com m ents on the muskrat falls reference
play

Com m ents on the Muskrat Falls Reference Presentation to the - PowerPoint PPT Presentation

www.centrehelios.org Com m ents on the Muskrat Falls Reference Presentation to the Public Utilities Board of Newfoundland and Labrador Newfoundland and Labrador Philip Raphals For Grand Riverkeeper Labrador Inc. F G d Ri k L b d I


  1. www.centrehelios.org Com m ents on the Muskrat Falls Reference Presentation to the Public Utilities Board of Newfoundland and Labrador Newfoundland and Labrador Philip Raphals For Grand Riverkeeper Labrador Inc. F G d Ri k L b d I February 23, 2012 1

  2. www. centrehelios.org O ti Optimality lit  « How did you ensure that  « How did you ensure that … you were you were dealing with the optimal scenario under each one? » > Technical optimization vs. planning processes > Iterative process seeking robust solutions > Real time (evolutive) versus planning exercise > Avoiding irrevocable choices that would turn out badly in certain possible futures out badly in certain possible futures > Scenario versus plan 2

  3. www. centrehelios.org PPA PPA payment options t ti  “Does the 2035 ratepayer have to pay  Does the 2035 ratepayer have to pay more so that the 2017 ratepayer can pay less?” less? > Nominal LUECs vs. escalating prices > Same present value, but different reality > Consumers unlikely to prefer escalating prices 3

  4. www. centrehelios.org PPA vs COS PPA COS  Simulate annual costs for Muskrat  Simulate annual costs for Muskrat Falls under COS > Higher than PPA in early years Hi h th PPA i l > Drastically lower in later years  Prices post 2067 > PPA: maintaining 2067 price levels ($400/MWh) ⇒ windfall profits $ > COS: continue to decline (< $20/MWh) 4

  5. www. centrehelios.org CDM CDM  MHI  MHI > model CDM like generation > End-use modelling  Nalcor’s approach > Integrate into load forecast through technological change variable > No mesure-by-mesure or program-by-program analysis  Objectives to date not met  Sensitivities > Far less than Marbek scenarios > At low demand (= high CDM) scenarios, ( g ) , CPW preference for Muskrat drastically reduced 5

  6. www. centrehelios.org 6 NWPPC fuel forecast 2009 Fuel price forecasts t f i l F

  7. www. centrehelios.org 7 EIA Retrospective Review i R ti EIA R t

  8. www. centrehelios.org Wi d Wind power assessment t  2004 NLH study  2004 NLH study > Sole source for Strategist inputs > 80 MW limits primarily economic > 80 MW limits primarily economic • Based on minimizing spill • Fails to take into account cost of wind, net of curtailment or spills curtailment or spills > « preliminary » > Government RFP shows that higher Go e e t s o s t at g e penetration remains an objective 8

  9. www. centrehelios.org C Conclusions l i  Reference question  Reference question > Verify that the costs attributed to each scenario are correct? > Verify that each scenario makes sense? V if th t h i k ?  Analyses of MHI and others > Results highly dependent on assumptions g y p p > Great uncertainties > Little confidence that the Isolated Island scenario would play out as defined play out as defined  If Muskrat Falls does not go forward > planning process will continue > May lead to solutions very different from IIS  Thus Reference Question largely academic 9

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.

Recommend


More recommend