European Network Code Implementation Overview Wednesday 3 May 2017 - - PowerPoint PPT Presentation
European Network Code Implementation Overview Wednesday 3 May 2017 - - PowerPoint PPT Presentation
European Network Code Implementation Overview Wednesday 3 May 2017 EU Code Implementation Overview Background and purpose More detail on: Connection Codes Requirements for Generators Operational Codes Balancing Codes
Background and purpose More detail on:
Connection Codes – Requirements for Generators Operational Codes Balancing Codes
Implementation Progress Get involved/Keep informed
2
EU Code Implementation Overview
European Network Code Implementation Overview
Rob Wilson Technical Codes Development Manager
European 3rd package drivers
4
The key players in ENC Development
5
European Network Codes Development Process
6
What are the codes and what do they do?
7
Markets
Establishes a platform for managing capacity and flow around the interconnected system to facilitate the setup of a single EU market Capacity Allocation & Congestion Management (“CACM”) Forward Capacity Allocation (“FCA”) Electricity Balancing Guideline (“EBGL”)
System Operation
Harmonises the processes Transmission System Operators have to manage their systems, including system restoration (Transmission) System Operation Guideline (“TSOG”) Emergency & Restoration (“ER”)
Grid Connection
Sets consistent technical requirements across EU for new connections of user equipment (e.g. generation/interconnectors) Requirements for Generators (“RfG”) High Voltage Direct Current (“HVDC”) Demand Connection (Code) (“DCC”)
More detail on: EU Connection Codes
9
Overview of the EU Connection codes
Requirements for Generators (RfG)
Entry Into Force: 17th May 2016 Applies to: New generation connections (800 Watts capacity and up) to Distribution and Transmission systems From: 17th May 2018 onwards
Demand Connection Code (DCC)
Entry Into Force: 7th September 2016 Applies to: New Transmission-connected Demand connections; and new equipment providing Demand Side Response From: 7th September 2018
High Voltage Direct Current (HVDC)
Entry Into Force: 29th September 2016 Applies to: New Transmission-connected Demand connections,, and new equipment providing Demand Side Response From: 7th September 2018
More detail on RfG – Generator Banding
- Technical requirements in RfG are arranged into x4 Types based
- n a user’s connection voltage and MW capacity
- Type A - B requirements are close to a product standard
- Type C - D requirements need active user management
- GB levels will apply consistently across Scotland and England +
- Wales. The local TSO (NGET) will make a proposal for the levels -
this is then ratified via industry consultation and regulatory approval
Maximum RfG banding levels permitted for GB: Type Connection Voltage Capacity A < 110kV 800 W – 1 MW B < 110kV 1 MW – 50 MW C < 110kV 50 MW – 75 MW D > 110kV 75 MW +
Current GB Levels: Generator Size SHET SPT NGET Small <10MW <30MW <50MW Medium 50-100MW Large >10MW >30MW >100MW
More detail on RfG – Requirements per Type
11
Technical Requirements Type A Type B Type C Type D Operation across a range of frequencies
- Limits on active power output over frequency range
- Rate of change of frequency settings applied (likely to be at least 1Hz/sec)
- Logic interface (input port) to cease active power output within 5 secs
- Ability to automatically reduce power on instruction
- Control schemes, protection and metering
- Fault Ride Through requirements
- Ability to reconnect
- Reactive capability
- Reactive current injection
- Active power controllability
- Frequency response
- Monitoring
- Automatic disconnection
- Optional Black start
- Stable operation anywhere in operating range
- Pole slipping protection
- Quick resynchronisation capability
- Instrumentation and monitoring requirements
- Ramp rate limits
- Simulation models
- Wider Voltage ranges / longer minimum operating times
- Synchronisation on instruction
- Enhanced Fault Ride through
More detail on: Transmission System Operation Guideline
Rob Selbie EU Codes Development Manager
Overview of the EU System Operation codes
13
Emergency & Restoration Code (E&R):
Harmonisation of system defence and restoration procedures during severe events
Transmission System Operation Guideline (TSOG):
system security, operational planning and frequency management standards
Operational Security
- Data Exchange
- System States
- System
Management
Operational Planning
- Regional security
coordination
- Outage
coordination
- Adequacy
Load Frequency Control & Reserves
- Operational
agreements
- Quality targets
Harmonises the processes TSO have to manage their systems, including system operation
So am I impacted?
