AMA-T-00014
Commercial Mining Booster Infrastructure Project A novel approach - - PowerPoint PPT Presentation
Commercial Mining Booster Infrastructure Project A novel approach - - PowerPoint PPT Presentation
AMA-T-00014 Commercial Mining Booster Infrastructure Project A novel approach to the manufacture of Boosters for the Mining Industry The Background AMA-T-00014 In 2016 Australian Munitions and Orica signed contract for the manufacture
OPEN
2 4/12/2017
AMA-T-00014
The Background
- In 2016 Australian Munitions and
Orica signed contract for the manufacture of Commercial Mining Boosters
- This required the development of a
new capability to be installed at Australian Munitions’ Benalla facility.
OPEN
3 4/12/2017
AMA-T-00014
The Plan
- What is a Mining Booster?
- The Existing Benalla Facility
- The Design Process
- New Explosives
- The New Production Facility
- Logistics
- The Benefits to our Customers
- The Wrap Up
- Thank You
OPEN
4 4/12/2017
AMA-T-00014
What is a Mining Booster?
- Small Explosive Device comprising:
- A plastic shell
- A sensitiser bottle (filled with PETN)
- Cast Mix Fill of RDX/TNT
- Used to help detonate large charges
(typically bulk emulsion)
- Used extensively across Australia’s
Mining and Construction Industry.
Image Courtesy of Orica Limited
OPEN
5 4/12/2017
AMA-T-00014
The Existing Benalla Facility
- Utilises two existing buildings in
Benalla – S05 and S03
- New capability had to integrate with
existing infrastructure
- And allow for quick changeover between
Booster Manufacture and Traditional Defence Stores.
- Uses the existing Meissner Shell
Filling Plant in S03
Satellite imagery courtesy of Google Earth.
OPEN
6 4/12/2017
AMA-T-00014
The Design Process
- Requirements Specifications Developed
- Supplier Selection Process – Chorus 2.0
- Multi Stage Risk Assessment Process
- HAZOP Studies
- Plant Risk Assessments
- Input from Orica Subject Matter Experts
- Particular emphasis on PETN – New to Benalla
- Need for High Levels of Automation
- Minimise exposure of personnel
- Ability to compete with overseas labour rates
- Use of modern control systems in Hazardous
Areas
Image Source: https://www.graphicproducts.com/articles/what-is-hazop/
OPEN
7 4/12/2017
AMA-T-00014
The Design Process
Concept
Independent Explosives Safety Validation
HAZOP Detailed Design CHAZOP
Five day workshop with input from Orica SMEs, Thales SMEs, Machine Designers and Operators. Three day workshop with input from Orica SME, Thales SMEs, and Machine Designers – focussed on control systems.
Weekly Design Reviews with sub-contractors Input from Orica SMEs when required
An Internal validation of the project management and safety principals being used.
OPEN
8 4/12/2017
AMA-T-00014
The Design Process
Build Factory Commissioning Factory Acceptance
Install
Frequent Site Visits, Acceptance Tests and Communication between Project team and Designers An opportunity to test in a workshop environment and confirm machine functionality A series of tests to confirm that all elements of the machine meet the original specification (or any agreed to changes) Involves attempting to break the safety systems to ensure they are robust.
OPEN
9 4/12/2017
AMA-T-00014
The Design Process
Plant Risk Assessment Inert Commissioning
External Safety Audit
Live Commissioning
Risk assessment focussing on plant safety (entanglement, cutting etc.) Completed by Internationally renowned explosive safety specialist
OPEN
10 4/12/2017
AMA-T-00014
New Explosives
As well as a new Production Facility, New Explosives were introduced. Bodies of work were conducted to understand these. Crude RDX/TNT:
- Lab Testing of Crude RDX Composition to
confirm long term stability
- Performance Testing
- Boosters filled with Crude RDX/TNT were X-
Rayed and Fired against witness plates.
PETN:
- Separation Distance Trials
- Conducted with and without Baffles
between samples
- Probit and FISH Data sourced from Orica
- Testing of “high speed” Near Infrared
Moisture sensing for Dried PETN
OPEN
11 4/12/2017
AMA-T-00014
The New Production Facility – PETN Drying
- 24 Stations, each holding
13kg PETN
- Warm air drawn through
PETN by Scrubber
- Approximately 6 Hour dry
cycle
- Typically Operated during
silent hours to minimise Operator exposure.
- Instant Moisture Content
Reading from NIR sensor
- Container used for drying
also used in Bottling process
OPEN
12 4/12/2017
AMA-T-00014
The New Production Facility – PETN Bottling
- Manned section and Unmanned
(remote) section
- Handling Empty Bottles, Dried
PETN and Caps
- Automated Quality Assurance
Checks
- Single Shift operation to match 3
shift LAP.
OPEN
13 4/12/2017
AMA-T-00014
The New Production Facility – Load, Assemble, Pack
OPEN
14 4/12/2017
AMA-T-00014
Logistics
- Increase in HE throughput for Benalla and Mulwala
- Management of Magazines
- Management of Building and Bay NEQs
- Update to DG Manifest
- Large volumes of raw materials
- Management of Incoming goods and returnable
packaging
- Transport of parts to workstations
- Introduction of 24 hour HE operation in Benalla
- Recruitment and training of new staff
- Technical, Mechanical and Electrical support for
afternoon and night shift
OPEN
15 4/12/2017
AMA-T-00014
The Benefit to our Customers – Australian Defence Force
- Maintain Skillsets for manufacture of defence
munitions
- Keeping staff (and plant) in a state of readiness
- Maintaining knowledge and a safety mindset ensure we
are always operationally ready for a shift to Defence Manufacture.
- Increase the utilisation of assets in Benalla and
Mulwala that had been underutilised in the past
- Underused machines tend to develop reliability
challenges such as corrosion, erosion, blockages etc.
- Using the plant frequently helps overcome these
challenges
OPEN
16 4/12/2017
AMA-T-00014
The Benefit to our Customers – Orica
- Improved Quality
- Including 100% automated checks for weight and
cleanliness
- Consistency of finished product through the use
- f Automation
- Shorter supply chains
- Product for the Australian Market is made in
Australia
- Improved logistics
- Location of the Benalla and Mulwala Sites with
respect to Orica’s Storage Facilities
OPEN
17 4/12/2017
AMA-T-00014
The Wrap-Up
- Australian Munitions now has a world class Booster
Manufacturing Facility
- Highly automated
- Incorporating existing infrastructure
- The design process worked through concept – detailed design –
build – install – commission
- Input from SMEs
- Thorough Risk Assessment process
- Resulting in benefits to the ADF and to Orica
OPEN
18 4/12/2017
AMA-T-00014
Thank You
- Thanks to the following for input to and content for this
presentation (in no particular order):
- Orica Limited
- Ryan Krake – LAP Video
- Ken Horne – PETN Bottling Content
- James Halacas – Meissner Plant Content
- Mulwala Trials Team
- The Benalla operations team – in particular, those featured in photos or videos