European Network Code Implementation Overview Wednesday 3 May 2017 - - PowerPoint PPT Presentation

european network code implementation overview
SMART_READER_LITE
LIVE PREVIEW

European Network Code Implementation Overview Wednesday 3 May 2017 - - PowerPoint PPT Presentation

European Network Code Implementation Overview Wednesday 3 May 2017 EU Code Implementation Overview Background and purpose More detail on: Connection Codes Requirements for Generators Operational Codes Balancing Codes


slide-1
SLIDE 1

European Network Code Implementation Overview

Wednesday 3 May 2017

slide-2
SLIDE 2

 Background and purpose  More detail on:

Connection Codes – Requirements for Generators Operational Codes Balancing Codes

 Implementation Progress  Get involved/Keep informed

2

EU Code Implementation Overview

slide-3
SLIDE 3

European Network Code Implementation Overview

Rob Wilson Technical Codes Development Manager

slide-4
SLIDE 4

European 3rd package drivers

4

slide-5
SLIDE 5

The key players in ENC Development

5

slide-6
SLIDE 6

European Network Codes Development Process

6

slide-7
SLIDE 7

What are the codes and what do they do?

7

Markets

Establishes a platform for managing capacity and flow around the interconnected system to facilitate the setup of a single EU market Capacity Allocation & Congestion Management (“CACM”) Forward Capacity Allocation (“FCA”) Electricity Balancing Guideline (“EBGL”)

System Operation

Harmonises the processes Transmission System Operators have to manage their systems, including system restoration (Transmission) System Operation Guideline (“TSOG”) Emergency & Restoration (“ER”)

Grid Connection

Sets consistent technical requirements across EU for new connections of user equipment (e.g. generation/interconnectors) Requirements for Generators (“RfG”) High Voltage Direct Current (“HVDC”) Demand Connection (Code) (“DCC”)

slide-8
SLIDE 8

More detail on: EU Connection Codes

slide-9
SLIDE 9

9

Overview of the EU Connection codes

Requirements for Generators (RfG)

Entry Into Force: 17th May 2016 Applies to: New generation connections (800 Watts capacity and up) to Distribution and Transmission systems From: 17th May 2018 onwards

Demand Connection Code (DCC)

Entry Into Force: 7th September 2016 Applies to: New Transmission-connected Demand connections; and new equipment providing Demand Side Response From: 7th September 2018

High Voltage Direct Current (HVDC)

Entry Into Force: 29th September 2016 Applies to: New Transmission-connected Demand connections,, and new equipment providing Demand Side Response From: 7th September 2018

slide-10
SLIDE 10

More detail on RfG – Generator Banding

  • Technical requirements in RfG are arranged into x4 Types based
  • n a user’s connection voltage and MW capacity
  • Type A - B requirements are close to a product standard
  • Type C - D requirements need active user management
  • GB levels will apply consistently across Scotland and England +
  • Wales. The local TSO (NGET) will make a proposal for the levels -

this is then ratified via industry consultation and regulatory approval

Maximum RfG banding levels permitted for GB: Type Connection Voltage Capacity A < 110kV 800 W – 1 MW B < 110kV 1 MW – 50 MW C < 110kV 50 MW – 75 MW D > 110kV 75 MW +

Current GB Levels: Generator Size SHET SPT NGET Small <10MW <30MW <50MW Medium 50-100MW Large >10MW >30MW >100MW

slide-11
SLIDE 11

More detail on RfG – Requirements per Type

11

Technical Requirements Type A Type B Type C Type D Operation across a range of frequencies

  • Limits on active power output over frequency range
  • Rate of change of frequency settings applied (likely to be at least 1Hz/sec)
  • Logic interface (input port) to cease active power output within 5 secs
  • Ability to automatically reduce power on instruction
  • Control schemes, protection and metering
  • Fault Ride Through requirements
  • Ability to reconnect
  • Reactive capability
  • Reactive current injection
  • Active power controllability
  • Frequency response
  • Monitoring
  • Automatic disconnection
  • Optional Black start
  • Stable operation anywhere in operating range
  • Pole slipping protection
  • Quick resynchronisation capability
  • Instrumentation and monitoring requirements
  • Ramp rate limits
  • Simulation models
  • Wider Voltage ranges / longer minimum operating times
  • Synchronisation on instruction
  • Enhanced Fault Ride through
slide-12
SLIDE 12

More detail on: Transmission System Operation Guideline

Rob Selbie EU Codes Development Manager

slide-13
SLIDE 13

Overview of the EU System Operation codes

13

Emergency & Restoration Code (E&R):

Harmonisation of system defence and restoration procedures during severe events

Transmission System Operation Guideline (TSOG):

system security, operational planning and frequency management standards

Operational Security

  • Data Exchange
  • System States
  • System

Management

Operational Planning

  • Regional security

coordination

  • Outage

coordination

  • Adequacy

Load Frequency Control & Reserves

  • Operational

agreements

  • Quality targets

Harmonises the processes TSO have to manage their systems, including system operation

slide-14
SLIDE 14

So am I impacted?

