flood risk management project
play

Flood Risk Management Project Karen Thomas Project Manager Water - PowerPoint PPT Presentation

Benacre & Kessingland Flood Risk Management Project Karen Thomas Project Manager Water Management Alliance On behalf of Waveney, Lower Yare and Lothingland Internal Drainage Board Lowestoft N Courtesy of Mike Page 2016 Courtesy of Mike


  1. Benacre & Kessingland Flood Risk Management Project Karen Thomas Project Manager Water Management Alliance On behalf of Waveney, Lower Yare and Lothingland Internal Drainage Board

  2. Lowestoft N

  3. Courtesy of Mike Page

  4. 2016 Courtesy of Mike Page

  5. 2017 Courtesy of Mike Page and Benacre Estates

  6. Breach Risk to Kessingland Levels

  7. Alternative Flood Risk Management Options

  8. Circa 44 Homes Commercial businesses What’s at Tidal Risk? 600 acres + Agriculture Abstraction Tourism Recreation and Access Transport links (A12) Utilities (water, electric) Landscape Wildlife

  9. SOUTH AREA 08/01/2019

  10. SOUTH AREA 08/01/2019

  11. NORTH AREA 08/01/2019

  12. NORTH AREA 08/01/2019

  13. Fluvial Flood Risk

  14. Surface water fl flooding in Kessingland

  15. Benacre flood defence options Preferred alignments of potential new defences

  16. Parkdean Resorts Alignment Options

  17. Benacre Estates- Lothingland Valley set-back option

  18. Economics studies • Wider economic study from Mott MacDonalds • Identifies £130M of wider economic benefits arising from an adaptive approach • SCC Highways report estimated present value losses (PV Losses), accrued over a 50 years (2018 – 2068), are £253,717,000 for the Do Nothing plus climate change scenario. • Both reports will feed into economic appraisal in OBC • Form basis of wider partnership funding ask for a scheme

  19. Stakeholder Engagement • Partnership approach • Project Board supported by local Councillors and MP Peter Aldous • Multi-agency project team • Local leadership from Kessingland Parish Council • 150 stakeholders attended initial drop-in Nov 2017 • Autumn 2019- update on latest information and likely preferred options • Spring 2020- final rounds of engagement and OBC submission

  20. Recent progress From October 2018 • RFCC decision on Levy funding • WMA & Jacobs programme for 18 months OBC • Includes Parkdean Resorts costed options in the appraisal • Developing our stakeholder engagement approach and share evidence • Identify potential funding routes (funding framework) for the capital scheme including private elements • Technical work to be developed over next 12 months- coastal change, ground conditions, outline designs for defences and pump capacity • Develop a preferred option and engage local people Autumn 2019 and Spring 2020 • Submit Business Case June 2020

  21. Opportunities & challenges • Outside of the FDGIA Business Case- the project aims to deliver wider benefits and attract broader funding streams • Opportunities for landscape scale adaptation • Freshwater capture and storage for habitat enhancement and agriculture • Fisheries, tourism and access can be enhanced • Need to attract investors • £10-15M scheme

  22. Questions

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend