december 6 2016 phase 2 project kickoff meeting overview
play

December 6, 2016 Phase 2 Project Kickoff Meeting Overview Phase 1: - PowerPoint PPT Presentation

30-Percent Engineering Design Services for the New Mexico Unit of Central Arizona Project December 6, 2016 Phase 2 Project Kickoff Meeting Overview Phase 1: Scope and Findings Summary Phase 2: Scope, Schedule, and Deliverables


  1. 30-Percent Engineering Design Services for the New Mexico Unit of Central Arizona Project December 6, 2016 Phase 2 – Project Kickoff Meeting

  2. Overview – Phase 1: Scope and Findings Summary – Phase 2: Scope, Schedule, and Deliverables – Gila Diversion Preliminary Findings 30 Percent Engineering Design Services for 2 New Mexico Unit of Central Arizona Project

  3. Phase 1: Scope and Findings

  4. Phase 1 – Scope Summary Scope Develop Screening Criteria for Diversion and Storage Concepts along the Gila and Mogollon – Storage: reservoirs and ASR – Diversions: open channel, pipelines, and pumping – Assess environmental impacts 30 Percent Engineering Design Services for 4 New Mexico Unit of Central Arizona Project

  5. Phase 1 – Selected Alternative 30 Percent Engineering Design Services for 5 New Mexico Unit of Central Arizona Project

  6. Phase 1 – Selected Alternative Alternative 4 (Selected Alternative) Initial Phase – Diversion of 150 cfs – Flood infiltration and storage with additional basins in the Cliff-Gila Valley – Ranney Wells – Construct Winn Reservoir and Diversion to 3,845 AF – Pipeline and pumping to the Upper Gila ditch 30 Percent Engineering Design Services for 6 New Mexico Unit of Central Arizona Project

  7. Phase 2 – Scope, Schedule, and Deliverables

  8. Phase 2 – Scope, Schedule, and Deliverables Scope – Diversion – ASR ground water model – ASR geotechnical investigation – ASR down valley sites – Agency requirements – Additional work 30 Percent Engineering Design Services for 8 New Mexico Unit of Central Arizona Project

  9. Phase 2 – Schedule Project Milestones – Task 6 – Project Management NTP – 11/7/2016 – Task 7 – Diversions NTP – 11/7/2016 – Draft Report Submitted 12/2/2016 – Task 8 – Coordination Meeting NTP - TBD – Task 9 – ASR Ground Water Model NTP – TBD – Task 10 – Geotechnical Investigation NTP - TBD – Task 11 – ASR Down Valley Sites NTP – TBD – Task 12 – Agency Coordination NTP - TBD 30 Percent Engineering Design Services for 9 New Mexico Unit of Central Arizona Project

  10. Phase 2 – Deliverables Deliverables – Diversion Report – ASR Numerical Model – ASR Geotechnical Report – Down Valley ASR Observations Memorandum – Permitting Summary Memorandum 30 Percent Engineering Design Services for 10 New Mexico Unit of Central Arizona Project

  11. Gila Diversion Preliminary Findings

  12. Gila Gage Diversion Site – Gila Stream Gage • USGS 09430500 – Land Ownership • US Forest Service (USFS) o No diversion activities on USFS lands • TNC & State of New Mexico o Co-ownership o National Lands Protection Act (NLPA) – Access Road Improvements • Regrade slopes >12% • Crossing of Mogollon Creek • Construction & maintenance 30 Percent Engineering Design Services for 12 New Mexico Unit of Central Arizona Project

  13. Conceptual Diversion Alternatives Criteria

  14. Site Evaluation Criteria – Available Head • Highest point below USFS boundary – All Weather Access • Except during flooding events – Structural Stability • Key diversion to bedrock – Lateral & Vertical Channel Stability • Bedrock along both banks • Observed channel degradation 30 Percent Engineering Design Services for 14 New Mexico Unit of Central Arizona Project

  15. Design Alternatives Selection Criteria – Structure Design • Grouted boulder vs. cast concrete • Adjustable vs. fixed invert • At grade vs. surface water intake – Sediment Transport http://www.wildlife.state.nm.us/fishing/game-fish/cold-water/ • Promote sediment continuity – Upstream Fish Passage • Prevent erosion & sedimentation • Design to T&E species requirements • Minimize limiting velocities & depths – Structure Bypass • Maintain design channel alignment – Downstream Navigability • Prevent future channel avulsion • Minimize recreational hazards 30 Percent Engineering Design Services for 15 New Mexico Unit of Central Arizona Project

  16. Conceptual Diversion Alternatives 30% Design

  17. Engineered Riffle Diversion – Invert 4662 ’ to 4666’ – Grouted Boulder or Concrete – Cast Concrete Walls – Elongated Riffle Rundown – Riprap Bank Protection – Bedload Deflection – Fish & Debris Exclusion – Sediment Sluicing – Surface Conveyance Canal 30 Percent Engineering Design Services for 17 New Mexico Unit of Central Arizona Project

  18. Engineered Riffle Diversion – Pros • Cost to construct • Fewer mechanical systems • Reduced power requirements • Recreational navigation – Cons • Non-adjustable invert • Static sediment management • No fish passage channel • Reduced flood flow conveyance Engineered Riffle: Kremlin, CO 30 Percent Engineering Design Services for 18 New Mexico Unit of Central Arizona Project

  19. Obermeyer Pneumatic Gates Diversion – Gates Raised 4662 ’ to 4666’ – Cast Concrete Sill & Walls – Riprap Bank Protection – Mechanical Infrastructure • Steel gates, pneumatic lines, bladders, compressors, operations controls & housing – Bedload Deflection – Fish & Debris Exclusion – Sediment Sluicing – Surface Conveyance Canal 30 Percent Engineering Design Services for 19 New Mexico Unit of Central Arizona Project

  20. Obermeyer Pneumatic Gates Diversion – Pros • Adjustable invert • Dynamic sediment flushing • Fish passage opportunities • Flood flow conveyance – Cons • Cost to construct • Mechanical systems maintenance • Additional power requirements Albuquerque Diversion Dam: http://mapio.net/pic/p-5170793/ 30 Percent Engineering Design Services for 20 New Mexico Unit of Central Arizona Project

  21. Combination Coanda Screen & Obermeyer Pneumatic Gate Diversion – Gates Raised 4662 ’ to 4666’ – Cast Concrete Sill & Walls – Riprap Bank Protection – Coanda Screens • 1 mm opening – Water Collection Vaults – Mechanical Infrastructure • Steel gates, pneumatic lines, bladders, compressors, operations controls & housing – Sediment Sluicing – Subgrade Conveyance Culvert 30 Percent Engineering Design Services for 21 New Mexico Unit of Central Arizona Project

  22. Combination Coanda Screen & Obermeyer Pneumatic Gate Diversion – Pros • Partially adjustable invert • Limited sediment flushing • Sediment & debris exclusion • Fish passage opportunities – Cons • Cost to construct • Mechanical systems maintenance • Sedimentation in vaults • Reduced head for conveyance • Additional power requirements http://www.elginindustries.com/equipment_group/norris_screen/products/product_line/Norri s_Screen/stainless_steel_screening_systems/coanda_screen 30 Percent Engineering Design Services for 22 New Mexico Unit of Central Arizona Project

  23. Channel Response to Historic Changes in the River System

  24. River Channel Modifications in the Cliff-Gila Valley – Channelization – Disconnection of Floodplain • Straightening & leveeing • Reduced overbank flood storage • Steeper channel slopes • Loss of vegetation & bank stability 30 Percent Engineering Design Services for 24 New Mexico Unit of Central Arizona Project

  25. Dynamic Channel Response in Cliff-Gila Valley – Independent of Flood Severity – Vertical Channel Instabilities • Upstream degradation o Headcutting • Downstream aggradation o Braiding – Lateral Channel Instability • Bank erosion & failure • Channel avulsion 30 Percent Engineering Design Services for 25 New Mexico Unit of Central Arizona Project

  26. Observed Channel Response at Gila Gage Site – Ongoing Channel Incision • Propagation of headcuts initiated downstream – Channel Abandonment • Historically irrigated fields • Fluvial landforms • USGS stream gage facility – Lowered Shallow Water Table • Perched riparian vegetation • Expanded upland conditions 30 Percent Engineering Design Services for 26 New Mexico Unit of Central Arizona Project

  27. Ecological & Functional Restoration of the Gila River

  28. Intent of Reach-Scale Channel Restoration – Re-elevate Incised Channel – Restore Stable Channel Geometries – Reduce Over-steepened Banks – Reconnect Abandoned Floodplains – Raise Shallow Water Tables – Reestablish Native Riparian Zones 30 Percent Engineering Design Services for 28 New Mexico Unit of Central Arizona Project

  29. Pros & Cons of Restoration to Diversion Project – Improve River Function • Vertical & lateral channel stability • Sediment continuity of reach – Raise Diversion Elevations • Gravity feed ASR infiltration fields – Restore Aquatic & Riparian Habitats • T&E species – Benefit River Based Recreation • Existing hazards – Disadvantages of Restoration • Increased project cost • Temporary construction impacts 30 Percent Engineering Design Services for 29 New Mexico Unit of Central Arizona Project

  30. Next Steps

  31. Recommended Path Forward – Continued Fluvial Geomorphic – Field Investigations for ASR Analysis – Stream Restoration Evaluation – Additional Hydraulic Modeling – Initiate Sediment Transport Modeling 30 Percent Engineering Design Services for 31 New Mexico Unit of Central Arizona Project

  32. Questions? December 6, 2016

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend