greenbank Loganlea Swanbank E Blackwall Molendinar Mudgeeraba Blackstone Middle Ridge Belmont Cades County Southport Merrimac Nerang Robina Terranora Legend

275kV transmission line 110kV transmission line 275kV substation 110kV substation Energex asset boundary Regional boundary

Surfers Paradise Varsity Lakes Burleigh Heads

Gold Coast Area

Emerging issues Three to five years

  • Mudgeeraba 275kV secondary

systems

  • No. 3 275/110kV transformer at

Mudgeeraba Five to 10 years

  • 2 x single circuit 275kV Greenbank

to Mudgeeraba transmission lines

  • Molendinar 275/110kV secondary

systems

  • Mudgeeraba 110kV Substation
  • Greenbank secondary systems

and SVC secondary systems

  • Mudgeeraba to STR-1731 (NSW

Boarder Terranora) 110kV double circuit transmission line

Legend Loganlea Cades County Southport Surfers Paradise Belmont Swanbank E Greenbank Merrimac Varsity Lakes Burleigh Heads Mudgeeraba Robina Nerang

Molendinar

Middle Ridge Blackstone Blackwall Terranora

275kV transmission line 110kV transmission line 275kV substation 110kV substation Energex asset boundary Regional boundary

slide-29
SLIDE 29

Questions?

slide-30
SLIDE 30
  • Thank you for attending today’s webinar
  • We encourage you to contact Powerlink for any

more details

  • Information on the RIT-T/non-network solutions

can be found on our website

  • For further questions or to join Powerlink’s

Non-Network Engagement Stakeholder Register (NNESR) please email networkassessments@powerlink.com.au.

Conclusion

slide-31
SLIDE 31

Thank you

www.powerlink.com.au networkassessments@powerlink.com.au