Flood Risk Management Project Karen Thomas Project Manager Water - - PowerPoint PPT Presentation

flood risk management project
SMART_READER_LITE
LIVE PREVIEW

Flood Risk Management Project Karen Thomas Project Manager Water - - PowerPoint PPT Presentation

Benacre & Kessingland Flood Risk Management Project Karen Thomas Project Manager Water Management Alliance On behalf of Waveney, Lower Yare and Lothingland Internal Drainage Board Lowestoft N Courtesy of Mike Page 2016 Courtesy of Mike


slide-1
SLIDE 1

Benacre & Kessingland Flood Risk Management Project

Karen Thomas

Project Manager Water Management Alliance On behalf of Waveney, Lower Yare and Lothingland Internal Drainage Board

slide-2
SLIDE 2

Lowestoft N

slide-3
SLIDE 3
slide-4
SLIDE 4

Courtesy of Mike Page

slide-5
SLIDE 5

Courtesy of Mike Page

2016

slide-6
SLIDE 6

Courtesy of Mike Page and Benacre Estates

2017

slide-7
SLIDE 7

Breach Risk to Kessingland Levels

slide-8
SLIDE 8

Alternative Flood Risk Management Options

slide-9
SLIDE 9

What’s at Tidal Risk?

Circa 44 Homes Commercial businesses 600 acres + Agriculture Abstraction Tourism Recreation and Access Transport links (A12) Utilities (water, electric) Landscape Wildlife

slide-10
SLIDE 10

SOUTH AREA 08/01/2019

slide-11
SLIDE 11

SOUTH AREA 08/01/2019

slide-12
SLIDE 12

NORTH AREA 08/01/2019

slide-13
SLIDE 13

NORTH AREA 08/01/2019

slide-14
SLIDE 14

Fluvial Flood Risk

slide-15
SLIDE 15

Surface water fl flooding in Kessingland

slide-16
SLIDE 16

Preferred alignments of potential new defences

Benacre flood defence options

slide-17
SLIDE 17

Parkdean Resorts Alignment Options

slide-18
SLIDE 18

Benacre Estates- Lothingland Valley set-back

  • ption
slide-19
SLIDE 19

Economics studies

  • Wider economic study from Mott

MacDonalds

  • Identifies £130M of wider economic

benefits arising from an adaptive approach

  • SCC Highways report estimated present

value losses (PV Losses), accrued over a 50 years (2018 –2068), are £253,717,000 for the Do Nothing plus climate change scenario.

  • Both reports will feed into economic

appraisal in OBC

  • Form basis of wider partnership funding

ask for a scheme

slide-20
SLIDE 20

Stakeholder Engagement

  • Partnership approach
  • Project Board supported by local

Councillors and MP Peter Aldous

  • Multi-agency project team
  • Local leadership from Kessingland

Parish Council

  • 150 stakeholders attended initial

drop-in Nov 2017

  • Autumn 2019- update on latest

information and likely preferred

  • ptions
  • Spring 2020- final rounds of

engagement and OBC submission

slide-21
SLIDE 21

Recent progress

From October 2018

  • RFCC decision on Levy funding
  • WMA & Jacobs programme for 18 months OBC
  • Includes Parkdean Resorts costed options in the appraisal
  • Developing our stakeholder engagement approach and share evidence
  • Identify potential funding routes (funding framework) for the capital scheme

including private elements

  • Technical work to be developed over next 12 months- coastal change, ground

conditions, outline designs for defences and pump capacity

  • Develop a preferred option and engage local people Autumn 2019 and Spring 2020
  • Submit Business Case June 2020
slide-22
SLIDE 22

Opportunities & challenges

  • Outside of the FDGIA Business

Case- the project aims to deliver wider benefits and attract broader funding streams

  • Opportunities for landscape scale

adaptation

  • Freshwater capture and storage for

habitat enhancement and agriculture

  • Fisheries, tourism and access can

be enhanced

  • Need to attract investors
  • £10-15M scheme
slide-23
SLIDE 23
slide-24
SLIDE 24

Questions