TSOs More transparency in system
- peration
Operational security analysis Cross-border processes Generators New data exchange requirements Including for distribution connected SGUs Distribution Network Operators New data exchange requirements and outage coordination responsibilities
Interconnectors
Facilitation of exchange of A/S Including agreements for cross-border processes
14
More detail on: Electricity Balancing Guideline; TERRE
Overview of the European MARKET codes
16
Early Implementation – Project TERRE
Pan-EU Balancing Energy Market
- Development of pan-EU platforms
for the exchange of standard balancing energy products
- 6 year implementation period
- Replacement Reserves (RR)
- Manual Frequency Restoration
Reserves (mFRR)
- Specific products retained
nationally
Harmonisation of Market Design & Settlement
- Harmonised Gate Closure Time for
standard products
- Harmonisation of ISP at Synchronous
Area level
- Harmonisation of imbalance
arrangements (preference for single imbalance pricing)
- Harmonisation of reserve procurement
arrangements
Cross Zonal Capacity Reservation (CZC)
- Opens the possibility for TSOs to
reserve XB capacity for the exchange of balancing energy
- Co optimisation with market
timeframes
- TSOs to develop detailed
methodologies
Overview of the European Market codes
17
TSOs: Access to a wider pool of flexibility EU Platforms procurement closer to real time Balancing Service Providers: New standard products; Access to EU market; Level playing field Balance Responsible Parties: Harmonised imbalance settlement; Imbalance Adjustment; More accurate price signals Interconnectors: Facilitation of exchange of A/S; More variability
Implementation Progress
ENC implementation approach (multiple interactions to manage!)
20
1
Grid Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Grid Code
National Grid GC0048 May-2017 17/05/2018
Consolidated mod - dependencies between banding and fault ride through parameters
2
Distribution Code - RfG Banding and Fast Fault Current Injection, RfG and HVDC Fault Ride Through Distribution Code
ENA TBC 17/05/2018
Consolidated mod - dependencies between banding and fault ride through parameters
3
Grid Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Grid Code
National Grid GC0048 May-2017 17/05/2018
4
Distribution Code - RfG and HVDC Voltage/Reactive and Frequency Response requirements Distribution Code
ENA TBC 17/05/2018
5
Grid Code - Compliance and System Management Grid Code
National Grid GC0048 Jun-2017 17/05/2018
6
Distribution Code - Compliance and System Management Distribution Code
ENA TBC 17/05/2018
7
Grid Code - DCC Technical & Demand Side Response Requirements Grid Code
National Grid GC0091 Jun-2017 07/09/2018
8
Distribution Code - DCC Technical & Demand Side Response Requirements Distribution Code
ENA TBC Jun-2017 07/08/2018
9
Grid Code – to enable data provision between NGET and other TSOs Grid Code
National Grid TBC Apr-2017 Q2 2018 Common Grid Model Project
10
Grid Code – to enable interconnector data provision to NGET after GB gate closure Grid Code
National Grid TBC Apr-2017 Q1 2019 (TBC)
11
EB GL - General Compliance (BSC) BSC
Elexon TBC Q3 2017 Q3 2018
12
EB GL - General Compliance (Grid Code) Grid Code
National Grid TBC Q3 2017 Q3 2018
13
EB GL - General Compliance (Distribution Code) Distribution Code
ENA TBC Q3 2017 Q3 2018
14
BSC - Publication of information BSC
Elexon TBC Q3 2017 Q4 2018 Project TERRE
15
BSC - Assignment Elexon Tasks BSC
Elexon TBC Apr-2017 Q3 2017
16
BSC - Replacement Reserves BSC
Elexon P344 Q2 2016 Q4 2018 Project TERRE
17
Grid Code - Replacement Reserves Grid Code
National Grid GC0097 Q1 2017 Q4 2018 Project TERRE
18
CUSC - Replacement Reserves CUSC
National Grid TBC Q4 2017 Q4 2018 Project TERRE
19
Grid Code - manual Frequency Restoration Reserves Grid Code
National Grid TBC Q1 2020 Q3 2021 mFRR Project
20
BSC - manual Frequency Restoration Reserves BSC
Elexon TBC Q1 2020 Q3 2021 mFRR Project
21
CUSC - manual Frequency Restoration Reserves CUSC
National Grid TBC Q3 2020 Q3 2021 mFRR Project
