City of Burnaby Presentation
2014 March
Kinder Morgan National Energy Board (NEB) Application for the Trans Mountain Expansion Project (TMEP)
City of Burnaby Presentation Kinder Morgan National Energy Board - - PowerPoint PPT Presentation
City of Burnaby Presentation Kinder Morgan National Energy Board (NEB) Application for the Trans Mountain Expansion Project (TMEP) 2014 March Presentation Outline Scope of Project Overview of the Trans Mountain Expansion Project (TMEP)
2014 March
Kinder Morgan National Energy Board (NEB) Application for the Trans Mountain Expansion Project (TMEP)
Scope of Project
National Energy Board
City Response
KM’s Initial Proposal 750,000 bpd Dual line operation “Twinning” of Pipeline 1000 km of new pipeline
Pump Station, Storage and Marine Terminal Expansion
Application to the NEB
890,000 bpd Product: Heavy crude
Langley to Burnaby – new corridor
980 km of new pipeline (reactivation of lines) Expansion concentrated in Burnaby
agreements for 15- and 20-year terms
707,500 bpd of the proposed 890,000 bpd
This map illustrates the existing Trans Mountain Pipeline through Burnaby
negotiated easement agreements
Written Permission/Permit Required for works within the Safety Zone:
right of way where a roadway does not exist;
Dual- line operation to introduce heavy crude product “Twinning” new pipeline within existing ROW, where possible
Line 1 (existing): 350,000 bpd* Line 2 (heavy crude): 540,000 bpd Separate new corridor * KM has indicated Line 1 may also be used for heavy crude at lowered capacities
This map illustrates the route options Kinder Morgan presented to the City in December 2012.
The highlighted areas represent the routing and alignment study areas for the proposed pipeline.
WESTRIDGE/ LOCHDALE FOREST GROVE/ LAKE CITY LOUGHEED TOWN CENTRE
The circles represent the neighbourhoods that would be directly affected by the proposed routing and alignment study areas.
Pipeline Expansion
Initial Proposal Consolidation of Burnaby Mountain Terminal – Westridge Marine Terminal distribution line 2 distribution lines through the neighbourhood within a single ROW Current Proposal Creating a new route through Westridge Neighbourhood to accommodate two 30” pipelines 3 distribution lines through the neighbourhood within two ROWs
WESTRIDGE ELEMENTARY LOCHDALE ELEMENTARY FOREST GROVE ELEMENARY BURNABY MOUNTAIN SECONDARY CAMERON ELEMENTARY STONEY CREEK COMMUNITY SCHOOL LYNDHURST ELEMENTARY
This map highlights the schools that may be impacted by the routing and alignment study areas for the proposed pipeline.
BRUNETTE RIVER AND CONSERVATION AREA BURNABY MOUNTAIN/ BURNABY 200 CONSERVATION AREAS BURNABY MOUNTAIN CONSERVATION AREA
This map highlights the conservation and environmentally sensitive areas that may be affected by the routing and alignment study areas for the proposed pipeline.
Construction of previously twinned section of the TMPL Jasper, Alberta
7185 Shellmont Street | 189 acre site Existing Site Context
13 storage tanks | 125,000 bbl – 130,000 bbl | Capacity: 1.7 million bbl Existing Burnaby Mountain Terminal Site
2 Local Watersheds Existing Site Context
14 new storage tanks | 250,000 bbl – 325, 000 bbl | Capacity: 5.6 million bbl Conceptual Burnaby Mountain Terminal Expansion
New Storage Tank Replacement Storage Tank
* Note: this layout is for demonstration purposes only.
Current Volume of Oil Per Unit: 8,995 bbl per acre (3,535 m3 per hectare)
Current Volume of Oil Per Unit: 8,995 bbl per acre (3,535 m3 per hectare)
Proposed Volume of Oil Per Unit: 29,630 bbl per acre (11,640 m3 per hectare)
Four Storage Terminals within the Trans Mountain Pipeline System:
In Operation 40 storage tanks Total capacity of 5.3 million barrels October 2014 (Edmonton Terminal Expansion Project in service) * 54 storage tanks Total capacity of 10.8 million barrels
* Edmonton Terminal Expansion Project – 15 new storage tanks (one replacement tank) approved under separate application to the NEB in 2008, and amended in 2011 for additional capacity
Burnaby
Sumas
Kamloops
Edmonton*
26 tanks 5.6 mil. bbl 7 tanks 890,000 bbl
2 tanks
160,768 bbl 39 tanks 9.25 mil. bbl
+ 14 tanks (one replacement) + 1 tank no tanks proposed + 5 tanks (one replacement)
* Including the Edmonton Terminal Expansion Project
20 new tanks distributed between the existing terminals = 72 storage tanks total with a capacity of 15.8 million barrels
For comparison 3 Aframax tankers can load approximately 1.7 million barrels
their spill prevention and Emergency Response Plan, requirement of the NEB
to assist in event of an emergency - Chevron, Suncor, Shell, Imperial Oil
Mutual Emergency Assistance Agreement (MEAA), effective January 2014
infrastructure and resources, as part of their proposal:
“first-responders” to leaks, spills, fires, and other emergencies
back-up water feed for the Burnaby Mountain Terminal (among other options)
2005
polluting Kilgard Creek 2007
2009 • 1,258 bbl oil leaked from Burnaby Mountain Terminal (contained on-site) 2012
2013
residents evacuated; 1200 m of shoreline along the Burrard Inlet impacted – long term impact to local ecosystems & wildlife
estimated at + $15 M
and 2 contractor companies at fault
Effects of the 2007 Burnaby Oil Spill
Kalamazoo River Oil Spill 2010
crude (diluted bitumen) spilled.
American history.
long-term impacts to environment and ecosystems; clean-up ongoing
pipe); poor response time
7065 Bayview Drive | 15 acre site Existing Westridge Marine Terminal Site
Existing Westridge Marine Terminal
Photo Credit: Stephen Rees
1.4 ha foreshore expansion
Kinder Morgan has indicated that the existing dock may be decommissioned in the future.
Conceptual Westridge Marine Terminal Expansion
Kinder Morgan visual representation of the proposed Westridge Marine Terminal Expansion
EXISTING PROPOSED
Marine Liability Act set liability at a $1.312 billion limit.
Four - tier approach to provision of funds:
($840 M)
with the regulatory public engagement process, as required by the NEB
Morgan’s properties in Burnaby is anticipated.
is currently not a part of KM’s proposal
TMEP
considered as part of the Public Hearing for the TMEP
in order to participate as an Intervenor in the anticipated Public Hearing Process
submitted their facilities application to the NEB for the TMEP
Participate as an Intervenor for the TMEP
Don Young, and Lyn Mercier)
completeness (3 to 4 months)
location of Hearing
months) to either:
conditions set out in the report; or
compensation for acquisition of rights-of-way (agreement, negotiation or arbitration)
Phase I
Hearing
Phase II • Strategy and Scoping of Issues Phase III • Preparation for the NEB Public Hearing Phase IV
Burnaby Urban Context - 1955
Burnaby Urban Context – 2012
City of Burnaby:
Intervenor
Environment Localized Impacts to Residents Economy and Employment Property, Land Use and Resources City Infrastructure Public Health and Safety Risk Assessment Emergency Response Off-Setting Benefits
Contact Information: Email: TMEPInquiry@burnaby.ca Phone: 604.297.4400 (direct line) Fax: 604.294.7425 Mail: Engineering Department