Fort Hills Project September 2015 Mining and Bitumen Extraction - - PowerPoint PPT Presentation

fort hills project
SMART_READER_LITE
LIVE PREVIEW

Fort Hills Project September 2015 Mining and Bitumen Extraction - - PowerPoint PPT Presentation

Fort Hills Project September 2015 Mining and Bitumen Extraction Process 1 Process Technology High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes


slide-1
SLIDE 1

Fort Hills Project

September 2015

slide-2
SLIDE 2

Mining and Bitumen Extraction Process

1

slide-3
SLIDE 3

Process Technology

High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes via reduced product carbon residue, sulphur, and other elements

2

slide-4
SLIDE 4

Project Status and Progress

Safety and Environment

continued positive performance

construction hours

without a reportable environmental or regulatory non-compliance

13 million

recordable injury frequency

per 200,000 exposure hours

0.35-0.45 90% engineering complete

as at August 2015

40% construction complete

as at August 2015

global fabrication, module and logistics program

performing well to date, delivering positive results

all critical schedule milestones have been achieved to date supporting target 2017 first oil

Project Progress

continues to track positively within project sanction cost and schedule expectations

slide-5
SLIDE 5

Fort Hills construction productivity has improved over previous regionally executed projects since the launch of a formal productivity improvement program

Construction Productivity

4

Improved construction productivity serves to de-risk project execution and contributes to on-plan schedule and on-budget cost attainment

Improved productivity level has been reflected in the sanction estimate and schedule

slide-6
SLIDE 6

Site resourcing continues to meet plan with increasing access to Western Canada based resources due to current market conditions

Site Workforce Profile

2000 4000 6000 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16 Jul-16 Sep-16 Nov-16 Jan-17 Mar-17 May-17 Jul-17 Sep-17 Nov-17

5

slide-7
SLIDE 7

Pipe and Module Fabrication, Korea

6

slide-8
SLIDE 8

Structural Steel Fabrication, China

7

slide-9
SLIDE 9

Piping Fabrication, India

8

slide-10
SLIDE 10

Mining Development, Looking NE

9

slide-11
SLIDE 11

Main Plant Site Looking NW

10

slide-12
SLIDE 12

Ore Preparation, Looking NE

11

slide-13
SLIDE 13

Ore Preparation, Crusher Plant

12

slide-14
SLIDE 14

Ore Preparation, Surge Bin

13

slide-15
SLIDE 15

Ore Preparation, Rotary Breakers

14

slide-16
SLIDE 16

Ore Preparation

15

slide-17
SLIDE 17

Hydro Transport Corridor

16

slide-18
SLIDE 18

Extraction and Tailings, Looking NE

17

slide-19
SLIDE 19

Extraction and Tailings

18

slide-20
SLIDE 20

Extraction and Tailings, Thickener

19

slide-21
SLIDE 21

Secondary Extraction, Looking West

20

slide-22
SLIDE 22

Secondary Extraction

21

slide-23
SLIDE 23

Secondary Extraction

22

slide-24
SLIDE 24

Secondary Extraction

23

slide-25
SLIDE 25

Utilities, Looking NW

24

slide-26
SLIDE 26

Utilities, Process Water Tanks

25

slide-27
SLIDE 27

Utilities, Cogen-GTG Building

26

slide-28
SLIDE 28

Utilities Recycle Water Pond, Looking SE

27

slide-29
SLIDE 29

River Water Intake, Looking NE

28

slide-30
SLIDE 30

Raw Water Pond, Looking NE

29

slide-31
SLIDE 31

Operations Lodge

30

slide-32
SLIDE 32

Maintenance Shops

31

slide-33
SLIDE 33

Main Substation

32

slide-34
SLIDE 34

Tank Farm

33

slide-35
SLIDE 35

Gate 9, Looking East

34

slide-36
SLIDE 36