22
BSC - Imbalance Settlement Harmonisation BSC
Elexon TBC Q1 2019 Q3 2020
23
STC - Multi TSO Training Cooperation STC
National Grid TBC Q3 2017 Q3 2018
24
SQSS - Determination of Minimum required Inertia SQSS
National Grid TBC Q3 2018 Q3 2019
25
Grid Code - TSOG requirements for data exchange Grid Code
National Grid TBC Q3 2017 Q3 2018
26
D-Code - TSOG requirements for data exchange Distribution Code
ENA TBC Q3 2017 Q3 2018
27
STC - TSOG requirements for data exchange STC
National Grid TBC Q3 2017 Q3 2018
28
Grid Code - Regional Outage Coordination and Security Analysis Grid Code
National Grid TBC Q1 2018 Q4 2018
29
D-Code - Regional Outage Coordination and Security Analysis Distribution Code
ENA TBC Q1 2018 Q4 2018
30
SQSS - Regional Outage Coordination and Security Analysis SQSS
National Grid TBC Q1 2018 Q4 2018
31
STC - Regional Outage Coordination and Security Analysis STC
National Grid TBC Q1 2018 Q4 2018
32
Grid Code - TSOG requirements in relation to reserve providers and operational agreements Grid Code
National Grid TBC Q1 2018 Q4 2018
33
SQSS - TSOG requirements in relation to reserve providers and operational agreements SQSS
National Grid TBC Q1 2018 Q4 2018
34
Grid Code - System Defence & Restoration Plans Grid Code
National Grid TBC Q3 2017 Q3 2018
35
BSC - Market Suspension BSC
National Grid TBC Q3 2017 Q3 2018
36
Grid Code - Market Suspension Grid Code
National Grid TBC Q3 2017 Q3 2018 Planned Date to Raise at Code Panel
Operational Codes
TSOG (EIF - 01/07/2017 Expected) E&R (EIF - Q3 2017 Expected)
Required Compliance Date Dependencies
Connection Codes
Requirements for Generators (EIF - 17/05/2016) & HVDC (EIF - 29/09/2016) DCC (EIF - 07/09/2016)
Market Codes
CACM (EIF - 14/08/2015) EB GL (EIF - Q3 2017 Expected)
EU Code Family Ref Modification Description
Which GB Code To be Applied
Code Administrator Modification Reference
Markets & Balancing Development
GB Code Modifications
Where can I find out more?
For more information/how to get involved
Joint European Stakeholder Group: A monthly meeting covering all European legislation issues (supported by BEIS, Ofgem, National Grid amongst others) Weekly Email Newsletter Update For more information contact: europeancodes.electricity@nationalgrid.com Implementation Workgroups (Grid Code): RfG Implementation Workgroup – GC0048 RfG Frequency Response provisions - GC0087 HVDC Implementation Workgroup - GC0090 DCC Implementation Workgroup - GC0091 TSOG Implementation Workgroup - GC0095 TERRE Implementation Workgroup – GC0097 For more information contact: Grid.Code@nationalgrid.com
22
Fact sheets
Fact sheets providing an overview on each EU code are available on our website:
http://www2.nationalgrid.com/UK/Industry-information/Electricity- codes/European-network-code/Development-process-and-code- information/
23
Back-up content
Where to find info on SO Ancillary Services
Our Balancing Services web page provides information on commercial opportunities: www2.nationalgrid.com/uk/services/balancing-services/ More detail on these services is set out in a range of guides available at this link: http://www2.nationalgrid.com/UK/Services/Balancing- services/Service-Guides/
25
For more information please contact: commercial.operation @nationalgrid.com
Update: Review of transmission charging
- In light of significant change in recent years, e.g. decentralisation,
decarbonisation and new technologies; we believe Transmission charging and commercial arrangements need holistic review
- This was supported by feedback from two dedicated charging
seminars held in July (outputs here: Charging Review Website)
- Feedback from these seminars has informed the scope and
approach of a review. At TCMF on 08/12/16 we presented further thoughts on the next steps. These are grouped in three areas… 1. Quick wins – a number of activities are progressing, including CUSC mods on half hourly charging (CMP266), a policy paper on storage (early 2017) and improvements to tariff forecasting. 2. Holistic review – we want to work with Ofgem to ensure their areas of work around embedded generation are comprehensive, particularly with regards to flexibility. 3. Stakeholder forum – we want to establish a forum to discuss broader industry reform and develop a route-map for change
26
Other Grid Code mods
GC0096 – Storage is a new workgroup kicking off in early 2017 In conjunction with the BEIS/Ofgem call for evidence on Flexibility, it will define (Electricity) Storage in the Grid Code, and make clear what technical requirements are required for: Stand-alone Storage connections, and... Storage configured with existing generation or demand units For more details on how to get involved please email Grid.Code@nationalgrid.com
27
Market Design
Capacity Allocation & Congestion Management (CACM) Guideline
- Implicit Day Ahead & Intraday cross border trading
- Bidding zone reporting process and subsequent review
Forward Capacity Allocation (FCA) Guideline
- Long term transmission rights;
- Physical Transmission Rights (PTRs) with Use It or
Sell It (UIOSI)
- Financial Transmission Rights (FTR) options
- FTR obligations
- Single Allocation Platform with Harmonised Allocation
Rules
Regional Capacity Calculation
- CACM and FCA both increase regional TSO
coordination with capacity calculation used to determine interconnector capacities
- Calculation underpinned by a pan- EU Common Grid
Model (CGM)
It establishes a platform for managing capacity & flow around the interconnected system to facilitate a single EU market
Overview of the European MARKET codes
CACM and FCA have been published and become law within the UK;
- CACM entry into force 14 Aug 2015
- FCA entry into force 17 Oct 2016CACM
and FCA now requires T TSOs, NEMOs to draft, consult, and submit proposals to regulators on detailed design aspects. CACM proposals largely complete by end
- f 2018, FCA by end of 2019.
Any changes to GB codes to implement CACM and FCA will be raised and consulted
- n through the normal GB code governance
routes
TSO = Transmission System Operator NEMO= Nominated Electricity Market Operator
Overview of the European MARKET codes
NG and other TSOs will develop new processes to increase regional coordination Trading Interconnector capacity in the forwards markets trading cross border energy in the day-ahead & intraday timeframes Generators and demand to provide information on which TSO decisions are made on a regional basis (see Common Grid Model) Power exchanges (in their new role as NEMOs) will develop new processes to deliver a pan-EU marketplace Interconnector owners (current and future) will operate under new rules, including new requirements on interconnector firmness
Overview of the European MARKET codes
CGM built at D-2 CGM built at D-1
Common Grid Model (CGM)
- A European-wide network model assembled from each TSO’s
individual grid model (IGM)
- Realistic and accurate representation of the Transmission &
Distribution networks
- One scenario for each market time unit (1 hour)
- Built to a common standard with a harmonised modelling approach
- Used as a key tool for many new coordinated European processes –
- incl. capacity calculation
Each TSO’s IGM is built using the latest available data from market participants for specific delivery times
Rolling Daily Process that supports target model
TSO A IGM
Overview of the European MARKET codes
TSO B IGM TSO C IGM
Overview of the European MARKET codes
32
Obligations
Q2 Q3 Q4 2016 Q1 Q2 Q3 Q4 2017 Q1 Q2 Q3 2018
ENC deadlines CGM Methodology GLDP Methodology
Early testing and parallel run of CGM process
NRA approval
DA & ID CGM Requirements (for CACM) delivered Update CGMM & GLDPM for FCA (Long- term timescales) FCA EIF TSOG EIF DA & ID data requirements for CACM) delivered Update CGMM & GLDPM for TSOG
CGM process fully
- perational
NRA approval
TSO develop IGM capability
TSOs publish list
- f parties
required to provide data Data Provision process fully operational
CACM EIF Aug 2015
So when does it come into effect?
Deadline Proposal Project
Key
Overview of the Joint European stakeholder group
33