freeing up melbourne s biggest bottleneck
play

FREEING UP MELBOURNE'S BIGGEST BOTTLENECK PRESENTATION TO THE - PowerPoint PPT Presentation

FREEING UP MELBOURNE'S BIGGEST BOTTLENECK PRESENTATION TO THE TOURISM INDUSTRY 29 AUGUST 2017 Evan Tattersall, CEO, Melbourne Metro Rail Authority MELBOURNES CHALLENGES POPULATION GROWTH NORTHERN +450,000 WESTERN EASTERN +420,000


  1. FREEING UP MELBOURNE'S BIGGEST BOTTLENECK PRESENTATION TO THE TOURISM INDUSTRY 29 AUGUST 2017 Evan Tattersall, CEO, Melbourne Metro Rail Authority

  2. MELBOURNE’S CHALLENGES

  3. POPULATION GROWTH NORTHERN +450,000 WESTERN EASTERN +420,000 +180,000 SOUTHERN +450,000 CENTRAL POPULATION GROWTH +270,000 WILL BE CONCENTRATED IN THE NORTH, WEST AND SOUTH EAST Figures indicate forecast population growth between 2011 and 2031. Source: Plan Melbourne

  4. NEW BUSINESS GROWTH NEW BUSINESSES 2001 – 2011 Professional Manufacturing 51-125 businesses 125-500 businesses 250-500 businesses Over 500 A CHANGING ECONOMY businesses IS HAVING AN IMPACT ON WHERE PEOPLE WORK Source: Plan Melbourne

  5. MELBOURNE’S RAIL NETWORK

  6. FUTURE RAIL PATRONAGE • Population growth • Inner city jobs • Road congestion • Parking costs • Environmental impacts

  7. RAIL NETWORK PINCH POINTS CITY LOOP APPROACHING CAPACITY NORTH MELBOURNE TRAINS QUEUE FOR CITY LOOP RICHMOND TRAINS QUEUE PINCH POINTS ARE FOR CITY LOOP AFFECTING RAIL NETWORK OPERABILITY

  8. TRAM PINCH POINTS ACCESS TO PARKVILLE TRAMS APPROACHING CAPACITY ACCESS TO ST KILDA TRAMS APPROACHING CAPACITY PINCH POINTS ARE AFFECTING CBD TRANSPORT OPERABILITY

  9. METRO TUNNEL PROJECT

  10. METRO TUNNEL

  11. CAPACITY BENEFITS

  12. METRO RAIL NETWORK MASTER PLAN

  13. TRAMS WHERE THEY ARE NEEDED INCREASING GROWTH AND DEMAND FOR TRAM SERVICES MELBOURNE CBD’S WEST AND NORTH-WEST AND DOCKLANDS RELIEVE CONGESTION AND RELIANCE ON TRAMS ALONG SWANSTON ST / ST KILDA RD METRO TUNNEL IS THE CATALYST FOR PTV TO MODERNISE THE TRAM NETWORK

  14. MILESTONES

  15. PROCUREMENT APPROACH

  16. WORK PACKAGES EARLY WORKS • Utility services relocation, demolition, CBD access shafts and other preparatory works (Managing Contractor) • Tram diversion works (Franchisee Works) • Construction power (Utility Service Provider) TUNNEL AND STATIONS (AVAILABILITY PPP) • 9km twin tunnels and five underground stations including fit-out • Mechanical and electrical systems • Tunnel and stations maintenance • Rail systems installation within the tunnel RAIL INFRASTRUCTURE (ALLIANCE) • Eastern and Western Portals • Integration of portal with existing rail networks (civil track, overhead line equipment, signalling) • Eastern and Western Turnback • Wider network enhancements RAIL SYSTEMS (ALLIANCE) • High capacity signalling • Conventional signalling upgrades and modifications • Communication systems • Platform screen doors • Train control and operational control systems • Systems integration and end-to-end commissioning

  17. PPP: CROSS YARRA PARTNERSHIP Approx 80 renowned companies

  18. RAIL SYSTEMS: CPB BOMBARDIER 4 Alliance Participants 8 key support firms

  19. STATIONS

  20. ARDEN

  21. ARDEN

  22. ARDEN

  23. ARDEN URBAN RENEWAL PRECINCT

  24. PARKVILLE

  25. PARKVILLE

  26. PARKVILLE

  27. CBD NORTH

  28. CBD NORTH

  29. CBD NORTH

  30. CBD NORTH

  31. OVERSITE DEVELOPMENT OPPORTUNITIES – CBD NORTH

  32. DIRECT CITY LOOP CONNECTION Metro Tunnel

  33. CBD SOUTH

  34. CBD SOUTH

  35. CBD SOUTH

  36. CBD SOUTH

  37. CBD SOUTH

  38. OVERSITE DEVELOPMENT OPPORTUNITIES – CBD SOUTH

  39. DOMAIN

  40. DOMAIN

  41. DOMAIN

  42. RAIL SYSTEMS

  43. HIGH CAPACITY SIGNALLING

  44. HIGH CAPACITY SIGNALLING Existing system: Moving block signalling technology:

  45. HIGH CAPACITY METRO TRAINS

  46. HIGH CAPACITY METRO TRAINS

  47. MANAGING CONSTRUCTION

  48. SIMULTANEOUS CONSTRUCTION

  49. TUNNEL BORING MACHINES

  50. CONSTRUCTION IMPACTS

  51. ARDEN DEMOLITION

  52. WORKS IN PARKVILLE

  53. QUEENSBERRY STREET

  54. FRANKLIN STREET PILING WORKS

  55. A’BECKETT STREET WORKS

  56. CITY SQUARE WORKS

  57. FEDERATION SQUARE

  58. DOMAIN ROAD PARTIAL CLOSURE

  59. ALBERT ROAD SEWER WORKS

  60. TOORAK ROAD WEST TRAM WORKS

  61. ST KILDA ROAD

  62. TURNING DISRUPTION INTO ATTRACTION

  63. MELBOURNE (1970 S )

  64. FINSBURY CIRCUS, LONDON (FUTURE LIVERPOOL ST STATION, CROSSRAIL)

  65. CROSSRAIL LIVERPOOL ST STATION

  66. HOARDING OPPORTUNITIES Crossrail Living or green installations Art Light projections Digital screens Community activity

  67. CITY SQUARE HOARDING

  68. CITY SQUARE HOARDING

  69. A’BECKETT ST HOARDING

  70. HOARDING CONCEPTS

  71. ACOUSTIC SHEDS

  72. ENGAGEMENT APPROACH Phase One Phase Two Phase Three Phase Four Phase Five Phase Six Raising public Public Formal Engagement to Ongoing Completion and awareness and engagement to consultation to support promotion of ‘big handover understanding support planning preparatory picture’ benefits support EES approvals and works, exhibition and Early Engagement to reference procurement public hearings stakeholder support major design and transition to engagement construction major construction

  73. STATION NAMING COMPETITION

  74. KEEPING MELBOURNE MOVING

  75. KEY ROAD CHANGES

  76. ROAD IMPACTS

  77. KEEPING MELBOURNE MOVING Transport for Victoria Travel Demand Management Network Impact Management Plan

  78. UPGRADING DIVERSION ROUTES

  79. WORKING WITH BUSINESSES & TOURISM INDUSTRY

  80. SUPPORTING BUSINESSES • MMRA is working with businesses to assess how the project may impact them and identify what options for assistance may be appropriate • Business support guidelines developed and implemented for early works • Exploring innovative ways to ensure Melbourne's CBD remains a destination for shopping and tourism • Much work has already been done to reduce potential impacts

  81. SUPPORTING BUSINESSES Range of business support measures including: � Marketing and promotion � Wayfinding and signage � Leverage existing events � Create local activation opportunities � Use construction infrastructure to create focal points � Upskill businesses � Regular, ongoing communications � Precinct and individual business action plans

  82. SUPPORTING BUSINESSES

  83. MAJOR EVENTS COORDINATION

  84. BUILDING PARTNERSHIPS

  85. TOURISM OPPORTUNITIES

  86. STAY INFORMED

  87. E-NEWS AND NOTIFICATIONS

  88. E-NEWS AND NOTIFICATIONS

  89. NEXT STEPS

  90. NEXT STEPS

  91. metrotunnel.vic.gov.au

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend