Edinburgh Glasgow Improvement Programme (EGIP) Presentation to June - - PowerPoint PPT Presentation

edinburgh glasgow improvement programme egip
SMART_READER_LITE
LIVE PREVIEW

Edinburgh Glasgow Improvement Programme (EGIP) Presentation to June - - PowerPoint PPT Presentation

Edinburgh Glasgow Improvement Programme (EGIP) Presentation to June 2012 Railfuture Summer Conference Geoff Cook 2 Edinburgh Glasgow Improvement Programme (EGIP) Background Consultation Process Feedback by Council Area Next Steps 3


slide-1
SLIDE 1
slide-2
SLIDE 2

2

Edinburgh Glasgow Improvement Programme (EGIP) Presentation to June 2012 Railfuture Summer Conference Geoff Cook

slide-3
SLIDE 3

3

Background Consultation Process Feedback by Council Area Next Steps Edinburgh Glasgow Improvement Programme (EGIP)

slide-4
SLIDE 4

4

Edinburgh Glasgow Improvement Programme (EGIP)

  • The next phase of improvements to Central Scotland’s rail network
  • Priority Scottish Government STPR Project
  • Faster, more frequent and more reliable trains
  • 350km of electrified railway
  • A significant contribution to a sustainable Scotland

What is EGIP ?

slide-5
SLIDE 5

5

Edinburgh Glasgow Improvement Programme (EGIP)

Why EGIP ? Strong passenger demand forecast to continue :

  • Edinburgh Suburban : 90% - 115%
  • Glasgow Suburban : 27% - 38%
  • Inter Urban : 48% - 74%
  • Rural : 27% – 48%
slide-6
SLIDE 6

6

Transport Scotland

Business Case Owner Programme Funder Specification of Outputs Rolling Stock Delivery

Network Rail

Programme Financing Infrastructure Delivery Programme Management Systems Integration

ScotRail

Timetabling Resource Implications Operational Advice

Edinburgh Glasgow Improvement Programme (EGIP)

Industry Stakeholders

slide-7
SLIDE 7

7

Edinburgh Glasgow Improvement Programme (EGIP)

EGIP Scope

1

Network Rail’s Industry Partners

.

DRUMGELLOCH

KEY : Existing Electrified Routes Route Electrified by the Airdrie to Bathgate project EGIP Electrification Proposals Croy Station Turnback Queen Street HL Infrastructure Capacity Dalmeny Chord Edinburgh Gateway Interchange Winchburgh to Dalmeny Upgrade Winchburgh Jcn Enhancement Greenhill Upper & Lower Jcn Enhancement Haymarket to Inverkeithing Signalling Headways Edinburgh Waverley Infrastructure Capacity Haymarket Interchange Stirling Area Stabling Facilities Hyndland Turnback Newton Remodelling EGIP Infrastructure Projects Other EGIP Projects Springburn Remodelling New EMU Depot

slide-8
SLIDE 8

8

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Timescales

  • 1st Tranche : Completed January 2012
  • Review and consider all comments
  • 2nd Tranche : Autumn/Winter 2012 report findings
  • Spring 2013 : Transport and Works Act lodged
slide-9
SLIDE 9

9

Edinburgh Glasgow Improvement Programme (EGIP)

Potentially one of the largest consultations in Britain :

  • Covers two thirds of Scotland’s population
  • 8 Central Scotland Local Authorities
  • 90 MP’s/MSP’s, 298 Councillors and 61 Community Councils
  • 230 meetings over a 6 month period

Consultation Scope

slide-10
SLIDE 10

10

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Media

  • Web page, Email address and help line
  • Radio campaign, advertising and exhibitions
  • Social media
  • Creation of informed groups liaising with the project
slide-11
SLIDE 11

11

EGIP Infrastructure EGIP Electrification GRIP 4 2016 Timetable Rolling Stock Specification + Procurement Car Parking Strategy Current Performance Issues Station Facilities Improvement Integrated Transport Strategy

EGIP SCOPE

Operations Management During works Impact of Electrification Output Scope predetermined Re-franchising Consultation Themes

slide-12
SLIDE 12

12

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : Clackmannanshire Services to Fife Services to Edinburgh Potential new station at Cambus

slide-13
SLIDE 13

13

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : East Dunbartonshire Car Parking Through services to Stirling / Dunblane Improved Edinburgh services Potential new stations at Westerhill and Woodilee

slide-14
SLIDE 14

14

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : Edinburgh

  • South Suburban Line electrification
  • Haymarket Station access / cycling improvements
  • Portobello Jcn improvements
  • Potential new station at Abbeyhill
slide-15
SLIDE 15

15

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : Falkirk

  • Service improvements / review of stopping patterns
  • Impact of proposed electrification works
  • Potential new stations at Grangemouth and Bonnybridge
slide-16
SLIDE 16

16

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : Glasgow

  • Garngad Chord
  • Glasgow to Anniesland Services
  • Enabler for Glasgow Crossrail
  • Hyndland – fully accessible design solution
  • Queen St HL – accessibility / cycling provision
  • Potential new station at Robroyston
slide-17
SLIDE 17

17

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : North Lanarkshire

  • Garngad Chord
  • Croy Station – fully accessible design solution
  • Improved services to Edinburgh
  • Impact of construction activities on the community
slide-18
SLIDE 18

18

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : Stirling

  • New stabling facilities
  • Stirling station improvements
  • Potential new station at Bannockburn
slide-19
SLIDE 19

19

Edinburgh Glasgow Improvement Programme (EGIP)

Consultation Feedback : West Lothian

  • Linlithgow – car parking and platform congestion
  • Overhead line installation
  • Impact of construction activities on the community
  • Potential new station at Winchburgh
slide-20
SLIDE 20

20

Edinburgh Glasgow Improvement Programme (EGIP)

Conclusions / Next Steps

  • EGIP delivers a major enhancement of Scotland’s rail network.
  • NR / TS to close out responses to consultation feedback received.
  • TAWS Order to be lodged in early 2013.
  • NR to commence procurement of contractors to deliver EGIP.
  • Finalise detailed implementation programme.
slide-21
SLIDE 21
slide-22
SLIDE 22
slide-23
SLIDE 23

Airdrie-Bathgate Rail Link

Reconnecting Communities

Ann Glen

slide-24
SLIDE 24
slide-25
SLIDE 25
slide-26
SLIDE 26
slide-27
SLIDE 27
slide-28
SLIDE 28
slide-29
SLIDE 29
slide-30
SLIDE 30
slide-31
SLIDE 31
slide-32
SLIDE 32
slide-33
SLIDE 33
slide-34
SLIDE 34
slide-35
SLIDE 35
slide-36
SLIDE 36
slide-37
SLIDE 37
slide-38
SLIDE 38
slide-39
SLIDE 39
slide-40
SLIDE 40
slide-41
SLIDE 41
slide-42
SLIDE 42
slide-43
SLIDE 43
slide-44
SLIDE 44
slide-45
SLIDE 45
slide-46
SLIDE 46
slide-47
SLIDE 47
slide-48
SLIDE 48
slide-49
SLIDE 49
slide-50
SLIDE 50
slide-51
SLIDE 51
slide-52
SLIDE 52
slide-53
SLIDE 53
slide-54
SLIDE 54
slide-55
SLIDE 55
slide-56
SLIDE 56
slide-57
SLIDE 57
slide-58
SLIDE 58
slide-59
SLIDE 59
slide-60
SLIDE 60
slide-61
SLIDE 61
slide-62
SLIDE 62
slide-63
SLIDE 63
slide-64
SLIDE 64
slide-65
SLIDE 65
slide-66
SLIDE 66
slide-67
SLIDE 67
slide-68
SLIDE 68
slide-69
SLIDE 69
slide-70
SLIDE 70
slide-71
SLIDE 71
slide-72
SLIDE 72
slide-73
SLIDE 73
slide-74
SLIDE 74
slide-75
SLIDE 75
slide-76
SLIDE 76
slide-77
SLIDE 77
slide-78
SLIDE 78
slide-79
SLIDE 79
slide-80
SLIDE 80
slide-81
SLIDE 81
slide-82
SLIDE 82
slide-83
SLIDE 83
slide-84
SLIDE 84
slide-85
SLIDE 85
slide-86
SLIDE 86
slide-87
SLIDE 87
slide-88
SLIDE 88
slide-89
SLIDE 89
slide-90
SLIDE 90
slide-91
SLIDE 91
slide-92
SLIDE 92
slide-93
SLIDE 93
slide-94
SLIDE 94
slide-95
SLIDE 95
slide-96
SLIDE 96
slide-97
SLIDE 97
slide-98
SLIDE 98
slide-99
SLIDE 99
slide-100
SLIDE 100
slide-101
SLIDE 101
slide-102
SLIDE 102

A regional injustice put right

Presentation to RailFuture conference – 16th June 2012

Bill Jamieson and David Spaven

slide-103
SLIDE 103

Today’s presentation

1. Decline, closure & abandonment 1963-1972 2. Wilderness years, then the tide turns 3. Parliamentary progress 2000-2006 4. The abortive DBFM process 5. Network Rail takes over in 2011 6. Looking ahead to 2014/15 re-opening

slide-104
SLIDE 104

1963 – the Beeching Report

  • one of the longest lines threatened
  • Hawick & Gala in highest revenue category
  • passengers & freight in decline
  • up to 5 hours between trains
  • less uproar than in the Highlands
  • Scottish Office / MoT skirmishes
  • conflict with economic plans
slide-105
SLIDE 105

1966 – closure proposal & hearing

  • the whole route to go – 97 miles & 24 stations
  • 508 objectors – but East Suffolk line 1,916!
  • TUCC verdict – “substantial hardship”
  • then 19 months in limbo
  • small stations destaffed
  • dieselisation, but few DMUs
  • service pattern unchanged
slide-106
SLIDE 106

1968 – the final decision

  • 2nd May – Barbara Castle backs closure
  • 6th May – Marsh takes over from Castle
  • 21st May Ministerial Committee meeting:
  • Willie Ross backs Edinburgh-Hawick retention
  • but a majority votes for complete closure
  • 23rd May Ross memo to Harold Wilson:
  • “I would beg you to look at the…consequences”
  • 5th June Wilson memo:
  • “I do not think it would be right to reopen the

the decisions reached by the Committee.”

slide-107
SLIDE 107

Closure: 6th January 1969

  • last train: 21.56 Edinburgh-St Pancras
  • David Steel MP on board
  • Hawick delay while pilot runs ahead
  • the Rev Brydon Maben and the

the Newcastleton blockade

  • David Steel’s appeal to the crowd
  • the train finally departs 2 hrs late
  • the Anglo-Scottish route is dead
slide-108
SLIDE 108

1969-72: a lingering death

  • Hawick trip survives till 25th April
  • the Border Union Railway Co:
  • breathtakingly ambitious
  • commuters / tourism / steam / timber
  • financial projections debatable
  • BR negotiations break down late 1969
  • the last tracks lifted in 1972
  • “by far the largest population

grouping in Britain with no accessible railway services”

slide-109
SLIDE 109

Why was the Waverley Route lost?

  • 1. The Central Borders economic dev. plan:
  • lukewarm support for the railway / roads seen as the priority
  • 2. BR management:
  • the culture of the time was closure = progress
  • no strategic decision 10 years earlier, to develop or rationalise
  • 3. Government structures:
  • no rail powers at Scottish Office
  • 4. ‘Realpolitik’:
  • financial symbolism of the route
  • no marginal constituencies!

5. The campaign:

  • too little / too late / Borders apathy
slide-110
SLIDE 110

Wilderness years, then the tide turns

  • 1975 – BR Edinburgh-Gala re-opening proposal
  • route protection is abandoned
  • Simon Longland’s 1992 motor-bike survey
  • 24 breaches, in particular roads and buildings
  • 66% of rail overbridges extant
  • 74% of road overbridges extant
  • further development threats eg A7 road

“..it is clear that before this asset is irrevocably thrown away, a full comparative economic cost / benefit analysis of the rail investment option for the region which it represents should be carried

  • ut as a matter of urgency..”
slide-111
SLIDE 111

Borders Transport Futures

  • launched 1994 with aim of re-opening the railway
  • Pre-feasibility Study for a N. Borders Rail Link (1994)
  • Edinburgh-Galashiels £28m
  • Pre-feasibility Study for a S. Borders Rail Link (1995)
  • Longtown-Riccarton-Kielder £18m for timber traffic
  • Border Rail Links Study (1995) by Oscar Faber
  • South Borders £20m / North Borders £18m!
  • Railtrack / EWS / First Eng. fund South Borders project development
  • Railtrack pulls out of S. Borders project in 1997
slide-112
SLIDE 112

Campaign for Borders Rail

  • launched in early 1999
  • three conferences & region-wide campaigning
  • 17,200 signatures on petition to Parliament
  • historic visit of Public Petitions Committee to Gala
  • evidence to Bill Committee in 2004-5
  • still campaigning strongly in 2012!
slide-113
SLIDE 113

Rail re-opening goes mainstream

  • 1998 – Borders factory closures
  • Scottish Office picks up BTF North Borders Rail

Link Study

  • rail seen as agent of economic regeneration
  • CBR leading the grassroots campaign
  • 1999 – Scottish Office commissions Scott Wilson

report on re-opening options

  • 1999-2000 – Scott Wilson at work on the study,

examining a ‘wide’ range of options

slide-114
SLIDE 114

Scott Wilson report – 2000

  • heavily ‘steered’ towards CrossRail extension?
  • half-hourly all-stations to Tweedbank / 55 minutes
  • estimated £73m capital cost
  • report did not evaluate:
  • Melrose as the terminus
  • two-tier Regional Express / Inner Suburban service
  • the tourist charter train market
  • 2000 SW report has remained the core spec
slide-115
SLIDE 115

The Waverley Railway Partnership

  • set up 2001 as Waverley Railway Project promoter
  • led by Scottish Borders Council, with Edinburgh &

Midlothian Councils & Sc Borders Enterprise

  • Scottish Executive set up the Councils to be the

‘fall guys’ if the project went pear-shaped?

  • faced many hurdles as the ‘guinea pig’ for rail re-
  • penings under the Scottish Executive
  • without WRP commitment and enthusiasm,

might the project have foundered?

slide-116
SLIDE 116

The Waverley Route Trust

  • established 2002
  • concerns about Waverley Railway Project:
  • escalating capital cost
  • one-size-fits-all timetable / slow journey time
  • lack of provision for charters and freight
  • social enterprise / community model not considered
  • commissioned Corus to undertake the ‘Delivering

an Innovative Borders Railway’ study in 2004

  • Corus endorsed WRT concerns and proposed

alternative spec – but rejected by WRP

slide-117
SLIDE 117

The Waverley Railway (Scotland) Act

  • Waverley Railway Bill C’ttee deliberates for 2 years
  • final report endorses project, with stations at Stow

and Shawfair [but 61-minute journey]

  • The Waverley Railway (Scotland) Act is passed in

June 2006, with just one MSP dissenting

  • estimated re-opening date 2011
  • 2008 – Transport Scotland becomes promoter

and switches from NR to DBFM model

slide-118
SLIDE 118

2009 DBFM pre-qual. document

  • maximum 55 mins journey time to Tweedbank
  • encouragement for freight & charters
  • new structures to accommodate W12 & RA10
  • provision for future electrification
  • passive provision for double track to Gorebridge
  • allow for extension south from Tweedbank
slide-119
SLIDE 119

Progress, but…

  • 2009-11 – advance works
  • 2010 – ‘Mastermind’ clause
  • 2010 – three DBFM bidders

drop to two

  • 2011 – down to one DBFM bidder
  • 2011 – Network Rail takes over
  • 2012 – further advance works
slide-120
SLIDE 120

Where are we now?

  • Transport Scotland and Network Rail completing

due diligence for ‘statutory undertaker’

  • final deal expected in August – £235m-£295m
  • Tweedbank station to be marginally relocated but

no ‘passive provision’ for freight / extension south

  • still no provision for charters:
  • Tweedbank platform tracks too short
  • no paths other than evenings / Sundays
  • CBR pressing hard on charters

and the community rail dimension

slide-121
SLIDE 121

The overall verdict?

  • a regional injustice put right after 45 years
  • 31 miles – the longest British rail re-opening
  • a step change in public transport – 50 minutes

Edinburgh-Gala v. 86 minutes by bus

  • well-located stations, but Melrose should have

been the terminus

  • better dialogue with campaigners

would have produced a better scheme

  • book your ticket for 2014!
slide-122
SLIDE 122

Questions and discussion

slide-123
SLIDE 123
slide-124
SLIDE 124

Route knowledge

slide-125
SLIDE 125
slide-126
SLIDE 126
slide-127
SLIDE 127

Railfuture 2012

Stirling – Alloa – Kincardine Railway

slide-128
SLIDE 128

Brief History of the Route

  • 1850 –

1851 Rail Link Dunfermline and Alloa

  • 1852 Alloa –

Stirling Link

  • 1893 Kincardine

Line

  • 1968 Alloa and Cambus
  • 1983 Alloa – Kincardine
  • 1993 Stirling - Cambus
  • 1996 Kincardine-

Longannet

  • 2005 SAK construction

commences

slide-129
SLIDE 129
slide-130
SLIDE 130

Fit with Local Planning and Transport Policy

  • 1970’s-

Clackmannanshire County Council

  • 1980’s-

Clackmannanshire District Council

  • 2002- Clackmannanshire

Finalised Local Plan

  • 2001 – 2004-

Clackmannanshire Transport Strategy

slide-131
SLIDE 131

Stirling- Alloa- Kincardine

  • Re-opening 21km of railway

between Stirling Station and Longannet Power Station

  • New Railway Station at Alloa
  • Hourly Passenger Services

between Alloa, Stirling and Glasgow, services on to Edinburgh

  • 17 passenger trips and 15 freight

trips in each direction per day

  • Freight link from Hunterston and

west of Scotland to Longannet Power Station

Alloa Station 2008

slide-132
SLIDE 132

National Strategic Transport Objectives

  • Improves the strategic accessibility
  • f Clackmannanshire
  • Alleviates capacity constraints on the

central Scotland rail network

  • Contributes to the reduction in

carbon emissions associated with road borne freight transport

  • Key link in the strategic rail network

to allow increased flexibility for freight transport

  • More efficient freight route from the

West of Scotland to Longannet Power Station

  • Reduces road congestion along the

route – both passenger and freight traffic

Alloa Station site from the West 2004

slide-133
SLIDE 133

Local Policy Objectives

.

Development Plan Vision

  • Promote Inclusion
  • Promote alternatives to private car
  • Environmental protection

Corporate Priorities

  • Improved Transport infrastructure
  • Protect and enhance the built

environment

  • Good Road and Rail Links
  • Note the new flats and town houses to the north of

the line a number of which have been purchased by First Engineering (one of the main contractors) personnel who have been impressed by the scenery, local facilities and the rail link to Glasgow

Alloa Station from the West 2008

slide-134
SLIDE 134

Strategic Overview

SAK implements a number of the key objectives

  • f the National Transport Strategy. The Local

Transport Strategy for Clackmannanshire and the Vision set out in the Clackmannanshire Local Plan

National Objectives Scotland’s Transport Future

Local Transport Strategy- Development Plan Vision

Clackmannanshire Corporate Priorities

STIRLING - ALLOA - KINCARDINE RAILWAY

slide-135
SLIDE 135

Economic Development Social Inclusion

  • SAK is an essential key plank in the

Economic Development Strategy for

  • Clackmannanshire. It is key to the

regeneration of Alloa Town Centre

  • Rail links from Alloa to Stirling,

Glasgow and Edinburgh contribute significantly to the improved connectivity that is essential for the economic well being of Clackmannanshire.

  • SAK provides Clackmannanshire

residents with significantly improved access to opportunities for employment, further education and

leisure activities.

“One of the keys to building any new business is

  • location. Lawscript based itself in Alloa

specifically to recruit locally from within

  • Clackmannanshire. As the company continues to

grow it is clear that our net will have to be cast further afield. The reintroduction of a rail link to Alloa will mean we can attract employees from

  • ther areas in the Central belt.” Lorna Edwards

Managing Director, Lawscript A key objective of this Council in terms of the economic “regeneration of the area, the reopening of the Stirling-Alloa-Kincardine rail line in 2008 is a tremendous boost opening Clackmannanshire up to the world. The economic effects of the railway are already being felt in the county” Janet Cadenhead, Leader Clackmannanshire Council “The advent of passenger services linking Alloa to the major cities of Glasgow and Edinburgh will allow greater tourism travel opportunities as well as encouraging economic growth.“ Paul Sutton, Chair Clackmannanshire Tourism Association

slide-136
SLIDE 136

Regeneration

The Project has regenerated Alloa Town Centre. A former derelict brewery site- a symbol of Alloa’s former decline – has been replaced by the new railway station, station square, new public realm and impressive public art. The station’s strong visual image is symbolic of Alloa’s regeneration.

slide-137
SLIDE 137

Integration

Alloa Station - a multi modal transport interchange and public transport focus for the town.

  • A new, high quality, fully

DDA compliant walkway links Alloa Railway Station with Alloa Town Centre and Alloa bus station. The station adjacent to bus and taxi services.

slide-138
SLIDE 138

Usage

  • Original Business Case forecast

80,000 passenger trips per annum.

  • Revised upwards to 155,000 in

light of better than expected patronage on Larkhall- Milngavie railway.

  • Actual usage indicates that in its first

year SAK will generate

400,000 passenger journeys

slide-139
SLIDE 139

Roles and Responsibilities

  • Transport Scotland
  • Clackmannanshire

Council

  • Network Rail
  • TOCs and FOCs
slide-140
SLIDE 140

The Bill Process

  • First Rail Bill
  • Core Documents
  • Consultations
  • Pre construction condition

surveys

slide-141
SLIDE 141

Core Documents

  • Promoters statement
  • Memoranda on need
  • Memorandum on Human

rights

  • Explanatory Note on

Other Railway Processes

  • Environmental Statement
slide-142
SLIDE 142

Environmental Impact Assessment

  • Assumptions
  • Mitigation measures
  • Peer Review
  • Committee conclusions
slide-143
SLIDE 143

Dealing with Noise and Vibration

  • Mitigation through design
  • Post construction

mitigation

  • Rationale for timing
  • Updating the

Environmental Statement

  • Basis for Measurement
  • Timescale for completion
slide-144
SLIDE 144

Railway Operations

  • Limitations of SAK Act
  • Evidence to Bill

Committee

  • Implications of Open

Access Railway

slide-145
SLIDE 145

Noise and Vibration

  • Environmental Statement
  • FOC requirements
  • Dealing with the fallout
slide-146
SLIDE 146

Facts and figures

  • 22,630m plain line and cable troughing
  • 33,846 sleepers
  • 79,094 tonnes ballast – pink Scottish granite
  • 29 Signals
  • 29 AWS units
  • 19 Overbridges
  • 13 Underbridges
  • 4 Footbridges
  • 3 public level crossings (waterside, Blackgrange, Cambus)
  • 3 Private level crossings (Manor Neuk, Manor Powis, & Kincardine)
  • 1 Superstructure (the Forth Viaduct)
  • A new station
slide-147
SLIDE 147

Challenges

  • Geotechnical
  • Grouting
  • Level crossing design
  • Cambus
  • Cuttings and embankments
  • Ballast
  • Signals
  • Coal trains
slide-148
SLIDE 148

Summary of benefits

  • 13km new line
  • Extension ot Alloa’s eastern

relief road

  • Freight traffic speeds
  • Reduction in congestion
  • Road freight
  • The Clacks effect
slide-149
SLIDE 149

Environment

SAK will enable more efficient delivery of coal to Longannet by rail. The reduction on CO2 emissions resulting from this modal shift are set out below. “I eagerly anticipate seeing a reduction in traffic congestion on the roads leading to Stirling as car users switch to using the rail service” Councillor Graham Reed Stirling Council “Freight use for Longannet Power Station will help keep the County’s roads free of heavy goods traffic to make tourist visits more enjoyable and stress free” Paul Sutton Current SAK and Current Road deliveries SAK and all rail delivered Lorry Journeys p.a. 15,600 15,600 Rail Journeys p.a. 3,680 2,333 2,666 Rail CO2 emissions p.a 119,000 tonnes 100,800 tonnes 115,200 tonnes Road CO2 emissions p.a. 14,500 tonnes 14,500 tonnes Total CO2 emissions p.a 133,500 tonnes 115,300 tonnes 115,200 tonnes

slide-150
SLIDE 150

SAK and EGIP

  • Upgrade Central Scotland’s

Rail Links

  • New Service levels
  • Journey time improvements

Alloa/Dunblane

  • Additional path per hour

Stirling – Alloa (passenger)

  • Alloa – Glasgow half hourly –

10minute reduction to journey time

  • Electric units
  • Possibility of station at

Cambus

slide-151
SLIDE 151

Local children race the train on

  • pening day. Community

participation was exceptional with

  • ver 1200 people riding the route on
  • pening day.
slide-152
SLIDE 152

QUESTIONS

slide-153
SLIDE 153