Fort Hills Project September 2015 Mining and Bitumen Extraction - - PowerPoint PPT Presentation
Fort Hills Project September 2015 Mining and Bitumen Extraction - - PowerPoint PPT Presentation
Fort Hills Project September 2015 Mining and Bitumen Extraction Process 1 Process Technology High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes
Mining and Bitumen Extraction Process
1
Process Technology
High temperature paraffinic froth treatment provides about 20% partial upgrading advantage over other more convention bitumen production processes via reduced product carbon residue, sulphur, and other elements
2
Project Status and Progress
Safety and Environment
continued positive performance
construction hours
without a reportable environmental or regulatory non-compliance
13 million
recordable injury frequency
per 200,000 exposure hours
0.35-0.45 90% engineering complete
as at August 2015
40% construction complete
as at August 2015
global fabrication, module and logistics program
performing well to date, delivering positive results
all critical schedule milestones have been achieved to date supporting target 2017 first oil
Project Progress
continues to track positively within project sanction cost and schedule expectations
Fort Hills construction productivity has improved over previous regionally executed projects since the launch of a formal productivity improvement program
Construction Productivity
4
Improved construction productivity serves to de-risk project execution and contributes to on-plan schedule and on-budget cost attainment
Improved productivity level has been reflected in the sanction estimate and schedule
Site resourcing continues to meet plan with increasing access to Western Canada based resources due to current market conditions
Site Workforce Profile
2000 4000 6000 Jan-14 Mar-14 May-14 Jul-14 Sep-14 Nov-14 Jan-15 Mar-15 May-15 Jul-15 Sep-15 Nov-15 Jan-16 Mar-16 May-16 Jul-16 Sep-16 Nov-16 Jan-17 Mar-17 May-17 Jul-17 Sep-17 Nov-17
5
Pipe and Module Fabrication, Korea
6
Structural Steel Fabrication, China
7
Piping Fabrication, India
8
Mining Development, Looking NE
9
Main Plant Site Looking NW
10
Ore Preparation, Looking NE
11
Ore Preparation, Crusher Plant
12
Ore Preparation, Surge Bin
13
Ore Preparation, Rotary Breakers
14
Ore Preparation
15
Hydro Transport Corridor
16
Extraction and Tailings, Looking NE
17
Extraction and Tailings
18
Extraction and Tailings, Thickener
19
Secondary Extraction, Looking West
20
Secondary Extraction
21
Secondary Extraction
22
Secondary Extraction
23
Utilities, Looking NW
24
Utilities, Process Water Tanks
25
Utilities, Cogen-GTG Building
26
Utilities Recycle Water Pond, Looking SE
27
River Water Intake, Looking NE
28
Raw Water Pond, Looking NE
29
Operations Lodge
30
Maintenance Shops
31
Main Substation
32
Tank Farm
33
Gate 9, Looking East
34