cornwall insight com tom palmer and tom edwards
play

www.cornwall-insight.com Tom Palmer and Tom Edwards HELPING YOU - PowerPoint PPT Presentation

www.cornwall-insight.com Tom Palmer and Tom Edwards HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS www.cornwall-insight.com 3 HELPING YOU MAKE SENSE OF


  1. www.cornwall-insight.com

  2. Tom Palmer and Tom Edwards HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS

  3. www.cornwall-insight.com 3

  4. HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS

  5. Flexibility market has undergone significant change over the last 6 months often not great • Low capacity market clearing prices • Storage capacity market de-rating • Optimistic revenue assumptions based 2016/17 outturn • CMP264/5 - triad • P354 – spill payments • System Needs and Product Strategy • Medium Combustion Plant Directive • Targeted charging Review Significant Code Review • Storage licencing and co-location • Rough closure & Beast from the East www.cornwall-insight.com 5

  6. Things are changing • Ofgem ‘Supplier Hub’ market arrangements • Regulatory sandbox • Technology developments – peer to peer and blockchain • DSO trials and tenders • Balancing Mechanism • P305 – Par 1 • Project TERRE • Storage costs and competition • Charging futures forum • Coal and nuclear closure • Capacity market review • Route to market offerings and financing arrangements • System Needs and Product Strategy • Smart Meter Roll-out • HH settlement www.cornwall-insight.com 6

  7. HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS

  8. • Increasing competition has driven down prices • Gas reciprocating engines are able to deliver provision at aggregated level • Introduction of P354 in April 2020 will impact non BM participants • Will there be increased participation from gas reciprocating assets and storage, o Competition in Dynamic FFR o Over expectation in wholesale revenues www.cornwall-insight.com 8

  9. Utilisation - £/MWh • Typically dominated by CCGT, Hydro, DSR • Market increasingly occupied by Non-BM participants with spill payments reducing utilisation prices • Availability prices for BM and Availability- £/MW/hr NBM are consistent • The market has yet to price in the P354 changes due to start in 2020 • Recent high level use by National Grid due to low utilisation prices – interaction with O&M agreements www.cornwall-insight.com 9

  10. • Annual Market Report 2016/17 • Total availability payments of £53.6m and £22.3 for utilisation • Key facts o 67% of units are between 3- 10MW o 59.7% can deliver contracted level within 10mins o Average utilisation price of £142.3/MWh o Average contracted prices of £4.2/MW/h for availability o 90% of instructions last for 30 minutes www.cornwall-insight.com 10

  11. • Secondary market still very active and oversubscribed • Dominated by DSR providers and gas/diesel generators • Limited volumes contracted ahead of time • Introduction of EFA blocks may impede revenue stacking potential or change bidding behaviour www.cornwall-insight.com 11

  12. • Prices have levelled out as a result of aggregator and diesel participation • Future changes to static may encourage assets that have traditionally been unable to participate (FCDM and other) – further pressure on prices www.cornwall-insight.com 12

  13. • Market has become oversaturated compared with the requirement • Almost fully contracted until April 2019…but never certain with tender results • Dominated by storage and hydro predominately o recent introduction of EFR • Introduction of EFA and seasonal products may change behaviour www.cornwall-insight.com 13

  14. Max prices fell in Feb to £15/MW/hr, with British Gas Trading Limejump (LJDYQ-1) were ( GHFFR-1) offering Up until April 2017 the battery market was accepted at £20/MW/hr for 3MW 3MW of response. dominated by Noriker Power, Kiwi Power of response. Similarly successful and Limejump. With a limited price range again in Dec & Jan, though of £19.5-20.1/MW/hr. Procuring 16MW of offering 2MW. Statera with 48MW response on average. The lowest accepted price by a battery assets was £6/MW/hr from Limejump (LJDYN-1) offering One accepted British Gas 6MW. Trading battery (GHFFR-1). Offering 3MW of response for just £7.5/MW/hr. *Dynamic response prices www.cornwall-insight.com 14

  15. • In 2018 the service will run from 1 May to 28 October o Demand turn up o Distributed generation turn down or charge • In 2017 138.6MW was accepted from six parties with an average availability was 82MW • Overall utilisation of DTU service: 4% utilisation rate o Driven by lower priced alternative services • DTU was used less in Summer 2017 than anticipated • 2018 footroom requirement expected to range from 0 - 4.5GW www.cornwall-insight.com 15

  16. HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS

  17. Work to date • Rationalisation o STOR Runway o Enhanced Optional STOR Where next • Standardisation • Simplified contract • Platform for Ancillary Services (PAS) What is missing? – Fast Reserve • Bilateral Fast Reserve participants paid – Then STOR for utilisation ~300MW • Planning for TERRE • £1m a month versus >£4m a month • Review outcomes of FFR trial • Register of asset with and without contracts • EFA blocks www.cornwall-insight.com 17

  18. Work to date • Rationalisation o EFR, Rapid FFR, Bridging, FCDM • Simplification (May tender) o Windows and duration Where next o Simplified contract o Auction trial o Testing and compliance What is missing? o Faster acting response • Register of asset with and those terminated • Bilateral information – volume and dates www.cornwall-insight.com 18

  19. Standardised within-day windows Standardised duration of (EFA blocks) contract (traded products) • • 23:00 start of the day Month ahead, Quarter ahead • 4 hour blocks as traded the and Seasons - 30 months • wholesale market No 6 month ahead rule • • Procure up to the minimum 2 bids per unit per tendered • Remaining requirement from period • static market (Total to Min Dyn) P/S, or P/S/H or H only • Increase transparency NGET benefit • Price discovery • Market diversity • Reduce complexity • Balancing Costs • Lower price www.cornwall-insight.com 19

  20. • Webinar held on 14th March • Focus on technical requirement, not commercial • 3 services proposed o Static Containment - post fault – 30 mins or under o Dynamic Balancing - pre fault, maybe 10-30 mins o Dynamic Containment – post fault, maybe 20mins • Procurement from December 2018 www.cornwall-insight.com 20

  21. www.cornwall-insight.com 21

  22. www.cornwall-insight.com 22

  23. www.cornwall-insight.com 23

  24. • First Quarter of 2018 Document outlining the SO's proposed actions in the remaining service areas (reactive power, black start, and constraints) ? • Black Start Strategy ended in April 2018. Exploring the following o Interconnectors o Islanding or Trip to House Load as a restoration service o Renewable generation can contribute to restoration Short-term = Baseline o Black Start service developed with more than one provider Medium-term = Tendered o Spinal Restoration model – energising a single energy corridor Medium-term = Market during restoration, rather than creating power islands www.cornwall-insight.com 24

  25. HELPING YOU MAKE SENSE OF THE HELPING YOU MAKE SENSE OF THE www.cornwall-insight.com ENERGY AND WATER SECTORS ENERGY AND WATER SECTORS

  26. • T-1 auction provided one-year agreements for delivery over winter 2018-19 • Followed T-4 auction in 2014 which secured 49.3GW • T-1 auction procured more capacity than normal – Due to withdrawal of Trafford (CCGT) and Longannet (coal) • 10.7GW of capacity entered auction • 5.8GW awarded agreements • Auction cleared at £6/kW/year o Lowest ever clearing price in a capacity auction www.cornwall-insight.com 26

  27. • T-4 2021-22 auction cleared at £8.40/kW o Record low for four year ahead auction • 74.2GW of capacity entered auction • 50.4GW of capacity awarded agreements www.cornwall-insight.com 27

  28. 55000 53000 51000 49000 De-rated capacity (MW) 47000 45000 43000 41000 39000 37000 35000 2017-18 2018-19 2019-20 2020-21 2021-22 Existing Generating CMU New Build Generating CMU Refurbishing Generating CMU Proven DSR CMU Unproven DSR CMU Existing Interconnector CMU New Build Interconnector CMU www.cornwall-insight.com 28

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend