District Energy System Program Options Report August 16 th 2018 DES - - PowerPoint PPT Presentation

district energy system program options report august 16
SMART_READER_LITE
LIVE PREVIEW

District Energy System Program Options Report August 16 th 2018 DES - - PowerPoint PPT Presentation

District Energy System Program Options Report August 16 th 2018 DES Project Summary FVB responded to, and was hired after a Request for Proposal (RFP) issuance in 2017 FVB prepared a comprehensive evaluation report for Metro to summarize


slide-1
SLIDE 1

District Energy System Program Options Report August 16th 2018

slide-2
SLIDE 2

DES Project Summary

— FVB responded to, and was hired after a Request for

Proposal (RFP) issuance in 2017

— FVB prepared a comprehensive evaluation report for Metro

to summarize the in-depth assessment of the economic viability of the DES

— Options/recommendations are provided for the future of

the system

— Four scenarios are developed and compared

slide-3
SLIDE 3

DES Project Scenarios

— FVB developed and analyzed four primary DES scenarios:

— No Growth (Business as Usual (BaU)) scenario

— Based on existing operations with little or no growth

— Growth scenario

— Based on expanding the system capabilities and customer base — Two different and not mutually exclusive expansion options explored

— Internal management and operations option

— Metro retains ownership and internally manages and operates DES

— Business Exit case

— Valuations if Metro exits the business

slide-4
SLIDE 4

DES Project Scenarios Overview

— FVB evaluated options for the future of the DES, but

no specific option is favored or recommendation explicitly given

slide-5
SLIDE 5

DES Project Key Takeaways

— Regardless of the ownership of DES, an active management

structure that takes ownership, has accountability, and encourages growth will need to be put in place

— It will be necessary to incorporate an effective marketing scheme

into the management structure to successfully capture growth

  • pportunities

— New customers should sign contracts that do not tie debt service

to customer revenues, and existing customer contracts need to be revisited and restructured to allow additional capital to flow to the DES to allow for system growth, Energy Generation Facility (EGF) maintenance and improvements, and additional capital expenditure (CAPEX) needs

slide-6
SLIDE 6

Scenario Overview

— DES currently receives a yearly subsidy from Metro in

the form of the Metro Funding Amount (MFA) – Fiscal Year (FY) 2019 MFA is $1,640,300

— The MFA will go down over time in any scenario, but at

different rates

— NPV (Net Present Value) is the difference between the

present value of the benefits of a project and its costs.

slide-7
SLIDE 7

BaU Scenario: Takeaways

— NPV of future MFAs discounted at 4.33%:

— $4.9 MM without additional CAPEX — $10.4 MM with additional CAPEX

— Sales value will decrease over time:

— Energy Generation Facility (EGF) equipment will age

and require additional CAPEX

— Contracts will move towards expiration — Potential additional growth opportunities will be missed

slide-8
SLIDE 8

BaU Scenario: CAPEX Requirements

$3,292,300 $687,500 $577,500 $2,142,800 $495,000 $0 $500,000 $1,000,000 $1,500,000 $2,000,000 $2,500,000 $3,000,000 $3,500,000 2019 2020 2021 2022 2023

CAPEX Requirements Fiscal Year

CAPEX requirements are estimated and subject to revision. $495,000/year is assumed after starting in 2023.

slide-9
SLIDE 9

BaU Scenario: The Metro Funding Amount (MFA) Over Time

  • 500

1,000 1,500 2,000 2,500 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

USD (in 000's) Year

MFA MFA with CAPEX

A 10% reduction in System Operator (SO) costs beginning in Fiscal Year 2019 is assumed.

slide-10
SLIDE 10

Growth Scenario: Energy Generation Facility (EGF) Expansion

— Expand the existing EGF to its maximum site capacity

by serving additional customers in the growing SoBro area

slide-11
SLIDE 11

Growth Scenario: Thermal Energy Storage (TES) Tank

— Construct a TES to serve additional customers in the

downtown area

slide-12
SLIDE 12

Growth Scenario: Takeaways

— Promising option

— Will require substantial upfront capital investment

— Energy Generation Facility (EGF) Expansion

— Present day capital cost: $52.7 MM — Investment has a positive return but negative cash flows would

need to be funded for the first eight years

— Thermal Energy Storage (TES) Expansion

— Present day capital cost: $38.5 MM — Investment has a positive return but negative cash flows would

need to be funded for the first five years

slide-13
SLIDE 13

Growth Scenario: The MFA Over Time

— The Growth scenario generates a sustained cash

surplus starting in 2031, consequently:

— Contributes to the value of the DES in the long run and

demonstrates promise to a potential acquirer.

— Does not contribute to a more rapid decline of the MFA.

slide-14
SLIDE 14

Internal Management and Operations Option: Takeaways

— Possible cost savings and operational efficiencies to be

gained could yield a 19% reduction in annual

  • perations & maintenance (O&M) costs enabling the

MFA to be eliminated faster

— A well-defined transition plan, management structure,

and capital plan are needed

slide-15
SLIDE 15

Internal Management and Operations Option: The MFA Over Time

  • 500

1,000 1,500 2,000 2,500 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027

USD (in 000's) Year

MFA MFA with CAPEX

slide-16
SLIDE 16

Business Exit Case: Takeaways

— Sale of the DES is likely to repay all existing debt

  • bligations

— The MFA will no longer be required

slide-17
SLIDE 17

Business Exit Case: Valuation Metrics

— Potential growth — CAPEX requirements (based on the age and condition

  • f the system)

— Customer contracts (structure and term) — Commodity risk (mitigated by pass-through contract

provisions)

slide-18
SLIDE 18

Business Exit Case:

DES Market Valuation Range with Reduced System Operator Costs and System Growth

Valuation* Valuation Net of Debt* $46.7 MM

  • $4.9 MM

$56.1 MM $4.5 MM $65.4 MM $13.8 MM

*DES net debt as of the end of FY 2017 is $51.6 MM.

An active market for DE assets and strong market participants suggest that the higher valuation range may be achieved.

slide-19
SLIDE 19

DES Project Summary

— FVB developed and analyzed four primary DES scenarios:

— No Growth (Business as Usual (BaU)) scenario

— Based on existing operations with little or no growth

— Growth scenario

— Based on expanding the system capabilities and customer base

— Internal management and operations option

— Metro retains ownership and internally manages and operates DES

— Business Exit case

— Valuations if Metro exits the business

slide-20
SLIDE 20

Summary of Scenarios

BaU Scenario

  • CAPEX funding not adequate
  • Sales value will decrease over time
  • Will continue to require

subsidization through FY 2021 Growth Scenario

  • Two promising and not mutually

exclusive growth options

  • Will require substantial upfront

capital investment Internal Management and Operations Option

  • Possible cost savings and operational

efficiencies to be gained could yield a 19% reduction in annual operations & maintenance (O&M) costs

  • A well-defined transition plan,

management structure, and capital plan are needed Business Exit Case

  • Sale of the DES is likely to repay all

existing debt obligations

  • The MFA will no longer be required
slide-21
SLIDE 21

Questions?