Update: Supplemental Environmental Projects (SEP)

Pete Maggiore NNSA Los Alamos Field Office

Presentation to the Regional Coalition

  • f LANL Communities

January 17, 2017

slide-2
SLIDE 2

Slide 2

U N C L A S S I F I E D

Timeline

1/22/2016 Settlement agreement signed 2/24/2016 First Milestone Met (Initial Meeting with NMED held) Ongoing SEP Team Meetings End of CY 2018 Target completion date for all SEPS

slide-3
SLIDE 3

Slide 3

U N C L A S S I F I E D

  • 1. Road Project
  • 2. Triennial Review Project
  • 3. Watershed

Enhancement Project

  • 4. Surface Water Sampling

and Monitoring Project

  • 5. Potable Water Line

Replacement Project

Supplemental Environmental Projects

slide-4
SLIDE 4

Slide 4

U N C L A S S I F I E D

Ø $12 million Ø “…to improve DOE-owned transportation routes at LANL used for the transportation of transuranic waste to WIPP.”

Paragraph 37

Road Project

slide-5
SLIDE 5

Slide 5

U N C L A S S I F I E D

Road Improvement Project

  • NNSA is working with the

US Army Corp of Engineers (USACE) to finalize and execute scope

slide-6
SLIDE 6

Slide 6

U N C L A S S I F I E D

Ø $2.5 million Ø “…independent, external triennial reviews of environmental …”

Ø Paragraph 38, regulatory compliance and

  • perations

Ø Results made available to LANL, NMED and the public

Triennial Review Project

slide-7
SLIDE 7

Slide 7

U N C L A S S I F I E D

Ø Statement of Work description under final review

– Focus on compliance – Programs to be evaluated during first review include: Hazardous

Waste Permit (RCRA), Title V Operating Permit (Air), Groundwater Discharge Permits Ø Acquisition Strategy (requires NMED concurrence)

– Upcoming Award on DOE Basic Purchase Agreement for NEPA

Support Services

– Sole Source (e.g., 8(a)) (backup plan)

Ø “The initial triennial review must be completed and made public before the end of Federal FY 2018.”

Paragraph 38A

Triennial Review Project

slide-8
SLIDE 8

Slide 8

U N C L A S S I F I E D

Ø $7.5 million Ø Addendum / Workplan approved 12/21/16 Ø “…design and install engineering structures in and around LANL to slow storm water flow and decrease sediment load to improve water quality in the area..”

Paragraph 39

Watershed Enhancement Project

slide-9
SLIDE 9

Slide 9

U N C L A S S I F I E D

Watershed Enhancement Project

Draft Addendum containing prioritized list of projects is currently undergoing final review

slide-10
SLIDE 10

Slide 10

U N C L A S S I F I E D

Surface Water Sampling and Monitoring Project

Ø $2.5 million Ø Workplan Approved

12/21/16

Ø “…increased sampling and

monitoring capabilities for storm water runoff in and around LANL with the results of sampling and monitoring shared with the public and NMED.”

Paragraph 40

slide-11
SLIDE 11

Slide 11

U N C L A S S I F I E D

Ø Draft addendum undergoing final review:

– Improvements to IntellusNM – Sampling and monitoring to fill data gaps

§ Background data, from developed areas, natural landscape, firing sites, atmospheric deposition

– Outreach to the four Accord Pueblos for training and

sampling equipment Ø All data collected will be made publically available

Surface Water Sampling and Monitoring Project

slide-12
SLIDE 12

Slide 12

U N C L A S S I F I E D

Ø $10 million Ø Workplan Approved 12/21/16 Ø “…replace aging potable water lines and install metering equipment for LANL potable water

  • systems. These

improvements will reduce potable water losses, minimize reportable spills, and enhance water conservation efforts at LANL.”

Paragraph 41

Potable Water Line Replacement Project

slide-13
SLIDE 13

Slide 13

U N C L A S S I F I E D

Potable Water Line Replacement Project

Draft Addendum undergoing final review

slide-14
SLIDE 14

Slide 14

U N C L A S S I F I E D

CY16 Q4 CY17 Q1 CY17 Q2 CY17 Q3 CY17 Q4 CY18 Q1 CY18 Q2 CY18 Q3 CY18 Q4 CY19 Q1

DOE Owned Roads Triennial Reviews Watershed Protection Sampling and Monitoring Potable Water Lines and Metering

Purchase Equip/Material Procure/Design Procure/Design Procure/Construction Procure/Construction Procure Assessors Perform Review Execute Sampling and Monitoring Scope Closeout Closeout Closeout Closeout Closeout Procure/Design Procure/Construction

LANL Supplemental Environmental Projects Nominal Schedule

This Schedule will be updated as scopes/plans are finalized and formally added to the Administrative Order

NMED/NNSA/et al Discussions (SA signed 1/22/16, discussions NMED/NNSA sign off on Scope/Plan

slide-15
SLIDE 15

Slide 15

U N C L A S S I F I E D

Path Forward

Ø Begin execution on Potable Water Line Replacement, Watershed Enhancement and Surface Water Monitoring SEPS Ø Finalize Scope of Work /Addendums for Road Improvement and Triennial Review Projects – Addendums will include scope, acquisition strategy, and schedule – Addendums will be “fully enforceable” (per paragraph 45 of the Settlement Agreement)