Design-Build Institute of America Western Pacific Region Mark Hovatter, Chief Facilities Executive Los Angeles Unified School District Thursday, October 20, 2016 Los Angeles, California Summar y F utur e Bo nds State L AUSD L ACCD


  1. Design-Build Institute of America Western Pacific Region Mark Hovatter, Chief Facilities Executive Los Angeles Unified School District Thursday, October 20, 2016 Los Angeles, California

  2. Summar y • F utur e Bo nds State L AUSD L ACCD • Pr o je c ts Cur r e ntly Unde r way • Upc o ming Pr o je c ts • Po te ntial F utur e De sign-Build Pr o je c ts • L AUSD De sign-Build Pr o c e ss • Ac c e le r ate d De live r y

  3. Cur r e ntly Unde r way  Amo unt - $2.8 Billio n Appr o ve d by the Bo ar d  Antic ipate Ano the r $1 Billio n by De c e mbe r 2016  Co mpr e he nsive Mo de r nizatio ns E le ve n have be e n appr o ve d Ano the r 10-15 pr o je c ts sho uld be appr o ve d by De c e mbe r

  4. Why De sign-Build Pr o c ur e me nt? • Co llabo r ative Ar c hite c t / Co ntr ac to r T e am • Pr imar ily Ne w Co nstr uc tio n and Site Wo r k • E xpe dite Pr o je c ts

  5. Cur r e nt De sign-Build Pr o je c ts • Po r te r Ranc h Co mmunity Sc ho o l Additio n Pr o je c t - Appr o ximate ly $10.8 Millio n • Inte r natio nal Studie s L e ar ning Ce nte r Additio n Pr o je c t - Appr o ximate ly $29.4 Millio n d Str • 93 r e e t E le me ntar y Sc ho o l F o o d Se r vic e Upgr ade Pr o je c t - Appr o ximate ly $7.4 Millio n

  6. $2.8 Billion in Boar d- Appr ove d Constr uc tion Pr oje c ts

  7. Appr o ve d Pr o je c ts - Cate go r ie s PROJECT TYPE BUDGET Comprehensive Modernization 1,420,794,936 HVAC 290,546,064 IT Network Upgrade 231,282,382 Seismic Modernization 212,396,394 Paving/Greening/Playground Equipment 150,646,803 Addition 102,880,614 Plumbing/Irrigation/Drainage 91,331,355 Campus Improvement 83,437,519 Roofing 46,301,268 Access Compliance 39,523,772 Food Services Renovation 32,379,615 Electrical/Lighting 30,689,853 Furniture/Fixtures/Equipment 24,500,000 Reconfiguration 13,461,576 Gym/Athletic Facilities Renovation 11,951,590

  8. Appr o ve d Pr o je c ts – Cate go r ie s c o nt. PROJECT TYPE BUDGET Excavation 8,858,957 Flooring 4,893,364 Portable 4,000,000 Fire Alarm System 2,702,889 Auditorium Renovation 1,496,876 SEEDS 1,143,409 Fencing 887,020 Lunch/Shade Shelter 429,226 Ceiling/Wall System 376,122 Grand Total 2,806,911,604

  9. Co mpr e he nsive Mo de r nizatio n Pr o je c ts Phase I E le ve n Pr o je c ts Appr o ve d * F ive will be De sign-Build Mo stly c o nstr uc ting ne w buildings * Six will be De sign-Bid-Build Mo stly mo de r nizing e xisting buildings (many o f whic h ar e histo r ic )

  10. Boa r d- Appr ove d Compr e he nsive Mode r niza tion Pr oje c ts Pr oje c t budge ts be twe e n appr oximate ly $100 million to $200 million - $ 1.4 Billion T otal Antic ipate d time fr ame appr oximate ly five ye ar s 1. Burroughs Middle Sc hool * 2. Cle ve land High Sc hool 3. Grant High Sc hool 4. Huntington Park High Sc hool 5. Je ffe rson High Sc hool 6. North Hollywood High Sc hool * 7. Polyte c hnic High Sc hool * 8. Roose ve lt High Sc hool 9. San Pe dro High Sc hool *10. She rman Oaks Ce nte r for E nric he d Studie s Magne t (SOCE S) *11. Ve nic e High Sc hool * De sign- Build

  11. Upc o ming De sign-Build Pr o c ur e me nt fo r F ive Co mpr e he nsive Mo de r nizatio n Pr o je c ts • Po lyte c hnic High Sc ho o l $105 - $115-millio n • Ro o se ve lt High Sc ho o l $90 - $100-millio n • She r man Oaks Ce nte r fo r E nr ic he d Studie s $60 - $70-millio n • Ve nic e High Sc ho o l $75 - $85-millio n • Cle ve land High Sc ho o l $65 - $75-millio n * Dollar values are approximate

  12. Upc o ming De sign-Build Co mpr e he nsive Mo de r nizatio n Pr o je c ts Site Acreage: 33.6 Acres Board Approved Budget: $109,823,330

  13. Upc o ming De sign-Build Co mpr e he nsive Mo de r nizatio n Pr o je c ts Site Acreage: 37.2 Acres Board Approved Budget: $162,209,848

  14. Upc o ming De sign-Build Co mpr e he nsive Mo de r nizatio n Pr o je c ts Site Acreage: 22.7 Acres Board Approved Budget: $137,437,976

  15. Upc o ming De sign-Build Co mpr e he nsive Mo de r nizatio n Pr o je c ts Site Acreage: 21.5 Acres Board Approved Budget: $93,463,772

  16. Upc o ming De sign-Build Co mpr e he nsive Mo de r nizatio n Pr o je c ts Site Acreage: 28.8 Acres Board Approved Budget: $111,491,261

  17. Re c e ntly Comple te d De sign- Build Pr oje c t JORDAN HIGH SCHOOL RE DE VE L OPME NT Main Gate at 103 rd Street Library of Administration Building Two Lunch shelters and Courtyard Construction Start: Q2 2013 (4-25-2013) • Construction Completed: April 15, 2016 • Approved Budget: $88,592,635 • Project Provides: • • Two New Three Story Classroom Buildings (Small Learning Community East, Small Learning Community West) & 1 New Practice Gym Building: Completed December 2014 • Conversion of Practice Gym to Food Services Facility: Completed March 2014 • Conversion of Wood Shop Building to Girl’s Locker Room: Completed November 2013 • Demolition of Existing Facilities, Site Work, Landscape and Irrigation • Renovation of Existing Administration Building and Multipurpose Room • Installation of Fully Automatic Campus-wide Fire Alarm System and Wireless Network System Architect/Engineer: DLR Group Contractor: Swinerton Builders 1 st Floor of Administration Building •

  18. JORDAN HIGH SCHOOL RE DE VE L OPME NT Practice Gym Classroom of Administration Building East Parking Lot – Looking South East Parking Lot – Looking North

  19. Jor dan High Sc hool Re de ve lopme nt Partnership for Los Angeles Schools (PLAS) Classroom Building Practice Gymnasium Exterior: Aerial View Practice Gym Interior Food Service Line

  20. Po te ntial F utur e De sign-Build Pr o je c ts Co mpr e he nsive Mo de r nizatio n Phase II De par tme nt o f Ho using Ce r tifie d Bungalo w Re plac e me nt Se ismic Pr o je c ts ADA Ac c e ss Co mplianc e Phase II o f So lar Pr o gr am

  21. Histo r y o f Pr o je c t De live r y Platfo r ms  De sign-Bid-Build E duc atio n Co de 17406 (L e ase -L e ase bac k) Co mpe titive Be st Value Awar d Hybr id: De sign-Bid-Build, De sign-Build Ne w L e gislatio n fo r 17406 (AB 2316) Basic ally says that it is o kay to use 17406 if yo u use the L AUSD Mo de l Adds the ability to awar d be fo r e DSA final de sign appr o val  De sign-Build E ar lie r L imitatio ns Me ans and Me tho ds De sign Co mpe titio n Stipe nds Se le c tio n Base d o n past Pe r fo r manc e

  22. Our Cur r e nt De sign-Build Pr o gr am

  23. Re que st fo r Qualific atio ns State me nt o f Qualific atio ns submitte d in r e spo nse to the Re que st fo r Qualific atio ns will be sc o r e d o n the fo llo wing c ate go r ie s and asso c iate d we ighte d po ints: • Pr o je c t E xpe r ie nc e (K-12) 25% • T e aming and Inte gr atio n (Past Pe r fo r manc e as a T e am) 22% • Ke y Pe r so nne l 22% • De sign-Build E xpe r ie nc e 17% • Or ganizatio n and T e c hnic al Appr o ac h 7% • Small Busine ss E nte r pr ise 5% • Safe ty 1% • Skille d & T r aine d Wo r kfo r c e 1% • L IF E CYCL E MAINT E NANCE ? % * Sc o r ing subje c t to c hange base d o n pr o je c t-spe c ific c r ite r ia

  24. Pr o po sal Sc o r ing Pr o po sals will be sc o r e d base d o n the fo llo wing c ate go r ie s and asso c iate d we ighte d po ints: • Pr ic e 28% • De sign Co nc e pt, Mate r ials & Appr o ac h 26% • T e c hnic al E xpe r tise / Phasing / Sc he dule 25% • Outr e ac h (SBE , We Build, & L o c al Wo r ke r Par tic ipatio n) 15% • L ife -Cyc le Co st 2% • Safe ty Re c o r d 2% • Skille d L abo r F o r c e Availability 1% • Wo r k-base d L e ar ning Par tne r ship 1% * Sc o r ing subje c t to c hange base d o n pr o je c t-spe c ific c r ite r ia

  25. Info r matio n L AUSD to Pr o vide to Pr o po sal T e ams • L imits o f Wo r k • Basis o f De sign • Pr e liminar y Sc he matic De sign • Building De mo litio n Plan • Pr o po se d Site L ayo ut, Building Massing, E xte r io r Mate r ials • Majo r Pr o gr am Adjac e nc y Re quir e me nts • De sign Standar ds • E duc atio nal Spe c ific atio ns

  26. Info r matio n L AUSD to Pr o vide to Pr o po sal T e ams Co nt. • Ge ne r al Re quir e me nts • T o po gr aphic Sur ve y • Ge o te c hnic al Re po r t • Utility Infr astr uc tur e Sur ve y • As-Built Re c o r d Dr awings • CE QA Mitigatio n Re quir e me nts • T r affic Study • Additio nal Info r matio n

  27. Pr o c ur e me nt Sc he dule – RF Q Re le ase o f RF Q and Adve r tising We e k 1 Mandato r y Pr e -RF Q Sc o pe Pr e se ntatio n We e k 2 Pr e -SOQ Que stio ns We e k 3 L AUSD Re spo nse to Que stio ns We e k 5 State me nt o f Qualific atio ns Due We e k 8 L AUSD Re vie w SOQ We e k 10 Anno unc e me nt o f 3 Sho r t-liste d De sign-Build T e ams We e k 11 * T ime fr ame s ar e appr o ximate and subje c t to c hange base d o n e ac h pr o je c t

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.