City of Anamosa, Iowa Police Department Needs Evaluation - Study Findings Presentation & Recommendations February 26, 2020 #2193000 City of Anamosa, IA Police Department Needs Evaluation Overall Need Summary by Owner Polk


slide-1
SLIDE 1

City of Anamosa, Iowa

Police Department Needs Evaluation - Study

Findings Presentation & Recommendations

‪February 26, 2020 ‪#2193000
slide-2
SLIDE 2

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

2

Parking 4-6 Stalls

Overall – Need Summary by Owner

Polk County Sheriff’s Office

slide-3
SLIDE 3

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

3

Parking 4-6 Stalls

Polk County Sheriff’s Office

Overall – Need Summary by Owner

slide-4
SLIDE 4

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

4

Parking 4-6 Stalls

Polk County Sheriff’s Office

Overall – Need Summary by Owner

slide-5
SLIDE 5

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

5

Parking 4-6 Stalls

Polk County Sheriff’s Office

Overall – Need Summary by Owner

slide-6
SLIDE 6

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

Demographic Data - Comparisons

Community Current Population Projected Population (30 years) to 2049 Projected Population Growth / Year (30 years) to 2049 Current Staff (sworn & civilian) Staff Projection (15 years) Staff Projection (30 years) Existing Space Calculation (GSF) Projected Space Needs to Support - 30 Year Staff Projection (GSF) SF per Staff #

Clive, IA

17,419 29,386 1.55% 28

  • 36

21,700 22,250

618.06 Altoona, IA

16,984 44,891 2.75% 30 48 66 8,000 36,100

546.97 Pleasant Hill, IA

9,314 25,783 3.04% 22 41 50 7,500 27,000

540.00 Mount Pleasant, IA

8,433 8,587 0.05% 17 17 17 4,000 8,000

470.59 Oelwein, IA

6,153 6,882 0.33% 22 22 22 TBD 12,637

574.41 Grinnell, IA

9,141 9,457 0.10% 16 16 20 TBD 14,214

710.70 Polk County, IA - Sheriff's Office

467,711 731,070 5.21% 118 123 128 TBD 52,500

410.16 Anamosa, IA (Projected with IDOC Census Pop.)

5,469 5,853 0.20% 9 12 12 TBD 6,500

541.67 Average of Comparable: 5

Note: Anamosa, IA Police Department Facility 30-year Planning / Program initial estiamte should fall within the expected range. Verification needed during detailed needs assessment phase. Initial Consideration: Range without Parking Garage between 450 to 550SF per staff position. (No Firing Range; Admin Space for Patrol, CID/Detectives, Dispatch, Evidence, Property Storage, Impound, and Training). With Community Meeting Space. (Published 6,400 pop)

G.S.F. / Staff

550.00

Recognized 'Best Practice' Industry Average Range is 500 to 600 SF pre projected Staff Position. Parking solutions are a variable. (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Animal Control). Without Community Meeting Space - Average SF per staff position is 383 GSF. -

EXCLUDED IN COM PARABLE AVERAGE

Notes (No Firing Range, 1,900sf Garage brings - Limited to Vehicle Maint. & Storage) (4,500 sf Vehicle Enclosure & 1,730 SF Vehicle Evidence Garage) (4,500 sf Firing Range, 10,000sf Garage (Parking) brings total to 50,600sf) (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training, Garage and Vehicle Maintenance). (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Processing). Without Community Meeting Space - Average SF per staff position between 500 to 600 GSF. (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Animal Control). With Community Meeting Space (2,047SF) - Total building area 18,263 SF. (Published 9,218 pop) - EXCLUDED IN

COM PARABLE AVERAGE

6

slide-7
SLIDE 7

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

SPACE NEEDS SUMMARY Description

Total (OSF) Patrol Division – Patrol, Patrol Work / Roll Call (Squad), Staff Support, Equipment & Storage, Printer, Armory, etc. 920 Ancillary – Public Reception, Building Support (IT, Mechanical, Electrical, Restrooms, etc.), Community Meeting Space, Break Room 1,665 Training & Support – Locker Rooms, Fitness, Defensive Tactics Training, Toilet / Shower, etc. 830 Criminal Investigation – Property & Evidence Control, Interview Rooms, Interview Viewing, Fingerprinting, Fingerprint Waiting, etc. 1,360 Chief & Administration – Chief’s‪Office, Workroom (supplies), Admin Assistant / Reception, Future Office 1,380 Garage & Garage Storage – Vehicles (2), Bike Storage, etc. 1,450

Sub-total: 7,605

Occupied .S.F.

TOTAL

[1.105 gross building factor]

8,362

Gross S.F.

9 12

Projected Staff with future Present / Current Staff

7

slide-8
SLIDE 8

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

8

Parking 4-6 Stalls

Overall Floor Plan – Existing

Polk County Sheriff’s Office

slide-9
SLIDE 9

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

9

Parking 4-6 Stalls

Overall Floor Plan – Existing Dimension & Areas

Polk County Sheriff’s Office

slide-10
SLIDE 10

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

11

Parking 4-6 Stalls

Overall Floor Plan – Concept Plan

Polk County Sheriff’s Office

slide-11
SLIDE 11

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

12

Parking 4-6 Stalls

Overall Floor Plan – Concept Elevations from 3D Scan Data

Polk County Sheriff’s Office

slide-12
SLIDE 12

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

13

Parking 4-6 Stalls

Overall Floor Plan – Existing Dimension & Areas

Polk County Sheriff’s Office

slide-13
SLIDE 13

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

14

Parking 4-6 Stalls

Polk County Sheriff’s Office

Consideration – Renovation Cost Summary by Owner

Construction Inflation is averaging 4% per year (So for comparison, $226 /SF in 2018 would be $242.44 /SF in 2020)

slide-14
SLIDE 14

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

15

Shive-Hattery - COST OPINION for RENOVATION

Targeted Project Cost Range

$1,225,000 A Site Work / Paving Improvements & Drainage Remediation $105,000 B Design & Estimating Contingency - 15% $200,000 C Furniture, Fixtures & Equipment - 6.25% $95,000

Project Construction Total (A+B+C)

GSF

8,362 $1,625,000 Construction Cost/Square Foot (Excluding Equipment 'FFE' Line 'C') $182.97

D Building / Land Acquisition Allowance $245,000 E Basic Services A/E Professional Fees - % with Civil Eng. $145,000 F Construction Contingency - 5% $80,000 G Other - Administrative - 1.8% $30,000

Total (Renovation / Remodel) Project Costs for a Spring 2020 Bid $2,125,000 5.00% Low Range High Range

H Construction Cost incl. FFE Range at 5% Variance

$1,550,000 $1,700,000

Cost per Gross Square Foot (Construction)

$174.00 $191.94

I Soft Cost Carry-over (D+E+F+G)

$500,000 $500,000 $2,050,000 $2,200,000

Item G Breakout: Notes: Est. of Probable Cost, assumes the existing building does not contain asbestos, no environmental contamination issues. Printing, survey, permitting, additional site visits, misc.

Project Soft Costs

(Including Building / Land Acquisition)

Project Cost Range Analysis (Due to Market Conditions) Total (Renovation / Addition) Project Budget Range (H+I) Sub-Total Building Components

STATEMENT OF PROBABLE COST - Existing Retrofit (Pre-Design Report)

slide-15
SLIDE 15

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

16

Parking 4-6 Stalls

Polk County Sheriff’s Office

Consideration – New Construction Cost Summary by Owner

Construction Inflation is averaging 4% per year (So for comparison, $316 /SF in 2016 would be $384.25 /SF in 2020)

slide-16
SLIDE 16

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

17

Shive-Hattery - COST OPINION for NEW CONSTRUCTION

Targeted Project Cost Range

$2,455,000 A Site Work / Parking Improvements & Drainage $295,000 B Design & Estimating Contingency - 12.5% $340,000 C Furniture, Fixtures & Equipment - 3.1% $95,000

Project Construction Total (A+B+C)

GSF

8,362 $3,185,000 Construction Cost/Square Foot (Excluding Equipment 'FFE' Line 'C') $369.53

D Building / Land Acquisition Allowance $245,000 E Basic Services A/E Professional Fees - % with Civil Eng. $270,000 F Construction Contingency - 5% $160,000 G Other - Administrative - 2% $65,000

Total (New Building) Project Costs for a Spring 2020 Bid $3,925,000 5.00% Low Range High Range

H Construction Cost incl. FFE Range at 5% Variance

$3,035,000 $3,335,000

Cost per Gross Square Foot (Construction)

$351.59 $387.47

I Soft Cost Carry-over (D+E+F+G)

$740,000 $740,000 $3,775,000 $4,075,000

Item G Breakout: Notes: Estimate of Probable Cost, assumes a selected site does not have environmental contamination issues. Printing, survey, permitting, additional site visits, misc.

Project Soft Costs

(Including Land Acquisition)

Project Cost Range Analysis (Due to Market Conditions) Total (Renovation / Addition) Project Budget Range (H+I) Sub-Total Building Components

STATEMENT OF PROBABLE COST - NEW COMPARISON (Pre-Design Report)

Projected cost increase compared with Renovated Construction option is $1.8 million.

slide-17
SLIDE 17

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

18

Shive-Hattery - COST OPINION for NEW CONSTRUCTION (Reduced Square Feet)

Targeted Project Cost Range

$1,975,000 A Site Work / Parking Improvements & Drainage $250,000 B Design & Estimating Contingency - 12.5% $280,000 C Furniture, Fixtures & Equipment - 3.8% $95,000

Project Construction Total (A+B+C)

GSF

6,465 $2,600,000 Construction Cost/Square Foot (Excluding Equipment 'FFE' Line 'C') $387.49

D Building / Land Acquisition Allowance $245,000 E Basic Services A/E Professional Fees - % with Civil Eng. $220,000 F Construction Contingency - 5% $130,000 G Other - Administrative - 2% $55,000

Total (New Building) Project Costs for a Spring 2020 Bid $3,250,000 5.00% Low Range High Range

H Construction Cost incl. FFE Range at 5% Variance

$2,475,000 $2,725,000

Cost per Gross Square Foot (Construction)

$368.15 $406.82

I Soft Cost Carry-over (D+E+F+G)

$650,000 $650,000 $3,125,000 $3,375,000

Item G Breakout: Notes: Estimate of Probable Cost, assumes a selected site does not have environmental contamination issues. Printing, survey, permitting, additional site visits, misc.

Project Soft Costs

(Including Land Acquisition)

Project Cost Range Analysis (Due to Market Conditions) Total (Renovation / Addition) Project Budget Range (H+I) Sub-Total Building Components

STATEMENT OF PROBABLE COST - NEW COMPARISON Reduced Scope (Pre-Design Report)

Projected cost increase compared with Renovated Construction option is $1.125 million.

slide-18
SLIDE 18

City of Anamosa, IA – Police Department Needs Evaluation

February 26, 2020

20