connection
play

CONNECTION Public Information Centre November 16, 2015 Agenda - PowerPoint PPT Presentation

LAKEVIEW WATERFRONT CONNECTION Public Information Centre November 16, 2015 Agenda Opening Remarks Status Update Proposed new construction access route Updated conservation area detailed design Status Update Environmental


  1. LAKEVIEW WATERFRONT CONNECTION Public Information Centre November 16, 2015

  2. Agenda • Opening Remarks • Status Update • Proposed new construction access route • Updated conservation area detailed design

  3. Status Update Environmental Assessment • Final EA submitted May 2 2014 • MOECC Approval May 27 2015 Design • Design work by team underway • Input from public and through permitting process in next few months • EA Amendment for Preferred Construction Access Route

  4. Preferred Alternative: 1.5M m 3 Footprint

  5. LWC Gains to the Mississauga Waterfront Existing Habitat % Habitat Lakeview Waterfront % increase in habitat (ha) Connection from LWC Meadow 225.47 6.0% 11.8 ha 4.97% Cobble beach 1.7 0.0005% 1.0 ha 58.5% Forest 485.26 12.9% 4.6 ha 1.02% Wetlands 18.4 0.5% 6.2 ha 20.2% Swamp 12.07 0.3% 1.5 ha 11.05% Rocky islands 0 ha 0 0.8 ha Total 742.9 26 ha LOISS Study Area = 3764.97 ha

  6. Project Costs LWC Cost Components 2013 2015 *Design - $1,200,000 Property Acquisition and Access $1,289,000 $2,908,000 Road Construction Construction $34,111,000 $42,952,000 *TRCA/CVC Project Management $6,300,000 $7,200,000 Cost Contingency $12,500,000 $5,432,000 Recovery -$23,600,000 -$23,600,000 Total $30,600,000 $36,100,000

  7. New Construction Access Route

  8. Interim Channel and Construction Route

  9. Benefits and Impacts of New Route 1c Main benefits • Phases project from west away from users of WT, Marie Curtis Park & Arsenal Lands • Allows for earlier establishment of terrestrial and wetland habitats • If required, possibly provide western trail link in event Inspiration Lakeview not sufficiently underway • Does not impede Arsenal Lands Master Planning and built-heritage features • Avoids temporary relocation of Waterfront Trail • Goes through less functional habitat and potentially impacts less rare plants • Further soil studies and treatment are not required Main Impacts • Requires temporary stream crossing • Located within potential Bobolink habitat • Requires removal of ~30 trees largely non-native/invasive with two locally rare plants • Passes through City of Mississauga Natural Areas System LV2 (poor quality habitat) • Cost • Pinch point north of WWTF and absence of traffic lights at Lakeview and WWTF driveway CONCLUSION – Preferred POST AMENDMENT DOCUMENT ON WEBSITE & WITH MOECC

  10. DISCUSSION ON EA AMENDMENT

  11. CONFIRMING COASTAL DESIGN

  12. Physical Model Outcomes Key Outcomes of the Physical Modeling: Able to test shoreline function and habitat stability over wide range of lake levels and wave sizes to account for normal cycles and Climate Change Reduced volume of purchased aggregate materials in the order of $2-$3M Identified design changes to ensure beach stability Explored beach sediment transport patterns and circulation behind the islands Examined ability of Applewood Creek to clear cobbles from outlets and directed design to reduce formation of large cobble plugs

  13. Refined Design

  14. Refined Design – Depicting Terrain

  15. Design Features 9. Seating Node (Typical)

  16. Sample Cross-sections

  17. OUTLOOKS 3 – Interpretative Boardwalk 2 – Seating Node 4 – Serson Wetland 1 - Promontory 5 - Seawall

  18. Promontory Key Features: Cobble beach with islands Toronto Skyline Revetment Trail

  19. Seating Node Key Features: Three tiers of armourstone seating Grass between tiers and natural viewscape

  20. Cross-Section of Seating Node & Trail Seating Node Seating Node

  21. Eastern Tie-off Area Key Features: Groyne: • Large Stone • 30-40m long • Emergent to Elevation 77- 76msl • Top end can be buried by beach material Trail Connection to WT: • Straight connection through woods • Curved connection along woods edge

  22. Constructed Island Key Features: Curvilinear Armourstone Island Navigation Lights

  23. Operations and Maintenance Key Features: • Passive use conservation area (walking, running, cycling, fishing, etc.) • CVC management and enforcement • Daylight hours of operation • Dogs on leash enforced; no boating or skating • Accessibility features (Built environment standards) • Natural park aesthetic • CPTED design principles (no lighting, site lines maintained, access point control, etc). • Minimal infrastructure; vandalism resistant features • Visitor monitoring (visitation numbers, visitor flow, impacts, etc) • Educational programming and research opportunities (in combination with Arsenal dev) • Self-guided interpretive signage • Special event spaces and opportunities (First Nations ceremonial, etc.)

  24. Construction Phasing

  25. Construction Phase vs Completion Phase

  26. AERIAL TOUR OF LAKEVIEW

  27. Schedule Task Date Region of Peel receives design proposal and October 22 2015 supports Project Construction Initiate construction of access road (assuming EA Early 2016 Amendment Approved by end of December) Start building rubble cell (Fisheries window July 2016 guidelines allows work from July 1 st to March 30 th ) Anticipated rubble Cell 1 completion Fall 2016 Fill material can be accepted at LWC Fall 2016 Construction from west to east Until 2023-2026

  28. Thank you!

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend