Environmental Management Los Alamos Field Office Fiscal Year 16 Accomplishments & Fiscal Years 17 and 18 Planned Activities Doug E. Hintze, Manager Environmental Management Los Alamos Field Office January 13, 2017 Main Bridge Contract


slide-1
SLIDE 1

Environmental Management Los Alamos Field Office Fiscal Year 16 Accomplishments & Fiscal Years 17 and 18 Planned Activities

Doug E. Hintze, Manager

Environmental Management Los Alamos Field Office January 13, 2017

slide-2
SLIDE 2

2

Main Bridge Contract Priorities for FY 2017

Treatment of the Remediated Nitrate Salts Chromium Interim Measures and Characterization Campaign Transition to Follow-on Contract

slide-3
SLIDE 3

3

Remediated Nitrate Salts

60 Remediated Nitrate Salt (RNS) drums are stored at Area G Fiscal Year 2016 Accomplishments

Extensive fire mitigation efforts were conducted around Area G Pressure relief devices (PRDs) were installed on the RNS drums A treatment plan for the RNS drums and 29 Un-remediated Nitrate Salt (UNS) drums was developed

Fiscal Year 2017 Planned Activities

Treat the 60 RNS drums and 29 UNS drums Treatment of the RNS drums is scheduled to start in spring of 2017 Treatment of the UNS will follow the treatment of the RNS

3 Workers installed PRDs on the RNS drums in the spring of 2016. The treatment process for the RNS is practiced and refined.

slide-4
SLIDE 4

4

2016 Consent Order

2016 Consent Order signed between DOE and NMED in June 2016 The Consent Order governs environmental cleanup activities only Consent Order lists enforceable milestones each year for the upcoming fiscal year, along with targets for the two fiscal years beyond that (Appendix B of the Consent Order) Priorities, defined as campaigns, are listed in Appendix C of the Consent Order

4

slide-5
SLIDE 5

5

Chromium Interim Measures and Characterization Campaign

Fiscal Year 2016 Accomplishments

Five out of six planned injection wells are installed and instrumented Continued pumping from boundary extraction well CrEX-1 and installed CrEX-3 First phase of piping installation completed Lab testing of potential treatment technologies

Fiscal Year 2017 Planned Activities

Construct and operate plume control system Pilot test of chemical in situ remediation

5 Workers use an angled drilling rig at the CrIN-4 site The closed vault at injection well CrIN-5

slide-6
SLIDE 6

6

6

RDX Characterization Campaign

Fiscal Year 2016 Accomplishments

Completed aquifer field testing in intermediate perched zone Approved work plans for groundwater and surface restoration of permeable reactive barrier Lab testing of biodegradation of RDX

Fiscal Year 2017 Planned Activities

Drill well R-68 to define extent of RDX plume Complete removal of permeable reactive barrier Complete report on aquifer and tracer testing

slide-7
SLIDE 7

7

Historical Properties Completion Campaign

Contaminated soil was placed in double-lined waste bags

Workers prepare a sealed bag of contaminated soil for transportation

7

Fiscal Year 2016 Accomplishments

Contaminated soil was removed from four legacy sites along the south-facing slopes of Los Alamos Canyon adjacent to the Los Alamos Townsite All but a few of the original 229 sites in Upper Los Alamos Canyon still require cleanup

Fiscal Year 2017 Planned Activities

Sampling and cleanup of the remaining sites in and adjacent to the Los Alamos Townsite Initiate risk assessments and investigation reports

slide-8
SLIDE 8

8

Technical Area 21 Campaign

8

Fiscal Year 2016 Accomplishments

Demolition of seven slabs and warehouse at Technical Area 21 Additional waste and debris cleaned up and disposed off-site

Fiscal Year 2017 Planned Activities

Moisture monitoring and MDA-T Additional opportunities to accelerate cleanup if sufficient funding is obtained:

  • TA-21 DP West to Building 257 D&D
slide-9
SLIDE 9

9

Fiscal Year 18 Planned Activities

Environmental Cleanup

Cleanup activities will ensure compliance with Consent Order

  • Chromium Project
  • RDX
  • Technical Area 21

Waste Management

Implement programmatic safety requirements Plan waste retrieval

slide-10
SLIDE 10

10

Moving Forward

The EM Los Alamos Field office will complete its activities in a safe and efficient manner and with full transparency

Workers used heavy equipment to remove contaminated soil from Upper Los Alamos Canyon Debris being cleared at the Los Alamos County Airport landfill