FINAL DESIGN PRESENTATION 13 th St N Kirkwood Rd to N. Johnson St - - PowerPoint PPT Presentation
FINAL DESIGN PRESENTATION 13 th St N Kirkwood Rd to N. Johnson St - - PowerPoint PPT Presentation
FINAL DESIGN PRESENTATION 13 th St N Kirkwood Rd to N. Johnson St (Lyon Village Neighborhood) Angela Marshall, Neighborhood Conservation Planner Community Planning, Housing, & Development Neighborhood Conservation Program Final Design
Final Design N560 13th Street N (N Kirkwood Rd to N Johnson St)
Agenda:
- 1. Overview of the Project
- 2. Street Improvement Design Plan
- 3. Sign and Pavement Markings Plan
- 4. Landscape Plan
Presentation Purpose: Present final design to property owners in preparation for construction of the street improvement project on 13th St N, Kirkwood Rd to N. Johnson St. Project Goal: Pedestrian Safety project to include a 5-foot wide sidewalk, curb and gutter on the south-side, and curb and gutter only
- n the north-side of 13th St N between Kirkwood Rd to N.
Johnson St and a retaining wall at one property. All improvements within existing right-of-way; ADA compliant accessible curb ramps at the intersection of 13th Street N and N Kirkwood Rd. Parking on either side of 13th St N will not be permitted.
Temporary Easements
- Temporary easements and construction agreements allow the County
contractor to access private yards to perform construction-related work, including the relocation of fences, replacement of disturbed sod, and making grade adjustments.
- The County agrees to restore the disturbed area on and adjacent to the
Temporary Easement Area as nearly as practicable to its original condition.
- Temporary easements become null and void at the end of the project.
Next steps
1. Questions and comments
- Relative to the overall project design
- Relative to individual lots
- 2. Final design plan 90%→100%
- 3. Temporary easements complete
- 4. Utility relocation complete
- 5. On-call contractor/Prepare for construction