SLIDE 1
East Somerville Community School Turf Renovation Projects Mayor - - PowerPoint PPT Presentation
East Somerville Community School Turf Renovation Projects Mayor - - PowerPoint PPT Presentation
Michael E. Capuano Field & East Somerville Community School Turf Renovation Projects Mayor Joseph A. Curtatone Councilor Matthew McLaughlin Informational Meeting: June 12, 2019 Warner Larson Landscape Architects David Warner, Principal
SLIDE 2
SLIDE 3
Overview
- Existing Conditions of the Fields
- Field Design
- Materials
- Schedule
SLIDE 4
- Field surfaces in poor condition
- Safety concerns
- Drainage issues
- Lighting
Existing Conditions
SLIDE 5
Aerial view
Existing Conditions ESCS
SLIDE 6
Surfaces in poor condition
Existing Conditions ESCS
Safety issues Drainage issues
SLIDE 7
Athletic field layout
ESCS Field Design
SLIDE 8
Athletic field layout and striping
ESCS Field Design
SLIDE 9
Athletic field lighting layout
ESCS Field Design
SLIDE 10
Aerial view
Existing Conditions Capuano Field
SLIDE 11
Existing Conditions Capuano Field
Surfaces in poor condition
SLIDE 12
Athletic field layout & striping layout
Capuano Field Design
SLIDE 13
- Synthetic Turf Carpet
- AstroTurf – Rhino Blend
- Dual fiber turf
- Synthetic Turf Infill
- Plant based infill material
- Sand
- Synthetic Turf Shock Pad
- 17mm
- Expanded polypropylene
Materials
SLIDE 14
- Athletic Field Lighting (Only at ESCS)
- LED fixtures
- 40’ Pole height
Materials
SLIDE 15
- Athletic Field Lighting at Winter Hill
Materials
SLIDE 16
Schedule
- June 19 fields closed/construction begins
- August 29 construction complete/fields open
SLIDE 17