economic regulation authority
play

Economic Regulation Authority www.era.wa.gov.au Western Australia - PowerPoint PPT Presentation

Economic Regulation Authority www.era.wa.gov.au Western Australia The Economics and Regulation of Gas Pipelines K Peter Kolf General Manager Economic Regulation Authority 10 August 2005 Introduction Pipeline Operations Pipeline


  1. Economic Regulation Authority www.era.wa.gov.au Western Australia The Economics and Regulation of Gas Pipelines K Peter Kolf General Manager Economic Regulation Authority 10 August 2005

  2. Introduction • Pipeline Operations • Pipeline Design • Looping • Pressure management

  3. AlintaGas Distribution Owner: AlintaGas Pipeline Networks Pty Ltd Networks Comprises approx. 10,500 km of Gas distribution pipelines and associated facilities. There are two networks in Albany and Kalgoorlie that are not covered by the Code. Access Arrangement Approved 18/7/2000 Geraldton Lateral Review due 1/4/2004

  4. Dampier to Bunbury Natural Gas Owner: Epic Energy Pipeline (WA) Transmission Pty Ltd Commissioned: 1984 Length: 1845 km Diameter: 660 mm Capacity: 600 TJ/d Carnarvon Lateral Average MDQ: 530 TJ/d Final Decision on Dampier to Bunbury Natural Gas Pipeline proposed Access (DBNGP) Arrangement issued 23/5/03. Geraldton Lateral Assessing the Revised Access Arrangement received 8/8/03

  5. Goldfields Gas Pipeline Owners: Southern Cross Pipelines Australia Pty Ltd, Southern Cross Pipelines (NPL) Australia Pty Ltd and Duke Energy International Commissioned: 1996 Length: 1378 km Newman Lateral Diameter: Telescopic Carnarvon Lateral 400 mm to 350mm Capacity: 100 TJ/d Dampier to Bunbury Natural Gas Pipeline Average MDQ: 98 TJ/d (DBNGP) Goldfields Gas Pipeline (GGP) Draft Decision is being amended. Geraldton Lateral Application for revocation lodged with NCC on 27/3/2003

  6. Tubridgi Owner: SAGASCO & Pan Pipeline Pacific Petroleum System Comprises two pipelines the Griffin and the Tubridgi Pipelines. Tubridgi Pipeline Commissioned: 1992 Length: 87.5 km Diameter: 168 mm Tubridgi Pipeline Capacity: 30 TJ/d System Newman Lateral Griffin Pipeline Carnarvon Lateral Commissioned: 1993 Length: 87 km Dampier to Bunbury Natural Gas Pipeline Diameter: 273 mm (DBNGP) Goldfields Gas Pipeline (GGP) Capacity: 90 TJ/d Geraldton Lateral Combined Average MDQ of about 30 TJ/d Access Arrangement approved on 19/10/2001 Review due 19/1/2006

  7. Kambalda Lateral Owner: Southern Cross Pipelines Australia Pty Ltd Commissioned: 1996 Length: 44 km Diameter: 219 mm Tubridgi Pipeline Capacity: 15 TJ/d System Throughput: 12 TJ/d Newman Lateral Carnarvon Lateral Extension of time to Dampier to Bunbury submit an Access Natural Gas Pipeline (DBNGP) Goldfields Gas Pipeline (GGP) Arrangement granted to 1 July 2004 Geraldton Lateral Kambalda Lateral

  8. Pipelines not covered Pipelines Not Covered: or regulated • Parmelia Pipeline • Mid West Pipeline by the Code • Harriet Pipelines North West Shelf Pipeline Cape Lambert Pipeline • Pilbara Energy Project Harriet Pipelines Pipeline Thevenard Island Pilbara Energy Project Pipeline Gas Pipeline (PEPL) • Cape Lambert Pipeline Griffin Offshore Pipeline Tubridgi Pipeline • Various GGP laterals System Newman Lateral • GGP to Mt Keith Carnarvon Lateral Carnarvon Lateral • GGP to Leinster Power Station Dampier to Bunbury Natural Gas Pipeline • GGP to Kalgoorlie (DBNGP) Goldfields Gas Pipeline (GGP) Power Station Mid West Pipeline Geraldton Lateral Unprocessed gas Parmelia Pipeline Kambalda Lateral pipelines are not regulated by the National Gas Agreement.

  9. Schematic of Pipeline Capacity Total Capacity Spot Capacity Interruptible Capacity (92%) Spot Capacity Firm Capacity (98%) Utilised Firm Capacity Time

  10. Operational Surcharges • Peaking Surcharge (hourly) – 20% MDQ margin • Overrun Surcharge (daily) – 10% MDQ • Nominations Surcharge (daily) – +/- 10% MDQ • Balancing Surcharge (daily on-going accumulation) – +/- 8% MDQ margin

  11. Operational Services • Peaking Service (hourly) • Overrun Service (daily) • Nominations Service (daily) • Park and Loan (daily on-going accumulation) • Secondary market – Spot – Bare transfer – Transfer of capacity (Subject to availability)

  12. Pipeline Design • Pipeline Diameter – Future demand – Length of the pipeline – Distribution of load – Operating pressure (MAOP) – Thickness of pipeline (material & pressure) • Compression – Location (determines power and fuel usage)

  13. Steps in Pipeline Development 1. Free Flow 2. Additional Compression 3. Additional Compression & Looping 4. Looping 5. Looping and additional compression Repeat from Step 2

  14. Pipeline Development Cycle Development Cycle of Pipeline Cost per $/GJ Compression Compression & Looping & Looping Ave Cost Compression Compression Looping Capacity TJ/d

  15. Principle of Looping • Bigger diameter • Higher Max Allowable Op Pressure (MAOP) – once fully looped can be operated independently • Looping of each section of the pipeline (between 2 compressor stations) starts at the beginning of the section • Objective is to bring the discharge pressure of the downstream compressor to the MAOP

  16. Pipeline Development Cycle Development Cycle of Pipeline Cost per $/GJ Compression Compression Ave Cost & Looping & Looping Incremental Cost Compression Looping Compression Capacity TJ/d

  17. Pressure Profile Looping C MAOP o Minimum m contracted delivery p pressure r e s s i o CS 1 CS 2 CS 3 CS 4 n Distance Inlet Location of Location Contracted Load

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend