EL CAMINO REAL TASK FORCE Issues & Criteria for Decision Making - - PowerPoint PPT Presentation

el camino real task force
SMART_READER_LITE
LIVE PREVIEW

EL CAMINO REAL TASK FORCE Issues & Criteria for Decision Making - - PowerPoint PPT Presentation

EL CAMINO REAL TASK FORCE Issues & Criteria for Decision Making Objectives Retain the character and health of The Grove, and Improve the safety of the roadway and sidewalks. Pilot Study Area ECR Task Force Organization


slide-1
SLIDE 1

EL CAMINO REAL TASK FORCE

Issues & Criteria for Decision Making

slide-2
SLIDE 2

Objectives

» Retain the character and health of “The Grove,” and » Improve the safety of the roadway and sidewalks.

slide-3
SLIDE 3

Pilot Study Area

slide-4
SLIDE 4

COMMUNITY GROUP

  • Residents
  • Historical Society
  • Traffic, Safety &

Parking Commission

  • Beautification

Commission

TECHNICAL GROUP

Burlingame

  • Public Works
  • Parks Department

Caltrans

  • Project Manager

ECR Task Force Organization

CITY COUNCIL SUBCOMMITTEE

Advisors

slide-5
SLIDE 5

PHASE I PHASE II PHASE III WRAP UP

ECR Task Force Process

Technical Group Organizational Meetings Design Parameters Recommendations Design Alternatives Recommendations Design Options Design Criteria Community Group Organizational Meetings

Next Steps Walk Around

slide-6
SLIDE 6

“Fishbowl” Meeting Format

slide-7
SLIDE 7

Decision Sequence

Component Trees Sidewalk Roadway Drainage

» Identifying trees to be preserved or rehabilitated will define the sidewalk and roadway options. » Roadway funding will require an ADA compliant sidewalk plan. » Improved roadway design will address safety issues. » Storm drain work will be completed with roadway improvements.

slide-8
SLIDE 8

Issues & Criteria

» Issues:

Factors that influence design options.

» Criteria:

Recommended standards for evaluating design options.

slide-9
SLIDE 9

TREES

slide-10
SLIDE 10

El Camino Real 1915

slide-11
SLIDE 11

El Camino Real 1975

slide-12
SLIDE 12

Historic Criteria

» Preserve and rehabilitate “The Grove” to be consistent with the criteria established in 2012 in the National Historic Register Designation. » All trees to be considered as visually contributory and essential to the whole. » Develop a maintenance and monitoring plan for healthy trees.

slide-13
SLIDE 13

Tree Issues

» Tree health and stability. » Potential private property encroachment to meander sidewalk. » Visibility at intersections. » Serious root damage possible from roadway and sidewalk construction.

slide-14
SLIDE 14

Caltrans Specifications

Allows for 13 trees in the pilot area

Source: Caltrans

Utility Poles

» 10 feet from utility poles and driveways » 100 feet from street corners » 30 feet between trunks

slide-15
SLIDE 15

Task Force Proposal

» Less than 10 feet from utility poles and driveways » 25 feet from street corners » 25 feet between tree trunks

Calls for 48 trees in the pilot area

Source: Caltrans

slide-16
SLIDE 16

Caltrans Specifications

Source: Caltrans

Task Force Proposal

Utility Poles

slide-17
SLIDE 17

Existing

Source: Caltrans

Task Force Proposal

slide-18
SLIDE 18

Citriodora Eucalyptus Patriot Elm

slide-19
SLIDE 19

Citriodora Grove

slide-20
SLIDE 20

SIDEWALKS

slide-21
SLIDE 21

Sidewalk Issues

» Tree roots lifting sidewalk. » West side unprotected from traffic. » Some trees embedded in retaining wall, which leans into sidewalk. » Portion of public right-of-way being used privately. » Incline of driveways.

slide-22
SLIDE 22

Sidewalk Criteria

» Improve safety for pedestrians. » Make sidewalks ADA compliant. » Plant trees between roadway and sidewalk. » Install a double ADA ramp at each corner. » Install lighting. » Meander sidewalk for tree wells where needed.

slide-23
SLIDE 23

ROADWAY

slide-24
SLIDE 24

Roadway Issues

» An ADA compliant sidewalk is required for roadway funding improvements. » Utility poles and boxes. » Retaining wall creates perceived roadway hazard. » Construction impacts to adjacent properties.

slide-25
SLIDE 25

Roadway Criteria

» Retain existing width of roadway. » Improve crosswalk safety. » Provide clear sight lines at intersections and driveways. » Install a quiet, smooth surface. » Explore potential for undergrounding utilities.

slide-26
SLIDE 26

DRAINAGE

slide-27
SLIDE 27

March 2011 Storm

slide-28
SLIDE 28

Drainage Issue

» Storm drain work needs to be coordinated with roadway improvements.

» Planning Sequence:

TREES SIDEWALK ROADWAY DRAINAGE

slide-29
SLIDE 29

Drainage Criteria

» Eliminate standing water on the roadway. » Avoid sheet flow of storm water across El Camino Real. » Protect adjacent property from flooding.

slide-30
SLIDE 30