TSOs More transparency in system

  • peration

Operational security analysis Cross-border processes Generators New data exchange requirements Including for distribution connected SGUs Distribution Network Operators New data exchange requirements and outage coordination responsibilities

Interconnectors

Facilitation of exchange of A/S Including agreements for cross-border processes

14

slide-15
SLIDE 15

More detail on: Electricity Balancing Guideline; TERRE

slide-16
SLIDE 16

Overview of the European MARKET codes

16

Early Implementation – Project TERRE

Pan-EU Balancing Energy Market

  • Development of pan-EU platforms

for the exchange of standard balancing energy products

  • 6 year implementation period
  • Replacement Reserves (RR)
  • Manual Frequency Restoration

Reserves (mFRR)

  • Specific products retained

nationally

Harmonisation of Market Design & Settlement

  • Harmonised Gate Closure Time for

standard products

  • Harmonisation of ISP at Synchronous

Area level

  • Harmonisation of imbalance

arrangements (preference for single imbalance pricing)

  • Harmonisation of reserve procurement

arrangements

Cross Zonal Capacity Reservation (CZC)

  • Opens the possibility for TSOs to

reserve XB capacity for the exchange of balancing energy

  • Co optimisation with market

timeframes

  • TSOs to develop detailed

methodologies

slide-17
SLIDE 17

Overview of the European Market codes

17

TSOs: Access to a wider pool of flexibility EU Platforms procurement closer to real time Balancing Service Providers: New standard products; Access to EU market; Level playing field Balance Responsible Parties: Harmonised imbalance settlement; Imbalance Adjustment; More accurate price signals Interconnectors: Facilitation of exchange of A/S; More variability

slide-18
SLIDE 18

Implementation Progress

slide-19
SLIDE 19

ENC implementation approach (multiple interactions to manage!)

slide-20
SLIDE 20

20

1

Grid Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Grid Code

National Grid GC0048 May-2017 17/05/2018

Consolidated mod - dependencies between banding and fault ride through parameters

2

Distribution Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Distribution Code

ENA TBC 17/05/2018

Consolidated mod - dependencies between banding and fault ride through parameters

3

Grid Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Grid Code

National Grid GC0048 May-2017 17/05/2018

4

Distribution Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Distribution Code

ENA TBC 17/05/2018

5

Grid Code - Compliance and System Management Grid Code

National Grid GC0048 Jun-2017 17/05/2018

6

Distribution Code - Compliance and System Management Distribution Code

ENA TBC 17/05/2018

7

Grid Code - DCC Technical & Demand Side Response Requirements Grid Code

National Grid GC0091 Jun-2017 07/09/2018

8

Distribution Code - DCC Technical & Demand Side Response Requirements Distribution Code

ENA TBC Jun-2017 07/08/2018

9

Grid Code – to enable data provision between NGET and other TSOs Grid Code

National Grid TBC Apr-2017 Q2 2018 Common Grid Model Project

10

Grid Code – to enable interconnector data provision to NGET after GB gate closure Grid Code

National Grid TBC Apr-2017 Q1 2019 (TBC)

11

EB GL - General Compliance (BSC) BSC

Elexon TBC Q3 2017 Q3 2018

12

EB GL - General Compliance (Grid Code) Grid Code

National Grid TBC Q3 2017 Q3 2018

13

EB GL - General Compliance (Distribution Code) Distribution Code

ENA TBC Q3 2017 Q3 2018

14

BSC - Publication of information BSC

Elexon TBC Q3 2017 Q4 2018 Project TERRE

15

BSC - Assignment Elexon Tasks BSC

Elexon TBC Apr-2017 Q3 2017

16

BSC - Replacement Reserves BSC

Elexon P344 Q2 2016 Q4 2018 Project TERRE

17

Grid Code - Replacement Reserves Grid Code

National Grid GC0097 Q1 2017 Q4 2018 Project TERRE

18

CUSC - Replacement Reserves CUSC

National Grid TBC Q4 2017 Q4 2018 Project TERRE

19

Grid Code - manual Frequency Restoration Reserves Grid Code

National Grid TBC Q1 2020 Q3 2021 mFRR Project

20

BSC - manual Frequency Restoration Reserves BSC

Elexon TBC Q1 2020 Q3 2021 mFRR Project

21

CUSC - manual Frequency Restoration Reserves CUSC

National Grid TBC Q3 2020 Q3 2021 mFRR Project

22

BSC - Imbalance Settlement Harmonisation BSC

Elexon TBC Q1 2019 Q3 2020

23

STC - Multi TSO Training Cooperation STC

National Grid TBC Q3 2017 Q3 2018

24

SQSS - Determination of Minimum required Inertia SQSS

National Grid TBC Q3 2018 Q3 2019

25

Grid Code - TSOG requirements for data exchange Grid Code

National Grid TBC Q3 2017 Q3 2018

26

D-Code - TSOG requirements for data exchange Distribution Code

ENA TBC Q3 2017 Q3 2018

27

STC - TSOG requirements for data exchange STC

National Grid TBC Q3 2017 Q3 2018

28

Grid Code - Regional Outage Coordination and Security Analysis Grid Code

National Grid TBC Q1 2018 Q4 2018

29

D-Code - Regional Outage Coordination and Security Analysis Distribution Code

ENA TBC Q1 2018 Q4 2018

30

SQSS - Regional Outage Coordination and Security Analysis SQSS

National Grid TBC Q1 2018 Q4 2018

31

STC - Regional Outage Coordination and Security Analysis STC

National Grid TBC Q1 2018 Q4 2018

32

Grid Code - TSOG requirements in relation to reserve providers and operational agreements Grid Code

National Grid TBC Q1 2018 Q4 2018

33

SQSS - TSOG requirements in relation to reserve providers and operational agreements SQSS

National Grid TBC Q1 2018 Q4 2018

34

Grid Code - System Defence & Restoration Plans Grid Code

National Grid TBC Q3 2017 Q3 2018

35

BSC - Market Suspension BSC

National Grid TBC Q3 2017 Q3 2018

36

Grid Code - Market Suspension Grid Code

National Grid TBC Q3 2017 Q3 2018 Planned Date to Raise at Code Panel

Operational Codes

TSOG (EIF - 01/07/2017 Expected) E&R (EIF - Q3 2017 Expected)

Required Compliance Date Dependencies

Connection Codes

Requirements for Generators (EIF - 17/05/2016) & HVDC (EIF - 29/09/2016) DCC (EIF - 07/09/2016)

Market Codes

CACM (EIF - 14/08/2015) EB GL (EIF - Q3 2017 Expected)

EU Code Family Ref Modification Description

Which GB Code To be Applied

Code Administrator Modification Reference

Markets & Balancing Development

GB Code Modifications

slide-21
SLIDE 21

Where can I find out more?

slide-22
SLIDE 22

For more information/how to get involved

Joint European Stakeholder Group:  A monthly meeting covering all European legislation issues (supported by BEIS, Ofgem, National Grid amongst others)  Weekly Email Newsletter Update  For more information contact: europeancodes.electricity@nationalgrid.com Implementation Workgroups (Grid Code):  RfG Implementation Workgroup – GC0048  RfG Frequency Response provisions - GC0087  HVDC Implementation Workgroup - GC0090  DCC Implementation Workgroup - GC0091  TSOG Implementation Workgroup - GC0095  TERRE Implementation Workgroup – GC0097  For more information contact: Grid.Code@nationalgrid.com

22

slide-23
SLIDE 23

Fact sheets

 Fact sheets providing an overview on each EU code are available on our website:

http://www2.nationalgrid.com/UK/Industry-information/Electricity- codes/European-network-code/Development-process-and-code- information/

23

slide-24
SLIDE 24

Back-up content

slide-25
SLIDE 25

Where to find info on SO Ancillary Services

 Our Balancing Services web page provides information on commercial opportunities: www2.nationalgrid.com/uk/services/balancing-services/  More detail on these services is set out in a range of guides available at this link: http://www2.nationalgrid.com/UK/Services/Balancing- services/Service-Guides/

25

For more information please contact: commercial.operation @nationalgrid.com

slide-26
SLIDE 26

Update: Review of transmission charging

  • In light of significant change in recent years, e.g. decentralisation,

decarbonisation and new technologies; we believe Transmission charging and commercial arrangements need holistic review

  • This was supported by feedback from two dedicated charging

seminars held in July (outputs here: Charging Review Website)

  • Feedback from these seminars has informed the scope and

approach of a review. At TCMF on 08/12/16 we presented further thoughts on the next steps. These are grouped in three areas… 1. Quick wins – a number of activities are progressing, including CUSC mods on half hourly charging (CMP266), a policy paper on storage (early 2017) and improvements to tariff forecasting. 2. Holistic review – we want to work with Ofgem to ensure their areas of work around embedded generation are comprehensive, particularly with regards to flexibility. 3. Stakeholder forum – we want to establish a forum to discuss broader industry reform and develop a route-map for change

