From Vision to Reality: Enhancing the Lower Boise River Dry Creek - - PowerPoint PPT Presentation

from vision to reality
SMART_READER_LITE
LIVE PREVIEW

From Vision to Reality: Enhancing the Lower Boise River Dry Creek - - PowerPoint PPT Presentation

From Vision to Reality: Enhancing the Lower Boise River Dry Creek Structure Rehabilitation and Stream Bank Restoration Project September 7 th , 2011 Scott Koberg - Ada Soil & Water Conservation District Meridian, Idaho Ada Soil &


slide-1
SLIDE 1

From Vision to Reality: Enhancing the Lower Boise River

Dry Creek Structure Rehabilitation and Stream Bank Restoration Project September 7th, 2011 Scott Koberg - Ada Soil & Water Conservation District Meridian, Idaho

slide-2
SLIDE 2

Ada Soil & Water Conservation District (Ada SWCD) 1 of 50 conservation districts in Idaho Identified in Idaho statute as “governmental subdivisions of the state” Lead non-regulatory efforts to conserve, sustain, improve, and enhance natural resources 5 or 7 board supervisors Locally elected public officials Contributions and allocations from state, county, local, and other organizations Always looking for partnership opportunities

slide-3
SLIDE 3
slide-4
SLIDE 4
slide-5
SLIDE 5

Dry Creek Erosion Control, Sediment Reduction, Streambank Restoration and Riparian Buffer

Project Area

slide-6
SLIDE 6
slide-7
SLIDE 7

Idaho State Department of Agriculture Water Quality Monitoring

Suspended Sediment Concentration: “There was a large spike of SSC that occurred on or just before May 15, 2008 at the lower station… Precipitation records prior to this date showed no significant rain fall and this peak concentration was not observed at the upstream

  • station. This would appear to indicate that the likely source of

this large SSC input may have resulted from a portion of a large cut bank sloughing into Dry Creek.” Total Phosphorus: “The total phosphorus (TP) concentrations within Dry Creek remained relatively stable with the exception of the large spike (0.45 mg/L) that occurred at DC-1 on the same date that corresponded to the high SSC spike.”

slide-8
SLIDE 8
slide-9
SLIDE 9

Dry Creek Stream Bank Rehabilitation and Riparian Restoration

 Project Goal: Create a stable stream channel and establish a riparian buffer corridor on each side of Dry Creek  Objectives: 1) Prevent stream bank erosion 2) Restore stream channel stability 3) Improve surface water quality (Dry Creek & Boise River) 4) Enhance wildlife habitat 5) Provide natural resource education & community outreach  Methods: 1) Restore structure to functioning condition 2) Shape & grade “steep wall” eroded stream banks 3) Plant native riparian herbaceous & woody species 4) Create 200’ wide riparian buffer on each side of creek 5) Install public pedestrian pathway & educational signage

slide-10
SLIDE 10
slide-11
SLIDE 11

Riparian Buffer (18 acres) 200’ Structure Location

Riparian Buffer Plan View

slide-12
SLIDE 12
slide-13
SLIDE 13
slide-14
SLIDE 14

November 29, 2007 May 23, 2008 October 3, 2008 September 24, 2008

slide-15
SLIDE 15

October 8, 2008

slide-16
SLIDE 16

August 17, 2009

slide-17
SLIDE 17

November 29, 2007 March 25, 2008 September 17, 2008 August 15, 2008

slide-18
SLIDE 18

October 7, 2008

slide-19
SLIDE 19

June 25, 2010

slide-20
SLIDE 20

September 24, 2008 October 7, 2008 September 16, 2008 April 17, 2009

slide-21
SLIDE 21

September 17, 2008 June 2, 2009

slide-22
SLIDE 22

November 29, 2007 August 15, 2008 October 3, 2008 September 24, 2008

slide-23
SLIDE 23

June 2, 2009

slide-24
SLIDE 24

Dry Creek Structure Rehabilitation and Stream Bank Restoration Project Successful Implementation Requires 5 “C”s: 1.Commitment (landowner) 2.Cooperators (technical partners) 3.Corps (Army COE) permits 4.Construction contractors 5.Cash

slide-25
SLIDE 25

Commitment (landowner)

slide-26
SLIDE 26

Cooperators (partners)

slide-27
SLIDE 27

Construction Contractors

slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30
slide-31
SLIDE 31
slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34

Cash

slide-35
SLIDE 35

Dry Creek Structure Rehabilitation and Stream Bank Restoration Project Successful Implementation Requires 5 “C”s: 1.Commitment (landowner) 2.Cooperators (technical partners) 3.Corps (Army COE) permits 4.Construction contractors 5.Cash

slide-36
SLIDE 36

Scott Koberg - adaswcd@clearwire.net (Ada SWCD Manager) http://www.adaswcd.org