Meeting #17 Wednesday 4 September, Seasons Botanic Gardens
DOMAIN COMMUNITY REFERENCE GROUP
1
DOMAIN COMMUNITY REFERENCE GROUP Meeting #17 Wednesday 4 September, - - PowerPoint PPT Presentation
DOMAIN COMMUNITY REFERENCE GROUP Meeting #17 Wednesday 4 September, Seasons Botanic Gardens 1 WORKS UPDATE 2 ANZAC STATION PROGRAM 2019 3 PROGRESS UPDATE NORTHERN SECTION 4 NORTHERN SECTION TIME-LAPSE 5 CURRENT AND UPCOMING WORKS
Meeting #17 Wednesday 4 September, Seasons Botanic Gardens
DOMAIN COMMUNITY REFERENCE GROUP
1
2
3
4
5
Under the roof slab 6
7
8
9
10
11
12
complete 28 August
from Albert Road site shed complex
closure drainage works
13
14
15 Current works Upcoming works Temporary closure Cyclists dismount Overnight closure
Bowen Lane
16
will be shut for approximately three weeks from the 13 September.
the Hallmark who would normally approach their carpark via Kings Way - Albert Road - St Kilda Road - Park Street.
Way - Bowen Crescent - St Kilda Road – Park Street.
Park Street/St Kilda road traffic lights is not an illegal manoeuvre.
17
18
Anzac Station site is split into the northern and southern sections
through the middle
sections.
19
construction of the middle box.
sections of the station box.
replace trams while St Kilda Road is realigned
cyclists
20
21
Day
Daytime/evening works 7am – 10pm
Nighttime works 10pm-6am Nighttime Noise
Sunday 13 None (Melbourne marathon)
< 65 dB
Monday 14
> 75 dB
Tuesday 15
Wednesday 16
Thursday 17
65-75 dB
Friday 18
Saturday 19
Sunday 20
Day Daytime works Nighttime works
Noise
Monday 21
Cable pulling (park street) 65-75 dB Tuesday 22
< 65 dB Wednesday 23
Thursday 24
Friday 25
wires) Saturday 26
Sunday 27
Trams resume
Vibratory roller monitoring conducted in the northern section 24
Limit Monitored Results NV8 5mm/s 0.62mm/s NV11 Day 0.4 0.31 NV11 Night 0.2 Will be monitored
NV11 NV8
25
per April 2018 occupation)
Laying of new tram tracks April 2018
26
running over the former southern station box
the new ‘middle box’ (yellow section)
St Kilda Road
configuration, however some site sheds will be removed.
27
28
Presented by: Leah Bygraves, Project Manager, MTP Tram Works Date: 4 September 2019
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
Level 3, 555 Bourke Street, Melbourne VIC 3000 yarratrams.com.au
48
49 Building Unmitigated Predicted Noise Level dB LAeq(15min) Evening noise guideline target (NV6) Measured Tuesday 27 August (first day of extended hours)
North Box Excavation: 10pm-12am 50
10pm to midnight works Lights out at midnight
No CYP works underway 51
52
Lighting up to 10pm (excavation from surface) Lighting 10pm to midnight (excavation and strutting below ground)
North Box excavation on surface until 8pm (3 excavators working) 53
Final Pour and D-Wall Breakout 54
Noise levels inside and outside the north box 55 LAeq15 Reduction LAeqMax Reduction Inside Box 88.5 104.3 Surface of Box 71.2 17.3 83.0 21.3 Domain 67.0 21.5 69.1 35.2 Hallmark 62.2 26.3 65.9 38.4
Albert Reserve Monitor 56
57
58
59
60 Artists impression of the acoustic shed
and light spill during 24-hour tunnelling activities
to lower in:
materials
61 Artist's impression of inside the acoustic shed
62
63
64
St Kilda Road works
business feedback
(CoPP); and Heritage Victoria on a tree protection plan
been installed, including for programming community and arts activities.
Artists impression of Albert Road Pop-up park
65
installed later this year, along part of Domain Road
planting to occur onsite
guide planting
been installed, to help inform other potential place making activities.
Artists impression of Domain Road Pop-up park
66