26

slide-27
SLIDE 27

Other Grid Code mods

GC0096 – Storage is a new workgroup kicking off in early 2017 In conjunction with the BEIS/Ofgem call for evidence on Flexibility, it will define (Electricity) Storage in the Grid Code, and make clear what technical requirements are required for: Stand-alone Storage connections, and... Storage configured with existing generation or demand units For more details on how to get involved please email Grid.Code@nationalgrid.com

27

slide-28
SLIDE 28

Market Design

Capacity Allocation & Congestion Management (CACM) Guideline

  • Implicit Day Ahead & Intraday cross border trading
  • Bidding zone reporting process and subsequent review

Forward Capacity Allocation (FCA) Guideline

  • Long term transmission rights;
  • Physical Transmission Rights (PTRs) with Use It or

Sell It (UIOSI)

  • Financial Transmission Rights (FTR) options
  • FTR obligations
  • Single Allocation Platform with Harmonised Allocation

Rules

Regional Capacity Calculation

  • CACM and FCA both increase regional TSO

coordination with capacity calculation used to determine interconnector capacities

  • Calculation underpinned by a pan- EU Common Grid

Model (CGM)

It establishes a platform for managing capacity & flow around the interconnected system to facilitate a single EU market

Overview of the European MARKET codes

slide-29
SLIDE 29

CACM and FCA have been published and become law within the UK;

  • CACM entry into force 14 Aug 2015
  • FCA entry into force 17 Oct 2016CACM

and FCA now requires T TSOs, NEMOs to draft, consult, and submit proposals to regulators on detailed design aspects. CACM proposals largely complete by end

  • f 2018, FCA by end of 2019.

Any changes to GB codes to implement CACM and FCA will be raised and consulted

  • n through the normal GB code governance

routes

TSO = Transmission System Operator NEMO= Nominated Electricity Market Operator

Overview of the European MARKET codes

slide-30
SLIDE 30

NG and other TSOs will develop new processes to increase regional coordination Trading Interconnector capacity in the forwards markets trading cross border energy in the day-ahead & intraday timeframes Generators and demand to provide information on which TSO decisions are made on a regional basis (see Common Grid Model) Power exchanges (in their new role as NEMOs) will develop new processes to deliver a pan-EU marketplace Interconnector owners (current and future) will operate under new rules, including new requirements on interconnector firmness

Overview of the European MARKET codes

slide-31
SLIDE 31

CGM built at D-2 CGM built at D-1

Common Grid Model (CGM)

  • A European-wide network model assembled from each TSO’s

individual grid model (IGM)

  • Realistic and accurate representation of the Transmission &

Distribution networks

  • One scenario for each market time unit (1 hour)
  • Built to a common standard with a harmonised modelling approach
  • Used as a key tool for many new coordinated European processes –
  • incl. capacity calculation

Each TSO’s IGM is built using the latest available data from market participants for specific delivery times

Rolling Daily Process that supports target model

TSO A IGM

Overview of the European MARKET codes

TSO B IGM TSO C IGM

slide-32
SLIDE 32

Overview of the European MARKET codes

32

Obligations

Q2 Q3 Q4 2016 Q1 Q2 Q3 Q4 2017 Q1 Q2 Q3 2018

ENC deadlines CGM Methodology GLDP Methodology

Early testing and parallel run of CGM process

NRA approval

DA & ID CGM Requirements (for CACM) delivered Update CGMM & GLDPM for FCA (Long- term timescales) FCA EIF TSOG EIF DA & ID data requirements for CACM) delivered Update CGMM & GLDPM for TSOG

CGM process fully

  • perational

NRA approval

TSO develop IGM capability

TSOs publish list

  • f parties

required to provide data Data Provision process fully operational

CACM EIF Aug 2015

So when does it come into effect?

Deadline Proposal Project

Key

slide-33
SLIDE 33

Overview of the Joint European stakeholder group

33

The Joint European Stakeholder Group is a

GB Stakeholder forum which will cover the development, Comitology process and implementation of European Network Codes (ENC), which provides a single group for GB stakeholder to engage on all aspects of European Policy Want to get Involved? WebEx/teleconference facilities available Weekly update – sign up on feedback form Monthly meetings – come along, held at Exelon offices, London Next meeting: 13th December 2016 – EID discussions. Come and talk at lunch should you want to know anymore Barbara Vest Director of Generation (Chair) Chrissie Brown NETSO Code Administration (Technical Secretary)