COURTS BUNDLE PPP PROJECT
MARKET LAUNCH DAY Kilkenny Courthouse, 13th May 2014
COURTS BUNDLE PPP PROJECT MARKET LAUNCH DAY Kilkenny Courthouse, 13 - - PowerPoint PPT Presentation
COURTS BUNDLE PPP PROJECT MARKET LAUNCH DAY Kilkenny Courthouse, 13 th May 2014 WELCOME AND OVERVIEW BRENDAN RYAN CHIEF EXECUTIVE OFFICER, COURTS SERVICE Overview Introduction & Opening address Introduction by Mr. Brendan Ryan, CEO of
COURTS BUNDLE PPP PROJECT
MARKET LAUNCH DAY Kilkenny Courthouse, 13th May 2014
WELCOME AND OVERVIEW
BRENDAN RYAN CHIEF EXECUTIVE OFFICER, COURTS SERVICE
Introduction & Opening address
Courts Bundle PPP Project Overview
Courts PPP Bundle Procurement Overview
Overview
COURTS BUNDLE PPP PROJECT INTRODUCTION
BRENDAN RYAN CHIEF EXECUTIVE OFFICER, COURTS SERVICE
COURTS BUNDLE PPP PROJECT ADDRESS BY
THE HON. MRS. JUSTICE SUSAN DENHAM, CHIEF JUSTICE
COURTS BUNDLE PPP PROJECT PROJECT AND SITE OVERVIEW
PAUL BURNS
HEAD OF INFRASTRUCTURE SERVICES DIRECTORATE, COURTS SERVICE
Department of Justice & Equality:
Courts Service:
NDFA:
The Roles of the Parties
Courts Service Act 1998:
Courts Service mission is:
quality and professional service to all users of the courts”
Courts Service functions are:
Courts Service
We want our court buildings to support the administration of justice, to allow us to provide quality services to court users and to present an appropriate image of the courts to the public
Since 1999 significant investment has been made in providing new and refurbished court facilities: one of the most recent was Kilkenny These have been procured both through traditional capital procurement and by way of Public Private Partnership in the case of the Criminal Courts of Justice in Dublin A major rationalisation of smaller venues has also taken place The availability of appropriate facilities for all court users with separate circulation routes is an important feature of courthouse design and operation The designs produced by the Office of Public Works for the 7 projects address these requirements In the 7 locations covered by the Courts Bundle, the existing court facilities are poor and in need of significant improvement, in both capacity and in the availability and standard of facilities
Courts Service Building Programme
SITE OVERVIEW
*Areas are indicative
Location Courthouse Buildings Total * Area (m2)
Letterkenny,
A new courthouse to accommodate four courtrooms and associated facilities to be constructed on a town centre site close to the existing courthouse 5,027
Drogheda, Co Louth
A new courthouse consisting of two courtrooms and associated facilities to be constructed on a landmark town centre site adjacent to the river Boyne 1,354
Mullingar, Co. Westmeath
The refurbishment and extension of the existing historic courthouse in Mullingar to accommodate three courtrooms, improved custody facilities, court offices and associated facilities. 3,320
Limerick City
A new criminal courthouse to be built on a site adjacent to Limerick Prison, to include six courtrooms, custody facilities, court offices and associated facilities 7,609
Project Scope
*Areas are indicative
Project Scope cont’d
Location Courthouse Buildings Total * Area (m2)
Wexford Town The refurbishment and extension of an existing landmark building to provide a new courthouse for Wexford Town consisting of four courtrooms, custody facilities, court offices and associated facilities 4,680 Waterford City The refurbishment and extension of the existing historic courthouse in Waterford to accommodate six courtrooms, improved custody facilities, court offices and associated facilities. 6,392 Cork City The refurbishment and extension of the existing landmark courthouse building at Anglesea Street to accommodate six courtrooms, improved custody facilities, court offices, the regional office and associated facilities. 8,490 Totals 36,872
SITE DRAWINGS AND PERSPECTIVES
DESCRIPTION NEW COURTHOUSE TO ACCOMMODATE FOUR COURTROOMS AND ASSOCIATED FACILITIES TO BE CONSTRUCTED ON A TOWN CENTRE SITE CLOSE TO THE EXISTING COURTHOUSE. AREA 5,027M2
DESCRIPTION NEW COURTHOUSE CONSISTING OF TWO COURTROOMS AND ASSOCIATED FACILITIES TO BE CONSTRUCTED ON A LANDMARK TOWN CENTRE SITE ADJACENT TO THE RIVER BOYNE. AREA 1,354M2
DESCRIPTION NEW COURTHOUSE TO ACCOMMODATE THREE COURTROOMS AND ASSOCIATED FACILITIES. THE DEVELOPMENT WILL CONSIST OF AN EXTENSION TO THE REAR AND SIDES OF THE EXISTING COURTHOUSE, AND ADAPTATION OF THE EXISTING BUILDING. AREA c3,320 sq.m.
