derby project
play

/ / / / Derby project Outline: A 198 million track & - PowerPoint PPT Presentation

/ / / / Derby project Outline: A 198 million track & signalling scheme The signalling equipment around Derby Station is nearing the end of its operational life The track layout is nearly 50 years old Since track &


  1. / /

  2. / /

  3. Derby project Outline: A £198 million track & signalling scheme • The signalling equipment around Derby Station is • nearing the end of its operational life The track layout is nearly 50 years old • Since track & signalling work in unison and so are • being replaced together Preparatory work has already begun and as much • work as possible will be done prior to disrupting station users & passengers  This includes installing 3.5km of track, new signal bases, drainage, signals & telecoms cabling and construction of a new station platform /

  4. Derby project Schedule of work: August 2017: Piling for new signal bases begins • Christmas 2017: •  Removal of sidings & goods lines in the station area  Some reduction in public car parking for materials storage January - June 2018: •  Installation of signalling continues  New 320 metre platform constructed - new stairs & lift from existing pedestrian footbridge installed 22 July to 7 Oct 2018: • Main works • /

  5. Derby project Main works (22 July to 7 Oct 2018) : The volume of work to be completed will take 79 • days During this time: •  14km of track will be replaced & re-laid in a new configuration  55 new straight post signals, 9 new signal gantries & 79 sets of points will be installed  150,000 tonnes of new ballast will be laid  240 engineering trains will bring in material & remove waste from the site The station will remain operational for the majority of this period /

  6. Derby project Benefits: The new layout will: •  Reduce bottlenecks  Increased line speed  Enable more efficient management of rail traffic & quicker passage through station  Deliver new signalling with remote condition monitoring for improved reliability & ease of maintenance  Provide greater operational flexibility & reliability  Deliver a layout to help meet future growth /

  7. Derby project Impact on station users/passengers: Derby Station will remain open & operational for • majority of 79 days in summer 2018 We are still a year away from any disruption • A train & replacement bus plan is being developed •  Network Rail and Train Operators are working together to ensure key links, such as Derby to London, are maintained wherever possible There will be significant communications activity • during the project to keep you informed  Including an online tool passengers can use to plan around the disruption /

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend