Questions & Comments Public Meeting for 36 th Avenue West Project from Tecumseh Road to north of Market Place Comments may be provided as follows: In-Person Attendance: Comment forms are provided and should be submitted to the


slide-1
SLIDE 1

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Comments may be provided as follows:

In-Person Attendance: Comment forms are provided and should be submitted to the meeting moderator (please discard your pencil after use)

Email comments to: Paul.Dandrea@normanok.gov

YouTube: Post questions to YouTube “LIVE CHAT” window. Do Do not

  • t post your

questions in the “COMMENTS” section as it is not being monitored

Printable forms on the 36th Ave. NW project page at www.normanok.gov

Mail forms to: City of Norman Attn: Paul D’Andrea 201 W. Gray St, Bldg. A Norman, OK 73069

Comments du due by August 1 13, 2020

Questions & Comments

slide-2
SLIDE 2

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

City of

  • f Nor
  • rman Pu

Public M Mee eeting 36 36th

th Aven

enue N NW Wide dening Pr Proj

  • jec

ect From

  • m T

Tec ecumseh R Roa

  • ad t

d to

  • nor
  • rth of
  • f Market Pl

Place

slide-3
SLIDE 3

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

  • Ron Brown, Division III Engineer
  • Brandon Sims, Local Government Division
  • Michael J. Knapik, Design Consultant
  • Scott Stegmann, Environmental Consultant
  • Shawn O’Leary, Director of Public Works
  • Scott Sturtz, City Engineer
  • Paul D’Andrea, Capital Projects Engineer
  • Mayor Breea Clark
  • Council Member Matthew Peacock, Ward 8
  • City Manager, Darrel Pyle

Project Team

CITY OF NORMAN CP&Y

OKLAHOMA DEPARTMENT OF TRANSPORTATION

slide-4
SLIDE 4

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Benefits

− Reduces traffic congestion − Improves traffic safety − ADA accessible sidewalks − Dedicated bike routes − Continuation of Legacy Trail from Tecumseh Road to Ruby

Grant Park

− Safer intersections: Franklin – Indian Hills − Improvements to public & private utilities

slide-5
SLIDE 5

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown Phase One

Begin north of Tecumseh Road Intersection Improvements

End north of Franklin Road and Franklin Road Intersection Improvements

Signalized Intersections at:

Franklin Road

All Saints School

slide-6
SLIDE 6

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown Phase Two

Begins at the end of Phase One and Franklin Road Intersection Improvements

Ends north of Market Place and Indian Hills Intersection Improvements

Signalized Intersection at Indian Hills Road

slide-7
SLIDE 7

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Proposed Enhancements

Phase One Roadway Improvements

5-lane roadway

11-foot wide driving lanes

Improved sight distance through correcting vertical curves

Addition of a storm water system

Continuous sidewalks on both sides of the street (Legacy Trail on east side)

Multimodal improvements including bike lanes

Proposed Roadway Cross Section

slide-8
SLIDE 8

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Proposed Enhancements

Phase Two Roadway Improvements

4-lane roadway

11-foot wide driving lanes

Improved sight distance through correcting vertical curves

Addition of a storm water system

Continuous sidewalks on both sides of the street

Multimodal improvements including bike lanes through Indian Hills Road

Proposed Roadway Cross Section

slide-9
SLIDE 9

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Proposed Enhancements

Multimodal Enhancements

5-foot wide bicycle routes

Legacy Trail multi-modal path on east side of 36th Ave. NW from Tecumseh

  • Rd. To Franklin Rd.

Continuous sidewalks throughout the corridor

ADA Compliance upgrades to existing facilities

slide-10
SLIDE 10

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase One – Begin Project

Constructed in 2000

5 lane signalized intersection

This project will tie onto the north leg of the Tecumseh Road intersection

Begin dedicated bike lane southbound

Bike to utilize trail for northbound

slide-11
SLIDE 11

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase One – Mid-Block Signal

Signalized intersection with pedestrian crossing

Realigned entrance to All Saints School

slide-12
SLIDE 12

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase One – Franklin Road Intersection

Signalized intersection with pedestrian crossings

Dedicated left and right turn lanes for all 4 Legs

Begin dedicated bike route northbound

slide-13
SLIDE 13

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase One/Phase Two – Project End/Begin

Phase Two of project scheduled to begin one year from Phase One

Bridge class culvert to replace 2-48 inch pipes

slide-14
SLIDE 14

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase Two – Indian Hills Road Intersection

Signalized intersection with pedestrian crossings

Dedicated left and right turn lanes for all 4 Legs

slide-15
SLIDE 15

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Project Breakdown

Phase Two – End of Project

Dedicated southbound turn lane for Market Place

End dedicated bike route northbound

slide-16
SLIDE 16

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Utility Relocations

City Utilities

Water Line (Norman and OKC)

Sanitary Sewer

Privately Owned Utilities

OG&E Distribution Line

OEC Distribution Line

Western Farmers Transmission Line

ONG Gas Line

Phone and communications

Utility construction has begun

slide-17
SLIDE 17

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Environmental Review

NEPA Process

Community Impacts Wetlands Endangered Species Safety All Applicable Federal Laws Flexible Design State & Local Law Transportation Enhancements Traditional Cultural Properties Environmental Justice Parklands Air Quality Historic

NEPA Process

Community Impacts Wetlands Endangered Species Safety All Applicable Federal Laws Flexible Design State & Local Law Transportation Enhancements Traditional Cultural Properties Environmental Justice Parklands Air Quality Historic

National Environmental Policy Act (NEPA)

Decision Making Process

NEPA is required when federal funding is provided for transportation projects

slide-18
SLIDE 18

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Environmental Review

Environmental Process

Public Meeting (Input) Incorporate Comments Environmental Studies Document Submission Approval

Construction Plans

slide-19
SLIDE 19

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Environmental Issues Considered, Studied, & Evaluated

Environmental Review

Right-of-Way Impacts

Wetland Impacts

Stream Impacts

Floodplain Impacts

Farmland Impacts

Threatened & Endangered Species

Tribal Concerns

Cultural Issues

Archeological Sites

Hazardous Waste Sites

Park Impacts

Traffic Noise Impacts

slide-20
SLIDE 20

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Right-of-Way Impacts

Environmental Review − Some right-of-way required, no displacements − Ruby Grant park land will not be affected

Stream & Wetland Impacts

− Impacts to waters anticipated, requires Corps of Engineers review

Cultural Issues & Archeological Sites

− No cultural or archeological impacts

slide-21
SLIDE 21

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Noise Study

Environmental Review

Completed in accordance with FHWA regulations and ODOT noise policy

Utilized the FHWA Traffic Noise Model in predicting existing and future noise levels based on roadway geometry, traffic data, receiver location, and general terrain features

Modeled receiver input being a location where frequent exterior human activity occurs such as a patio, playground, or pool area

For residential dwellings, an exterior impact occurs when future noise levels meet or exceed 66 dBA

  • r when there is a substantial increase in future noise levels that exceed existing levels by 15 decibels
slide-22
SLIDE 22

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Noise Study – Results of the Analysis

Environmental Review

− For the existing condition, no residential receivers are impacted with noise levels meeting or exceeding 66 dBA. − Based on the proposed project and future traffic, 8 residential receivers will be impacted with future noise levels ranging from 66.7 to 69.4 dBA. The highest increase over existing sound levels is 5.3 dBA. − Future impacts occur to the near receivers in Castlerock and the residential area located just south of Indian Hills Road

slide-23
SLIDE 23

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Noise Study – Noise Mitigation Considerations

Environmental Review

− Noise mitigation in the form of a free standing noise wall within the existing right-

  • f-way was considered for the impacted residential dwellings.

− For those impacted receivers within Castlerock, noise mitigation was determined not feasible because the modeled noise barrier did not achieve the required noise reduction of 7 dBA. − For the impacted receiver identified south of Indian Hills Road, noise mitigation was determined not reasonable due to the high construction cost for the benefitted receiver.

slide-24
SLIDE 24

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Schedule

Receive comments from public thru August 13, 2020

Complete environmental documents Fall 2020

Right-of-way acquisition & utility relocations Ongoing

Construct project

Phase One ASAP Pending Federal Transportation Grant Funding

Phase Two ASAP Pending Federal Transportation Grant Funding

Project Schedule

slide-25
SLIDE 25

Public Meeting for 36th Avenue West Project from Tecumseh Road to north of Market Place

Comments may be provided as follows:

In-Person Attendance: Comment forms are provided and should be submitted to the meeting moderator (please discard your pencil after use)

Email comments to: Paul.Dandrea@normanok.gov

YouTube: Post questions to YouTube “LIVE CHAT” window. Do Do not

  • t post your

questions in the “COMMENTS” section as it is not being monitored

Printable forms on the 36th Ave. NW project page at www.normanok.gov

Mail forms to: City of Norman Attn: Paul D’Andrea 201 W. Gray St, Bldg. A Norman, OK 73069

Comments du due by August 1 13, 2020

Questions & Comments