/ / / / Derby project Outline: A 198 million track & - - PowerPoint PPT Presentation

derby project
SMART_READER_LITE
LIVE PREVIEW

/ / / / Derby project Outline: A 198 million track & - - PowerPoint PPT Presentation

/ / / / Derby project Outline: A 198 million track & signalling scheme The signalling equipment around Derby Station is nearing the end of its operational life The track layout is nearly 50 years old Since track &


slide-1
SLIDE 1

/ /

slide-2
SLIDE 2

/ /

slide-3
SLIDE 3

/

Outline:

  • A £198 million track & signalling scheme
  • The signalling equipment around Derby Station is

nearing the end of its operational life

  • The track layout is nearly 50 years old
  • Since track & signalling work in unison and so are

being replaced together

  • Preparatory work has already begun and as much

work as possible will be done prior to disrupting station users & passengers

  • This includes installing 3.5km of track, new signal

bases, drainage, signals & telecoms cabling and construction of a new station platform

Derby project

slide-4
SLIDE 4

/

Schedule of work:

  • August 2017: Piling for new signal bases begins
  • Christmas 2017:
  • Removal of sidings & goods lines in the station area
  • Some reduction in public car parking for materials

storage

  • January - June 2018:
  • Installation of signalling continues
  • New 320 metre platform constructed - new stairs & lift

from existing pedestrian footbridge installed

  • 22 July to 7 Oct 2018:
  • Main works

Derby project

slide-5
SLIDE 5

/

Main works (22 July to 7 Oct 2018) :

  • The volume of work to be completed will take 79

days

  • During this time:
  • 14km of track will be replaced & re-laid in a new

configuration

  • 55 new straight post signals, 9 new signal gantries & 79

sets of points will be installed

  • 150,000 tonnes of new ballast will be laid
  • 240 engineering trains will bring in material & remove

waste from the site

The station will remain operational for the majority

  • f this period

Derby project

slide-6
SLIDE 6

/

Benefits:

  • The new layout will:
  • Reduce bottlenecks
  • Increased line speed
  • Enable more efficient management of rail traffic &

quicker passage through station

  • Deliver new signalling with remote condition

monitoring for improved reliability & ease of maintenance

  • Provide greater operational flexibility & reliability
  • Deliver a layout to help meet future growth

Derby project

slide-7
SLIDE 7

/

Impact on station users/passengers:

  • Derby Station will remain open & operational for

majority of 79 days in summer 2018

  • We are still a year away from any disruption
  • A train & replacement bus plan is being developed
  • Network Rail and Train Operators are working together to

ensure key links, such as Derby to London, are maintained wherever possible

  • There will be significant communications activity

during the project to keep you informed

  • Including an online tool passengers can use to plan around

the disruption

Derby project