Delaware County Regional Wastewater District (DCRWD) Wastewater Utility Preliminary Engineering Report July 19, 2018 A wealth of resources to master a common goal. Summary I. Delaware County Regional Waste District (DCRWD) New


slide-1
SLIDE 1

Delaware County Regional Wastewater District (DCRWD) Wastewater Utility Preliminary Engineering Report July 19, 2018

A wealth of resources to master a common goal.

slide-2
SLIDE 2

Summary

I. Delaware County Regional Waste District (DCRWD) – New Wastewater Treatment Plant (WWTP) and supporting infrastructure

A wealth of resources to master a common goal.

A. DCRWD is projected to save approximately $27,000,000+/- over the 20 year project planning period by building and utilizing a new WWTP versus continuing contractual treatment by Muncie Sanitary District (MSD) B. Additional rate relief is probable through:

  • Solicitating and obtaining grants for the Project
  • Refinancing outstanding debt through the Project
  • Revisiting holistically existing budgets and altering accordingly
slide-3
SLIDE 3

Summary

A wealth of resources to master a common goal.

II. DCRWD and Liberty Regional Waste District (LRWD) – New WWTP and supporting infrastructure A. DCRWD and LRWD are projected to save approximately $44,000,000 over the 20 year project planning period by building and utilizing a new WWTP versus continuing contractual treatment by MSD. B. Additional rate relief is probable through:

  • Solicitating and obtaining grant funds for the Project
  • Refinancing outstanding debt through the Project
  • O&M&R savings/synergies through potential merger of the Districts
slide-4
SLIDE 4
  • Background
  • Current Planning Document
  • Conclusions and Recommendations

Presentation Outline

slide-5
SLIDE 5

Background

  • DCRWD Wastewater Utility Bills Have Risen Dramatically
  • Royerton and DeSoto Contractual Treatment Costs from Muncie Sanitary

District (MSD) are Overly Burdensome

  • MSD Has Performed $8.8M of their Required $160M of Wastewater Utility

Work To Date

  • As MSD Completes the Remaining $150M +/- of the Required Wastewater

Utility Work, DCRWD Rates Will Rise

A wealth of resources to master a common goal.

slide-6
SLIDE 6

Background

  • Previous Consultant assembled a “Joint Wastewater Treatment Plan Study”

for DCRWD and Liberty Regional Waste District (LRWD); October 2016

  • Previous Consultant Proposed Project Included Collection System Work and a

New 1.0MGD WWTP

  • Previous Consultant Identified Project Costs Were:

➢ Construction: $ 29,799,000 ➢ Non-Construction: $ 5,263,000 ➢ Total: $ 35,062,000

A wealth of resources to master a common goal.

slide-7
SLIDE 7
  • Background
  • Current Planning Document
  • Conclusions and Recommendations

Presentation Outline

slide-8
SLIDE 8

Current Planning Document

Planning Area

slide-9
SLIDE 9

Current Planning Document

Need for Project

A wealth of resources to master a common goal.

slide-10
SLIDE 10

Current Planning Document

Alternatives Considered

A wealth of resources to master a common goal.

slide-11
SLIDE 11

Current Planning Document

Estimated Project Costs

  • DCRWD Only:

$10,127,500 (1.0 MGD WWTP)

  • DCRWD & LRWD:

$17,263,000 (1.6 MGD WWTP)

Note: Costs are 1/3 and 1/2 respectively of pervious consultant’s recommended $35,062,000 project, for a WWTP with 60% additional treatment capacity!

A wealth of resources to master a common goal.

slide-12
SLIDE 12

Current Planning Document

Revised Operation and Maintenance Expenses – New WWTP DCRWD Only

A wealth of resources to master a common goal.

slide-13
SLIDE 13

Current Planning Document

Estimated Annual Debt Repayment Associated with New WWTP DCRWD Only

Note: With $804,800 savings, eliminating MSD cost to treat and adding O&M for new WWTP, and $394,995 in additional debt service, a net savings of $409,805 annually would be realized day one (or 34% savings in cost to treat versus what Royerton and Desoto payed MSD in 2017!). A wealth of resources to master a common goal.

slide-14
SLIDE 14

Current Planning Document

Revised Operation and Maintenance Expenses – New WWTP DCRWD & LRWD

A wealth of resources to master a common goal.

slide-15
SLIDE 15

Current Planning Document

Estimated Annual Debt Repayment Associated with New WWTP DCRWD & LRWD

Note: With $829,800 savings, eliminating MSD cost to treat and adding O&M for the new WWTP, and $322,276 in additional debt service, a net savings of $419,995 annually would be realized day one (or 35% savings in cost to treat versus what Royerton and Desoto payed MSD in 2017!). A wealth of resources to master a common goal.

slide-16
SLIDE 16

Current Planning Document

Revised Operation and Maintenance Expenses – New WWTP DCRWD & LRWD

A wealth of resources to master a common goal.

slide-17
SLIDE 17

Current Planning Document

Estimated Annual Debt Repayment Associated with New WWTP DCRWD & LRWD

Note: With $530,300 savings, eliminating MSD cost to treat and adding O&M for the new WWTP, and $351,020 in additional debt service, a net savings of $179,280 annually would be realized day one (or 23.7% savings in cost to treat versus what LRWD payed MSD in 2017). A wealth of resources to master a common goal.

slide-18
SLIDE 18

Current Planning Document

The annual savings, however, associated with abandoning MSD contractual treatment and building a dedicated WWTP amplifies over the planning period as MSD costs to increase due to implementation of $150M +/- in required LTCP work! A wealth of resources to master a common goal.

slide-19
SLIDE 19

Current Planning Document

A wealth of resources to master a common goal.

slide-20
SLIDE 20

Current Planning Document

A wealth of resources to master a common goal.

slide-21
SLIDE 21

Current Planning Document

A wealth of resources to master a common goal.

slide-22
SLIDE 22
  • Background
  • Current Planning Document
  • Conclusions and Recommendations

Presentation Outline

slide-23
SLIDE 23

Conclusions and Recommendations

I. Delaware County Regional Waste District (DCRWD) – New Wastewater Treatment Plant (WWTP) and supporting infrastructure A. DCRWD is projected to save approximately $27,000,000+/- over the 20 year project planning period by building and utilizing a new WWTP versus continuing contractual treatment by Muncie Sanitary District (MSD) B. Additional rate relief is probable through:

  • Solicitating and obtaining grants for the Project
  • Refinancing outstanding debt through the Project
  • Revisiting holistically existing budgets and altering accordingly
slide-24
SLIDE 24

Conclusions and Recommendations

II. DCRWD and Liberty Regional Waste District (LRWD) – New WWTP and supporting infrastructure A. DCRWD and LRWD are projected to save approximately $44,000,000 over the 20 year project planning period by building and utilizing a new WWTP versus continuing contractual treatment by MSD. B. Additional rate relief is probable through:

  • Solicitating and obtaining grant funds for the Project
  • Refinancing outstanding debt through the Project
  • O&M&R savings/synergies through potential merger of the Districts
slide-25
SLIDE 25

Questions

A wealth of resources to master a common goal.

Al Stong

Project Manager

astong@contactcei.com

Rob Bellucci Senior Project Engineer

rbellucci@contactcei.com

slide-26
SLIDE 26

White River Discharge - History

  • June 2012 PELs to White River Issued to GRW
  • November 2012 PELs to White River Issued to GRW (Modified to Include

Phosphorus)

  • May 2015 PELs to White River Requested by GRW
  • IDEM Requested GRW withdraw request due to proximity (<1 mile)

to Indiana American Water Intake

  • March 2016 PELs requested to Mississinewa River
slide-27
SLIDE 27

Proposed WWTP Discharge

  • June 2018 PELs to Muncie Creek

(Flows through north-central Muncie, then connects to the White River downstream of Indiana American Water Supply)