Dormay Street & King Georges Park Community Liaison Working - - PowerPoint PPT Presentation

dormay street king george s park
SMART_READER_LITE
LIVE PREVIEW

Dormay Street & King Georges Park Community Liaison Working - - PowerPoint PPT Presentation

Dormay Street & King Georges Park Community Liaison Working Group 11 July 2019 DORMAY STREET Kevin Dollard Section Manager Frogmore Connection Tunnel - Location Works Update: TBM Drive March 2019 May 2019 TBM Charlotte was


slide-1
SLIDE 1

Dormay Street & King George’s Park

Community Liaison Working Group

11 July 2019

slide-2
SLIDE 2

DORMAY STREET Kevin Dollard – Section Manager

slide-3
SLIDE 3

Frogmore Connection Tunnel - Location

slide-4
SLIDE 4

Works Update: TBM Drive March 2019 – May 2019

  • TBM Charlotte was launched and fully

assembled with all 9 gantries

slide-5
SLIDE 5

Works Update: TBM Drive June 2019

  • TBM Charlotte advanced to Ring 111 and ready for dual track installation
slide-6
SLIDE 6

Works Update: TBM Drive June/July 2019

  • Dual track installed and pit bottom lift complete for full production mode
slide-7
SLIDE 7

Works Update: CSO Interception March 2019 – May 2019

  • All Riverwall strengthening complete at Dormay Street
slide-8
SLIDE 8

Works Update: CSO Interception June 2019

Keltbray remobilised to complete piling for interception chamber

slide-9
SLIDE 9

Works Update: CSO Interception July 2019

Cofferdam excavation commenced

slide-10
SLIDE 10

Dormay Street 3D Overview

slide-11
SLIDE 11

Landscaping

  • Application for the permanent above

ground structures submitted to London Borough of Wandsworth on 24 June 2019

  • Determination of application due by

19 August 2019

  • Deadline for public comments 15

July 2019

slide-12
SLIDE 12

Look Ahead (Next 6 Months)

*Core working hours 8am-6pm Monday – Friday and 8am-1pm Saturday .. One hour start up and shut down periods either side of working hours

slide-13
SLIDE 13

Predicted and Actual Heavy Goods Vehicles (HGVs) coming intosite: March – June 2019

5 10 15 20 25 30 March April May June

Predicted and Actual Heavy Goods Vehicle coming into site (Monthly Daily Average) March – June 2019

Predicted Actual

slide-14
SLIDE 14

Predicted Heavy Goods Vehicles(HGVs) coming intosite: July to December 2019

2 4 6 8 10 12 July August September October November December

Predicted Heavy Goods Vehicles (HGVs) coming into site (Monthly Daily Average) July – December 2019

slide-15
SLIDE 15

QUESTIONS?

slide-16
SLIDE 16

KIN KING GEORGE’S PARK RK Kevin Do Dolla lard rd – Sect ction

  • n Manag

nager er

slide-17
SLIDE 17

King George’s Park February 2019

  • Shaft excavation and

Sprayed Concrete Lining

  • Cofferdam finished

excavation and casting base

slide-18
SLIDE 18

King George’s Park March 2019

  • Shaft excavation and

Sprayed Concrete Lining complete

  • Reinforcement for base

plug shaft complete

slide-19
SLIDE 19

King George’s Park April 2019

  • Excavation and temporary

propping for cofferdam complete

  • Blinding layer poured
slide-20
SLIDE 20

King George’s Park May 2019

  • Shaft base slab, benching

and eye complete ready for the arrival of TBM Charlotte

  • Bottom waling frame

removed from cofferdam for base slab to be cast

slide-21
SLIDE 21

King George’s Park June 2019

  • Mobilisation of Kilnbridge
  • n site to complete

reinforced concrete works in cofferdam

  • Base slab in cofferdam

complete

slide-22
SLIDE 22

King George’s Park July 2019

  • Back-blinding for walls in

cofferdam complete

  • Reinforcement for walls

in progress

slide-23
SLIDE 23

King George’s Park 3D Overview

slide-24
SLIDE 24

Landscaping

  • Application for the permanent above ground

structures submitted to London Borough of Wandsworth on 03 June 2019

  • Determination of application due by 29 August

2019

  • Deadline for public comments closed on 24

June 2019

slide-25
SLIDE 25

Temporary Works – Neville Gill Close Temporary Traffic Management Scheme

  • Area required for Temporary Works installation
  • 6 month temporary Traffic Management scheme to be confirmed
slide-26
SLIDE 26

*Short Term Look Ahead

*Core working hours 8am-6pm Monday – Friday and 8am-1pm Saturday .. One hour start up and shut down periods either side of working hours

slide-27
SLIDE 27

Predicted and Actual Heavy Goods Vehicles (HGVs) coming intosite: March – June 2019

1 2 3 4 5 6 7 8 9 March April May June

Predicted and Actual Vehicle Movements (Monthly Daily Average) March - June 2019

Predicted Actual

slide-28
SLIDE 28

Predicted Heavy Goods Vehicles (HGVs) coming into site: July to December 2019

2 4 6 8 10 12 July August September October November December

Predicted Heavy Goods Vehicles (HGVs) coming into site (Monthly Daily Average) July - December

slide-29
SLIDE 29

COMM OMMUNITY ENGAGEMENT

slide-30
SLIDE 30

Community Engagement

  • 1 complaint / enquiry received for King George’s Park since

last meeting – This was a general enquiry requesting for project end date

  • No complaints / enquiries received for Dormay Street since last

meeting Enquiry was responded to within 24 hours

slide-31
SLIDE 31

20

HOW TO MAKE A CLAIM IF YOU ARE AFFECTED BY TIDEWAY’S WORK

Who do I go to for advice?

  • Independent Advisory Service (IAS) Helpline for independent advice:

0800 917 8845 or info@tidewayias.co.uk

  • Tideway’s Compensation Officer

, Louise Walsh, for personal assistance and advice: via Tideway Helpdesk 08000 30 80 80 or helpdesk@tideway .london or direct 07971 077165 or louise.walsh@tideway .london How do I submit my claim?

  • Louise can submit your claim to the Independent Compensation Panel (ICP)
  • n your behalf, or
  • Y
  • u can submit your claim direct to the ICP: admin@tidewayicp.london
  • The IAS can send you a claim form, or you can download a claim form off the

Tideway website: www .tideway .london/help-advice/compensation- information/Independent-Compensation-Panel

slide-32
SLIDE 32

Site Visit by Rt Hon Justine Greening

slide-33
SLIDE 33

33

BMB Tideway West

Community Investment

slide-34
SLIDE 34

BMB Tideway West – Women in Engineering Video available to view https://www.youtube.com/watch?v=r5rYBQmaLmU

slide-35
SLIDE 35
  • Dormay Street received Considerate

Constructors Scheme Bronze award

  • Tideway Awards – King George’s Park

Fluming Works

  • Morgan Sindall Allstars - Best Practice for

Diversity and Inclusion

  • Morgan Sindall Allstars– RAG Zone System

Site Awards

slide-36
SLIDE 36

QUES ESTIONS?