December 6, 2016 Phase 2 Project Kickoff Meeting Overview Phase 1: - - PowerPoint PPT Presentation

december 6 2016 phase 2 project kickoff meeting overview
SMART_READER_LITE
LIVE PREVIEW

December 6, 2016 Phase 2 Project Kickoff Meeting Overview Phase 1: - - PowerPoint PPT Presentation

30-Percent Engineering Design Services for the New Mexico Unit of Central Arizona Project December 6, 2016 Phase 2 Project Kickoff Meeting Overview Phase 1: Scope and Findings Summary Phase 2: Scope, Schedule, and Deliverables


slide-1
SLIDE 1

30-Percent Engineering Design Services for the

New Mexico Unit of Central Arizona Project

December 6, 2016 Phase 2 – Project Kickoff Meeting

slide-2
SLIDE 2

Overview – Phase 1: Scope and Findings Summary – Phase 2: Scope, Schedule, and Deliverables – Gila Diversion Preliminary Findings

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 2

slide-3
SLIDE 3

Phase 1: Scope and Findings

slide-4
SLIDE 4

Phase 1 – Scope Summary Scope Develop Screening Criteria for Diversion and Storage Concepts along the Gila and Mogollon – Storage: reservoirs and ASR – Diversions: open channel, pipelines, and pumping – Assess environmental impacts

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 4

slide-5
SLIDE 5

Phase 1 – Selected Alternative

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 5

slide-6
SLIDE 6

Phase 1 – Selected Alternative Alternative 4 (Selected Alternative) Initial Phase – Diversion of 150 cfs – Flood infiltration and storage with additional basins in the Cliff-Gila Valley – Ranney Wells – Construct Winn Reservoir and Diversion to 3,845 AF – Pipeline and pumping to the Upper Gila ditch

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 6

slide-7
SLIDE 7

Phase 2 – Scope, Schedule, and Deliverables

slide-8
SLIDE 8

Phase 2 – Scope, Schedule, and Deliverables Scope – Diversion – ASR ground water model – ASR geotechnical investigation – ASR down valley sites – Agency requirements – Additional work

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 8

slide-9
SLIDE 9

Phase 2 – Schedule

9 30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project

Project Milestones – Task 6 – Project Management NTP – 11/7/2016 – Task 7 – Diversions NTP – 11/7/2016

– Draft Report Submitted 12/2/2016

– Task 8 – Coordination Meeting NTP - TBD – Task 9 – ASR Ground Water Model NTP – TBD – Task 10 – Geotechnical Investigation NTP - TBD – Task 11 – ASR Down Valley Sites NTP – TBD – Task 12 – Agency Coordination NTP - TBD

slide-10
SLIDE 10

Phase 2 – Deliverables Deliverables – Diversion Report – ASR Numerical Model – ASR Geotechnical Report – Down Valley ASR Observations Memorandum – Permitting Summary Memorandum

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 10

slide-11
SLIDE 11

Gila Diversion Preliminary Findings

slide-12
SLIDE 12

Gila Gage Diversion Site – Gila Stream Gage

  • USGS 09430500

– Land Ownership

  • US Forest Service (USFS)
  • No diversion activities on USFS lands
  • TNC & State of New Mexico
  • Co-ownership
  • National Lands Protection Act (NLPA)

– Access Road Improvements

  • Regrade slopes >12%
  • Crossing of Mogollon Creek
  • Construction & maintenance

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 12

slide-13
SLIDE 13

Conceptual Diversion Alternatives Criteria

slide-14
SLIDE 14

Site Evaluation Criteria – Available Head

  • Highest point below USFS boundary

– All Weather Access

  • Except during flooding events

– Structural Stability

  • Key diversion to bedrock

– Lateral & Vertical Channel Stability

  • Bedrock along both banks
  • Observed channel degradation

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 14

slide-15
SLIDE 15

Design Alternatives Selection Criteria – Structure Design

  • Grouted boulder vs. cast concrete
  • Adjustable vs. fixed invert
  • At grade vs. surface water intake

– Sediment Transport

  • Promote sediment continuity
  • Prevent erosion & sedimentation

– Structure Bypass

  • Maintain design channel alignment
  • Prevent future channel avulsion

– Upstream Fish Passage

  • Design to T&E species requirements
  • Minimize limiting velocities & depths

– Downstream Navigability

  • Minimize recreational hazards

http://www.wildlife.state.nm.us/fishing/game-fish/cold-water/ 30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 15

slide-16
SLIDE 16

Conceptual Diversion Alternatives 30% Design

slide-17
SLIDE 17

Engineered Riffle Diversion

– Invert 4662’ to 4666’ – Grouted Boulder or Concrete – Cast Concrete Walls – Elongated Riffle Rundown – Riprap Bank Protection – Bedload Deflection – Fish & Debris Exclusion – Sediment Sluicing – Surface Conveyance Canal

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 17

slide-18
SLIDE 18

Engineered Riffle Diversion – Pros

  • Cost to construct
  • Fewer mechanical systems
  • Reduced power requirements
  • Recreational navigation

– Cons

  • Non-adjustable invert
  • Static sediment management
  • No fish passage channel
  • Reduced flood flow conveyance

Engineered Riffle: Kremlin, CO 30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 18

slide-19
SLIDE 19

Obermeyer Pneumatic Gates Diversion

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 19

– Gates Raised 4662’ to 4666’ – Cast Concrete Sill & Walls – Riprap Bank Protection – Mechanical Infrastructure

  • Steel gates, pneumatic lines,

bladders, compressors,

  • perations controls & housing

– Bedload Deflection – Fish & Debris Exclusion – Sediment Sluicing – Surface Conveyance Canal

slide-20
SLIDE 20

Obermeyer Pneumatic Gates Diversion – Pros

  • Adjustable invert
  • Dynamic sediment flushing
  • Fish passage opportunities
  • Flood flow conveyance

– Cons

  • Cost to construct
  • Mechanical systems maintenance
  • Additional power requirements

Albuquerque Diversion Dam: http://mapio.net/pic/p-5170793/ 30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 20

slide-21
SLIDE 21

Combination Coanda Screen & Obermeyer Pneumatic Gate Diversion

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 21

– Gates Raised 4662’ to 4666’ – Cast Concrete Sill & Walls – Riprap Bank Protection – Coanda Screens

  • 1 mm opening

– Water Collection Vaults – Mechanical Infrastructure

  • Steel gates, pneumatic lines,

bladders, compressors,

  • perations controls & housing

– Sediment Sluicing – Subgrade Conveyance Culvert

slide-22
SLIDE 22

Combination Coanda Screen & Obermeyer Pneumatic Gate Diversion – Pros

  • Partially adjustable invert
  • Limited sediment flushing
  • Sediment & debris exclusion
  • Fish passage opportunities

– Cons

  • Cost to construct
  • Mechanical systems maintenance
  • Sedimentation in vaults
  • Reduced head for conveyance
  • Additional power requirements

http://www.elginindustries.com/equipment_group/norris_screen/products/product_line/Norri s_Screen/stainless_steel_screening_systems/coanda_screen 30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 22

slide-23
SLIDE 23

Channel Response to Historic Changes in the River System

slide-24
SLIDE 24

River Channel Modifications in the Cliff-Gila Valley – Channelization

  • Straightening & leveeing
  • Steeper channel slopes

– Disconnection of Floodplain

  • Reduced overbank flood storage
  • Loss of vegetation & bank stability

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 24

slide-25
SLIDE 25

Dynamic Channel Response in Cliff-Gila Valley – Independent of Flood Severity – Vertical Channel Instabilities

  • Upstream degradation
  • Headcutting
  • Downstream aggradation
  • Braiding

– Lateral Channel Instability

  • Bank erosion & failure
  • Channel avulsion

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 25

slide-26
SLIDE 26

Observed Channel Response at Gila Gage Site – Ongoing Channel Incision

  • Propagation of headcuts

initiated downstream

– Channel Abandonment

  • Historically irrigated fields
  • Fluvial landforms
  • USGS stream gage facility

– Lowered Shallow Water Table

  • Perched riparian vegetation
  • Expanded upland conditions

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 26

slide-27
SLIDE 27

Ecological & Functional Restoration of the Gila River

slide-28
SLIDE 28

Intent of Reach-Scale Channel Restoration – Re-elevate Incised Channel – Restore Stable Channel Geometries – Reduce Over-steepened Banks – Reconnect Abandoned Floodplains – Raise Shallow Water Tables – Reestablish Native Riparian Zones

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 28

slide-29
SLIDE 29

Pros & Cons of Restoration to Diversion Project – Improve River Function

  • Vertical & lateral channel stability
  • Sediment continuity of reach

– Raise Diversion Elevations

  • Gravity feed ASR infiltration fields

– Restore Aquatic & Riparian Habitats

  • T&E species

– Benefit River Based Recreation

  • Existing hazards

– Disadvantages of Restoration

  • Increased project cost
  • Temporary construction impacts

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 29

slide-30
SLIDE 30

Next Steps

slide-31
SLIDE 31

Recommended Path Forward – Continued Fluvial Geomorphic Analysis – Additional Hydraulic Modeling – Initiate Sediment Transport Modeling – Field Investigations for ASR – Stream Restoration Evaluation

30 Percent Engineering Design Services for New Mexico Unit of Central Arizona Project 31

slide-32
SLIDE 32

Questions?

December 6, 2016