Exeter Flood Defence Scheme CECA South West Members Presentation - - PowerPoint PPT Presentation

exeter flood defence scheme
SMART_READER_LITE
LIVE PREVIEW

Exeter Flood Defence Scheme CECA South West Members Presentation - - PowerPoint PPT Presentation

Exeter Flood Defence Scheme CECA South West Members Presentation 30th November 2016 Tristan Bassett Commercial Services Manager, EA Don Higgs Framework Manager, BMM JV Update Covering .. Why were Building What were Building


slide-1
SLIDE 1

Exeter Flood Defence Scheme

CECA South West Member’s Presentation 30th November 2016 Tristan Bassett – Commercial Services Manager, EA Don Higgs – Framework Manager, BMM JV

slide-2
SLIDE 2

Update – Covering ..

Why we’re Building What we’re Building How we’re Building plus construction Challenges

slide-3
SLIDE 3

Areas at risk of Flooding – 1:100 Year Event

Properties at Risk

  • Approx. 2300 Domestic Properties
  • Approx. 1000 Commercial Properties

Critical Infrastructure Current Standard : Generally 1 in 40 Blocker to Economic Growth

City Centre Marsh Barton St Thomas Exwick

Why We’re Building

slide-4
SLIDE 4

Description of the Works

  • Scheme Starts at Cowley Bridge in

the North

  • End at Countess Wear / Bridge Road

in the South

  • Spread out over 7 km

Zone 1 – Location of Network Rail Land Zone 2 – Exwick & Flowerpot Fields Zone 3 – Central Exeter Zone 4 – Exeter Quay Zone 5 – Exeter Canal Zone 6 – Countess Wear

slide-5
SLIDE 5

Overall Programme for Exeter FDS

Phase 1 : In-channel works south of Trew’s Weir

  • Permitted development
  • Completed October 2015

Phase 2 : Raised defences, gates etc

  • Planning Consent received July 2015
  • Future Milestones:

– March 2016: Award Construction Contract – May 2016: Site works to commence – Summer 2018: Completion

slide-6
SLIDE 6

Phase 1

Modification of Trew’s Flood Relief Channel

Reduce crest of side weir Deepen flood relief channel and create wetland habitat Remove existing check weir New fish passes on Trews Weir and side weir

slide-7
SLIDE 7

Exe Bridges – defence embankments Exwick – defence walls and banks Cowley Bridge – defence solutions to be designed in association with Network Rail Railway – defence walls and banks Station Road – flood gates St Davids Station – defence walls Haven Banks – defence embankments and walls Bonhay Road - Localised defences. Eagle Cottages – defence walls

Design Aim = to maximise flow capacity Channel capacity improvements Structural alterations 7.4km raised defences

Phase 2

slide-8
SLIDE 8

Countess Wear Sewage Treatment Works – SWW defence embankments Mill Lane – Defence wall and embankments Canal Banks – raised embankments and walls (also acts to protect trunk sewer) Trews Side Weir – crest modifications Trews Flood Relief Channel – regrading to improve capacity The Quay – Demountable defences

Will raise standard of flood protection from 1/40 annual risk to 1/100 annual risk Construction in 2 phases: 1. ‘In Channel’ works 2. Flood defences

Phase 2

slide-9
SLIDE 9

Phase 2 - The Quay Before

slide-10
SLIDE 10

Phase 2 - The Quay After

slide-11
SLIDE 11

Phase 2 – ‘The Quay’ During

slide-12
SLIDE 12

Phase 2 – Flood Gates

slide-13
SLIDE 13

Interface with Network Rail infrastructure Access

Phase 2 – Cowley to St Davids

slide-14
SLIDE 14

Costs, Funding and Partner Co-

  • peration

The Partners Governance & Project Team Staff & DCC departments Future Operations Cost - £32.5m Funding Contributors Exeter CC - £3m Devon CC - £3m SWW – Up to £1.5m, dialogue ongoing EA - £25m

slide-15
SLIDE 15

How we’re Building plus construction Challenges

Key Quantities Earthworks Strategy Key locations and challenges

slide-16
SLIDE 16

Key Quantities

Earthworks Total – 130,000m3 Sheet Piling Total – 1670m CFA Piling – 280no RC Walls – 1690m Flood Gates – 14no Glass Flood Panels – 130m Demountable Flood Panels – 95m

slide-17
SLIDE 17

Key Quantities

Earthwork Strategy

  • Ensure

fill meets engineering requirements, advanced trial holes / testing.

  • No material moved off site.
  • Control of high value core fill material.
  • Programming

to take advantage

  • f

summer months where possible given other constraints.

  • Minimise

haul distances and vehicular movements.

slide-18
SLIDE 18

Station Road

slide-19
SLIDE 19

Bonhay Road

slide-20
SLIDE 20

Eagle Cottages

slide-21
SLIDE 21

The Quay

slide-22
SLIDE 22

Double Locks

slide-23
SLIDE 23

Countess Wear

slide-24
SLIDE 24

Communications

Importance recognised for public, businesses and partner organisations Dedicated PL staff member Several evening drop in sessions Extensive use of social media

slide-25
SLIDE 25

Zone 1 – Cowley Bridge

slide-26
SLIDE 26

Zone 1 – Cowley Bridge

slide-27
SLIDE 27

Zone 2 – Exwick / Flowerpot

slide-28
SLIDE 28

Zone 2 – Exwick / Flowerpot

slide-29
SLIDE 29

Zone 2 – Exwick / Flowerpot

slide-30
SLIDE 30

Zone 3 – Trew’s Flood Relief Channel

slide-31
SLIDE 31

Zone 3 – Trew’s Flood Relief Channel

slide-32
SLIDE 32

Zone 3 – Trew’s Flood Relief Channel

slide-33
SLIDE 33

Zone 6 – Countess Weir

slide-34
SLIDE 34

Zone 6 – Countess Weir

slide-35
SLIDE 35

Zone 6 – Countess Weir

slide-36
SLIDE 36

Thank you!