ARLINGTON CAREER CENTER EXPANSION EDUCATIONAL SPECIFICATIONS SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019 SUMMARY 1. Staff presented this material as an information item at the October 17, 2019 School Board meeting. 2. The Educational


slide-1
SLIDE 1

ARLINGTON CAREER CENTER EXPANSION

EDUCATIONAL SPECIFICATIONS

SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-2
SLIDE 2

SUMMARY

1. Staff presented this material as an information item at the October 17, 2019 School Board meeting. 2. The Educational Specifications (Ed Specs) document was revised to clarify the difference between Planned Enrollment and Calculated Capacity (pages 21, 31, and 39).

2

SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-3
SLIDE 3

PLANNING PARAMETERS

1. Planning parameters are aligned with school, APS and DOE strategic initiatives 2. Program and capacity analysis for the following instructional programs inform facility requirements in these Ed Specs:

Program Seats Arlington Tech 600 TBD1 800 CTE (from neighborhood HS)2 300 Academic Academy 60 EL (formerly HILT) 70 PEP 70 Subtotal Planned Enrollment (Min.) 1,900

1.

  • Ed. Specs. assume the space requirements and facility needs are similar to those of the Arlington

Tech program. 2. Provides capability of serving up to 900 students each day; 300 students in each of three blocks. 3

Allowance for growth of CTE (from neighborhood HS), Academic Academy, EL and PEP Programs____________________________

294 Total Calculated Capacity 2,194

SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-4
SLIDE 4

SUMMARY OF CALCULATED CAPACITY

4 SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-5
SLIDE 5
  • 1. Quantity and size of individual spaces in the Ed Specs was determined using a variety of

input that included:

  • a. Arlington Career Center and Department of Teaching and Learning leaders
  • b. Guidelines from the Virginia Department of Education
  • c. Comparable facilities provided at other APS high schools
  • d. Current best design practices for similar schools/programs
  • e. Lessons learned from recent projects
  • 2. Space program assumes that undersized and/or inefficient spaces within the existing building

will be improved to reflect current requirements

  • 3. Refinements to the space program will occur as part of the typical design process; which

includes detailed floor plan review by staff at Arlington Career Center and Department of Teaching and Learning

5

SPACE PROGRAM

SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-6
SLIDE 6

NEXT STEPS

  • 1. November 2019 to February 2020 –

Concept Design phase BLPC/PFRC meetings

  • Ed Specs refinement is expected

during the phase as design options are developed

  • 2. March 2020 – School Board information

and action on proposed Concept Design

  • 3. June 25, 2020 – School Board action on

FY2021-30 Capital Improvement Plan

6 SCHOOL BOARD ACTION ITEM NOVEMBER 7, 2019

slide-7
SLIDE 7

RECOMMENDATIONS

Staff recommend the School Board take the following actions:

  • Approve the Arlington Career

Center Expansion Educational Specifications document dated November 6, 2019 attached to this presentation.

  • Direct staff to provide an update
  • n the Ed Specs (highlighting any

refinements) concurrent with the proposed Concept Design in March 2020.

SCHOOL BOARD ACTION ITEM 7 NOVEMBER 7, 2019