Mount Street, Mullingar, Co Westmeath
DESCRIPTION NEW CRIMINAL COURTHOUSE TO BE BUILT ON A SITE ADJACENT TO LIMERICK PRISON, TO INCLUDE SIX COURTROOMS, CUSTODY FACILITIES, COURT OFFICES AND ASSOCIATED FACILITIES. AREA 7,609M2 (INCL. 259M2 REFURBISHMENT)
DESCRIPTION NEW COURTHOUSE TO ACCOMMODATE FOUR COURTROOMS AND ASSOCIATED FACILITIES TO BE CONSTRUCTED ON THE SITE OF THE EXISTING MUNICIPAL OFFICES AT WYGRAM PLACE, AND ADAPTATION OF THE EXISTING MUNICIPAL OFFICES BUILDING. AREA c4,680 sq.m.
Wygram Place, Davitt Road North, Wexford, Co. Wexford.
DESCRIPTION REFURBISHMENT AND EXTENSION OF THE EXISTING HISTORIC COURTHOUSE IN WATERFORD TO ACCOMMODATE SIX COURTROOMS, IMPROVED CUSTODY FACILITIES, COURT OFFICES AND ASSOCIATED FACILITIES. AREA 6,392M2 (INCL. 1,798M2 REFURBISHMENT)
DESCRIPTION REFURBISHMENT AND EXTENSION OF THE EXISTING LANDMARK COURTHOUSE BUILDING AT ANGLESEA STREET TO ACCOMMODATE SIX COURTROOMS, IMPROVED CUSTODY FACILITIES, COURT OFFICES, THE REGIONAL OFFICE AND ASSOCIATED FACILITIES. AREA 8,490M2 (INCL. 1,556M2 REFURBISHMENT)
Planning
Development Regulations 2001 to 2013.
Licence to occupy site
accordance with contract for PPP Co. to execute contract.
Design Intent
Project Details
PROCUREMENT OVERVIEW
DAMIAN DUFFY SENIOR PROJECT MANAGER, NDFA
NDFA Act 2002:
value (PPP & Non PPP)
NDFA (Amendment) Act 2007:
authority and transport PPPs
education, justice and health sectors.
(“turnkey”)
NTMA (Amendment) Bill 2014:
National Development Finance Agency
Status of PPP Stimulus Programme
Building Project Tender notice published Expressions of Interest received Tenders Schools Bundle 4 Schools Bundle 5 ITN Q2 2014 GDA-DIT PPP ITN Issued Primary Health Care ITN Q2 2014 Courts Bundle PPP 12 June 2014 ITN Q3 2014 Garda (Police) PPP Withdrawn: to progress with direct Exchequer funding
The Authority’s Project Team for the Project consists of:
Project & Procurement Management NDFA
Financial Advisor NDFA
Legal Advisor McCann FitzGerald
Insurance Advisor Willis
Technical Advisors
Office of Public Works
RPS
Office of Public Works
Office of Public Works
Cyril Sweett
End user representation Courts Service
Authority Project Team
Pre-Procurement phase – Courts Service
Procurement Process and Programme
Procurement phase – National Development Finance Agency
17th April 2014 (closing date for submissions is 12th June 2014)
recent Projects i.e. Schools Bundle 3 PPP and also that being used on the more recent Stimulus Package PPPs (SB4&5 / Grangegorman-DIT).
the Tender phase.
Procurement Process and Programme
Summary of anticipated procurement procedure and indicative timescales:
Stage 1: Pre-Qualification of 3 Candidates (17 weeks): Stage 2: Consultation Period (c. 22-24 weeks):
Stage 3: Tender Evaluation and PT Period (target 6 months)
Procurement Process and Programme
Part 9 planning in place for each site, tenderers to adhere to same
Design Intent provided outlining layouts and adjacencies
Use of self-declarations in prequalification submissions
Reduced level of detail required to be submitted at Tender
Tender Cost Reimbursement provision
Policy decision agreed by Government in December 2012
Initiatives to reduce Tender Cost
OVERVIEW OF DEAL STRUCTURE AND FUNDING
PHILIP RYAN SENIOR FINANCIAL ANALYST, NDFA
25 year Design Build Finance & Maintain PPP Contract
PPP Co. remunerated by a monthly Unitary Charge paid by the Courts Service Construction contract value estimated at circa Ex VAT €120m Construction and Availability risk passed to PPP Co.
Change in Law to reflect PF2 developments
Overview of Deal Structure
25 year service period, expected to include all aspects of
ecurity (passive)
Facilities Management
CEB / ISIF funding possibilities
Authority term sheet envisaged at Tender evaluation stage Debt funding finalised in PT stage Authority open to bank debt and institutional funding solutions
No government equity participation envisaged
Funding
Concession period of 25 years from Service Commencement Date Method of Payment
Construction and Availability risk passed to PPP Co.
Payment Mechanism
Part 9 planning in place Design Intent setting out Authority requirement Tender cost reimbursement arrangements Potential funding solutions available Contract Notice issued 17 April 2014 – Submissions due 12 June 2014 Queries to QueryPPPCourtsPQQ@ntma.ie
NDFA Website > Tender Competitions : Project Information and Market Updates
Closing Comments
Q & A