Subcontractor Informational Meeting August 12, 2016
Cleveland Opportunity Corridor Project Section 3 Subcontractor - - PowerPoint PPT Presentation
Cleveland Opportunity Corridor Project Section 3 Subcontractor - - PowerPoint PPT Presentation
Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview Title Q&A
Title
Subtitle Date
Title
Subtitle Date
Agenda
- Welcome and Opening Remarks
- Project Overview
- Prequalifications & Work Types
- Procurement Overview
- Q&A
- Adjourn
Overall Project Purpose and Need Improve the roadway network within a historically underserved, economically depressed area in the City of Cleveland
Opening Remarks
- Deliver the Project at or below budget.
- Deliver a positive economic impact to the
community through Diversity and Inclusion efforts.
- Maximize team diversity (quantity and type) for
project specific goals by the inclusion of the percent and number of available firms utilized on the project.
- Maximize quality, meeting or exceeding applicable
standards in all areas.
Opening Remarks – Project Goals
- Minimize duration of traffic impacts and open
Opportunity Corridor Boulevard no later than November 1, 2019.
- Meet or exceed aesthetics and sustainability
guidelines.
- Deliver the Project with zero lost-time incidents.
- Demolish existing residential and commercial
structures as soon as possible.
Opening Remarks – Project Goals
Continued
Project Overview
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Roadway)
- New Roadway
− Construct two miles of 5 lane road (I-490 to E 93rd St)
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Roadway)
- Existing Roadways
−
- E. 55th Street
− Kinsman Road −
- E. 75th Street
−
- E. 79th Street
− Rawlings Avenue − Buckeye Road − Woodland Avenue − Removal of various local streets
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Basic Configuration
- Typical Sections
− Number of lanes − Lane and shoulder widths − Median width and type − Sidewalk and multi-use path width and relative locations − Tree lawn widths and relative locations
- Centerline and vertical alignments may be modified
as long as:
− No new right-of-way − Revisions meet contract requirements, including vertical clearance − No new design exceptions − Vertical alignment grades less than 5% on OC boulevard
- Aesthetic Criteria
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Structures)
New Structures 1.
- E. 55th Street over OC Boulevard
2. Pedestrian Bridge over OC Boulevard at E. 59th Street 3. OC Boulevard over Kingsbury Run ravine and GCRTA test track 4. OC Boulevard over GCRTA Blue and Green Lines 5. NS Railroad over OC Boulevard 6. Pedestrian Bridge over NS/RTA at E 89th Street
1 2 3 4 5 6
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Structures)
Removal of Structures 1. NS Railroad over vacated Grand Avenue 2.
- E. 89th Street Pedestrian Bridge
2 1
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Rail Involvement)
1
1
1
2
1
3
1
4
1
5
1
6
- 1. OC Boulevard bridge over GCRTA test track in the Kingsbury Run Valley
- 2. OC Boulevard bridge over GCRTA Blue/Green Lines
- 3. OC Boulevard under NS mainline (3 phase track location)
- 4. Remove existing Grand Avenue under NS mainline
- 5. Sewer bore under NS Nickelplate line
- 6. OC Pedestrian bridge over NS and GCRTA at E. 89th Street
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Utilities)
- New storm sewer (including retention basin, junction
chamber, bored sewer under railroad)
- Reconfigure CPP power distribution system
- New water mains (transmission and distribution)
- New/relocated sanitary sewers (including regulator
relocation)
- Coordination with private utilities
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Environmental)
- Obtain all permits and pay associated fees
- 401 and 404 permits not anticipated
- DBT prepares SWPPP; ODOT prepares NOI
- No tree removal from April 1 to September 30 due to
Indiana Bat & Northern Long-Eared Bat
- ODOT will perform asbestos surveys for bridge removals
- Phase II ESA reports under development for 34 sites
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Diversity & Inclusion)
- New, Small, Local, and EDGE
- Business Development
- Outreach
- OJT
NEW: Established within 5 years or never worked on an ODOT project SMALL: On SBE list or meet requirements defined in RFQ LOCAL: Have a physical office in Cuyahoga County or Lorain County since August 1, 2014 EDGE: Certified EDGE (Encouraging Diversity, Growth, and Equity) business
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Scope (Other)
- Right of Way
− ODOT is acquiring properties − Availability table will be provided
- Building Demolition
− 12 structures (mostly commercial) − ODOT in the process of acquiring properties and structures − Most residential structures are being demolished under OC2 project (PID 98695)
Title
Subtitle Date
Title
Subtitle Date
Project Overview – Schedule
- Substantial Completion: November 1, 2019
− Opportunity Corridor open to traffic − Intermittent local street closures and landscaping continues
- Final Completion: June 30, 2020
Title
Subtitle Date
Title
Subtitle Date
Prequalifications & Work Types
Title
Subtitle Date
Title
Subtitle Date
Prequalifications (Design)
CATEGORY Roadway: Bicycle Facilities and Enhancement Design Complex Roadway Design Subsurface Utility Engineering Bridge Design: Level 2 Bridge Design Level 3 Bridge Design (for the elements of the bridge proposed by the DBT that exceed Level 2 Bridge Design) Bridge Design Sub-factors: Complex geometry Soils/Geotechnical Services: Geotechnical Engineering Services Geotechnical Testing Laboratory Geotechnical Field Exploration Services Geotechnical Drilling Inspection Services Traffic Signal Design: Traffic Signal System Design Highway Lighting Design: Complex Lighting Design Environmental Documentation: Environmental Site Assessment Phase II ***All prequalified engineering consultants must be prequalified in ODOT’s COST ACCOUNTING SYSTEM.
The Design Build Team must list relevant prequalification categories for Consultant and Sub-Consultants to show that the prequalification requirements listed are satisfied.
Anticipated Work Types (Construction)
CODE DESCRIPTION
1 Clearing & Grubbing 2 Building Removal 4 Roadway Excavation & Embankment Construction 5 Major Roadway Excavations 6 Incidental Grading 7 Soil Stabilization 8 Temporary Soil Erosion & Sediment Control 9 Aggregate Bases 10 Flexible Paving 12 Rigid Paving 13 Pavement Planning, Milling, Scarification 15 Sawing 16 Flexible Replacement 17 Rigid Replacement 19 Structure Removal 21 Level 2 Bridge 23 Reinforcing Steel 24 Structural Steel Erection 26 Structural Steel Painting
CODE DESCRIPTION
27 Expansion & Contraction Joints, Joint sealers, Bearing Devices 28 Caissons / Drilled Shafts 34 Earth Retaining Structures 35 Drainage (Culverts, Misc.) 36 Guardrail / Attenuators 37 Fence 38
- Misc. Concrete
39 Maintaining Traffic 42 Signing 43 Highway Lighting 44 Traffic Signals-Standard 45 Pavement Markings 46 Landscaping 48 Trucking 53 Piling 54 Post-Tensioning Bridge Members 57 Sealing of Concrete Surfaces with Epoxy or Non- Epoxy Sealers
Roadway & Pavement
CODE DESCRIPTION
1 Clearing & Grubbing 2 Building Removal 4 Roadway Excavation & Embankment Construction 5 Major Roadway Excavations 6 Incidental Grading 7 Soil Stabilization 8 Temporary Soil Erosion & Sediment Control 9 Aggregate Bases 10 Flexible Paving 12 Rigid Paving 13 Pavement Planning, Milling, Scarification 15 Sawing 16 Flexible Replacement 17 Rigid Pavement Replacement 36 Guardrail / Attenuators 37 Fence 38
- Misc. Concrete
48 Trucking
- Construct two miles of 5
lane road (I-490 to E 93rd St)
- Asphalt Pavement
- Concrete Pavement
- Geotextile Subgrade
- Multipurpose Path
- Building Removal
Drainage, Erosion Control & Water Work
- Drainage Structure
Connections
- Erosion Control
- Transmission and
Distribution Watermains
- Sanitary Sewers
CODE DESCRIPTION 4 Roadway Excavation & Embankment Construction 6 Incidental Grading 8 Temporary Soil Erosion & Sediment Control 35 Drainage (Culverts, Misc.) 48 Trucking
Traffic Control, Signals & Lighting
- LED Street Lighting
- CPP Underground
Power System
- High efficiency LED
fixtures
- 150-foot pole spacing
- Underground circuitry
CODE DESCRIPTION 42 Signing 43 Highway Lighting 44 Traffic Signals-Standard 45 Pavement Markings
Maintenance of Traffic
CODE DESCRIPTION 39 Maintenance of Traffic
- Phases and Detours
- GCRTA and EMS
Coordination
- Pedestrian Traffic
- Norfolk Southern
Coordination
Structures
CODE DESCRIPTION 19 Structure Removal 21 Level 2 Bridge 23 Reinforcing Steel 24 Structural Steel Erection 26 Structural Steel Painting 27 Expansion & Contraction Joints, Joint sealers, Bearing Devices 28 Caissons / Drilled Shafts 34 Earth Retaining Structures 35 Drainage (Culverts, Misc.) 48 Trucking 53 Piling 54 Post-Tensioning Bridge 57 Sealing of Concrete Surfaces with Epoxy or Non-Epoxy Sealers
New Structures 1.
- E. 55th Street over OC Boulevard
2. Pedestrian Bridge over OC Boulevard at E. 59th Street 3. OC Boulevard over Kingsbury Run ravine and GCRTA test track 4. OC Boulevard over GCRTA Blue and Green Lines 5. NS Railroad over OC Boulevard 6. Pedestrian Bridge over NS/RTA at E 89th Street Removal of Structures 1. NS Railroad over vacated Grand Avenue 2.
- E. 89th Street Pedestrian Bridge
Landscaping
- Landscape
(plantings)
- Street Trees
- Medians and
tree lawns
CODE DESCRIPTION 46 Landscaping 48 Trucking