Daniel Boone Homestead Master Plan RFP Pre-Proposal Meeting August 18, 2020 BACKGROUND 569-acre property owned by the PA Historical and Museum Commission (PHMC) located in the Eastern portion of Exeter Township. Historical birthplace


slide-1
SLIDE 1

Daniel Boone Homestead Master Plan RFP

Pre-Proposal Meeting August 18, 2020

slide-2
SLIDE 2

BACKGROUND

  • 569-acre property owned by the PA Historical and Museum Commission (PHMC) located in the Eastern portion of Exeter

Township.

  • Historical birthplace and boyhood home of iconic pioneer Daniel Boone.
  • Purchased by the Commonwealth in 1937 to be “…preserved as a historical place and park for the benefit of the people of

the Commonwealth.”

  • Exeter Township currently leases 31-acres utilized as Pineland Park.
slide-3
SLIDE 3

GOALS

1. Preserve and Enhance Historical Experience/Promote Historic Core. 2. Expand Recreational Opportunities. 3. Assess Natural Features and Site Hydrology to Create Community Attraction. 4. Protect Natural Resources and Address Stormwater Issues. 5. Address Site Circulation and Parking Improvements.

slide-4
SLIDE 4

PLANNED CAPITAL PROJECTS

  • Sanitary Sewer System Improvement Project.
  • ADA Restroom Renovations at Visitor Center.
  • Bridge Renovation Project.
  • Paving Project at Second Entrance (Temporary

Primary Entrance).

slide-5
SLIDE 5

KEY EXPECTATIONS

Public Participation; Study Committee, Public Survey, Key Person Interviews. Incorporation into Larger Township Parks System. Site Information and Analysis; Historic Core and Recommendations for Non-Historic Areas. Activities and Facilities Analysis; Attracting New Users, Events, Programming.

  • Trail System Expansion and Connectivity.

Maintenance Plan and Estimate. Security Analysis; Evaluate Current Status and Recommendations for Improvement.

slide-6
SLIDE 6

TIMELINE

Deadline for Questions Submitted

21 Aug. 2020

Responses for Questions

28 Aug. 2020

Proposals Due

10 Sep. 2020

Expected Project Commencement Date

  • Nov. 2020
slide-7
SLIDE 7

QUESTIONS?