City of Anamosa, Iowa Police Department Needs Evaluation - Study - PowerPoint PPT Presentation

City of Anamosa, Iowa Police Department Needs Evaluation - Study Findings Presentation & Recommendations February 26, 2020 #2193000 City of Anamosa, IA Police Department Needs Evaluation Overall Need Summary by Owner Polk


  1. City of Anamosa, Iowa Police Department Needs Evaluation - Study Findings Presentation & Recommendations ‪ February 26, 2020 ‪ #2193000

  2. City of Anamosa, IA – Police Department Needs Evaluation Overall – Need Summary by Owner Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 2

  3. City of Anamosa, IA – Police Department Needs Evaluation Overall – Need Summary by Owner Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 3

  4. City of Anamosa, IA – Police Department Needs Evaluation Overall – Need Summary by Owner Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 4

  5. City of Anamosa, IA – Police Department Needs Evaluation Overall – Need Summary by Owner Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 5

  6. City of Anamosa, IA – Police Department Needs Evaluation Demographic Data - Comparisons Projected Projected Projected Space Population Current Staff Current Population Staff Projection Staff Projection Existing Space Needs to Support - SF per Notes Community Growth / Year (sworn & Population (30 years) to (15 years) (30 years) Calculation (GSF) 30 Year Staff Staff # (30 years) to civilian) 2049 Projection (GSF) 2049 (4,500 sf Vehicle Enclosure & 1,730 SF Vehicle ---- Clive, IA 17,419 29,386 1.55% 28 36 21,700 22,250 618.06 Evidence Garage) (4,500 sf Firing Range, 10,000sf Garage (Parking) Altoona, IA 16,984 44,891 2.75% 30 48 66 8,000 36,100 546.97 brings total to 50,600sf) (No Firing Range, 1,900sf Garage brings - Limited Pleasant Hill, IA 540.00 9,314 25,783 3.04% 22 41 50 7,500 27,000 to Vehicle Maint. & Storage) (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training, Garage and Mount Pleasant, IA 470.59 8,433 8,587 0.05% 17 17 17 4,000 8,000 Vehicle Maintenance). (No Firing Range; Admin Space for Patrol, CID/Detectives, Dispatch, Evidence, Property Storage, Impound, and Training). With Community Oelwein, IA 6,153 6,882 0.33% 22 22 22 TBD 12,637 574.41 Meeting Space. (Published 6,400 pop) (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Animal Control). With Community Meeting Space (2,047SF) - Total building area 18,263 SF. (Published 9,218 pop) - EXCLUDED IN Grinnell, IA 710.70 9,141 9,457 0.10% 16 16 20 TBD 14,214 COM PARABLE AVERAGE (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Animal Control). Without Community Meeting Space - Average SF per staff position is 383 GSF. - Polk County, IA - Sheriff's Office 410.16 467,711 731,070 5.21% 118 123 128 TBD 52,500 EXCLUDED IN COM PARABLE AVERAGE (No Firing Range; Admin Space for Patrol, CID/Detectives, Evidence, Training and Processing). Without Community Meeting Space - Anamosa, IA (Projected with IDOC Average SF per staff position between 500 to 600 Census Pop.) 5,469 5,853 0.20% 9 12 12 TBD 6,500 541.67 GSF. 550.00 Average of Comparable: 5 G.S.F. / Staff Recognized 'Best Practice' Industry Average Range is 500 to 600 SF pre projected Staff Position. Parking solutions are a variable. Note: Anamosa, IA Police Department Facility 30-year Planning / Program initial estiamte should fall within the expected range. Verification February 26, 2020 needed during detailed needs assessment phase. Initial Consideration: Range without Parking Garage between 450 to 550SF per staff position. 6

  7. City of Anamosa, IA – Police Department Needs Evaluation SPACE NEEDS SUMMARY Present / Current Description 9 Total (OSF) Staff Patrol Division – Patrol, Patrol Work / Roll Call (Squad), Staff Support, 920 Equipment & Storage, Printer, Armory, etc. Ancillary – Public Reception, Building Support (IT, Mechanical, Electrical, 1,665 Restrooms, etc.), Community Meeting Space, Break Room 12 Projected Staff 830 with future Training & Support – Locker Rooms, Fitness, Defensive Tactics Training, Toilet / Shower, etc. Criminal Investigation – Property & Evidence Control, Interview Rooms, 1,360 Interview Viewing, Fingerprinting, Fingerprint Waiting, etc. Chief & Administration – Chief’s‪Office , Workroom (supplies), Admin Assistant / 1,380 Reception, Future Office Garage & Garage Storage – Vehicles (2), Bike Storage, etc. 1,450 Sub-total: 7,605 Occupied .S.F . TOTAL 8,362 February 26, 2020 [1.105 gross building factor] Gross S.F. 7

  8. City of Anamosa, IA – Police Department Needs Evaluation Overall Floor Plan – Existing Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 8

  9. City of Anamosa, IA – Police Department Needs Evaluation Overall Floor Plan – Existing Dimension & Areas Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 9

  10. City of Anamosa, IA – Police Department Needs Evaluation Overall Floor Plan – Concept Plan Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 11

  11. City of Anamosa, IA – Police Department Needs Evaluation Overall Floor Plan – Concept Elevations from 3D Scan Data Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 12

  12. City of Anamosa, IA – Police Department Needs Evaluation Overall Floor Plan – Existing Dimension & Areas Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 13

  13. City of Anamosa, IA – Police Department Needs Evaluation Consideration – Renovation Cost Summary by Owner Construction Inflation is averaging 4% per year (So for comparison, $226 /SF in 2018 would be $242.44 /SF in 2020) Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 14

  14. City of Anamosa, IA – Police Department Needs Evaluation Shive-Hattery - COST OPINION for RENOVATION STATEMENT OF PROBABLE COST - Existing Retrofit (Pre-Design Report) Sub-Total Building Components $1,225,000 A Site Work / Paving Improvements & Drainage Remediation $105,000 B Design & Estimating Contingency - 15% $200,000 C Furniture, Fixtures & Equipment - 6.25% $95,000 Project Construction Total (A+B+C) 8,362 $1,625,000 GSF Construction Cost/Square Foot (Excluding Equipment 'FFE' Line 'C') $182.97 Project Soft Costs D Building / Land Acquisition Allowance $245,000 E Basic Services A/E Professional Fees - % with Civil Eng. $145,000 F Construction Contingency - 5% $80,000 G Other - Administrative - 1.8% $30,000 Targeted Total (Renovation / Remodel) Project Costs for a Spring 2020 Bid $2,125,000 (Including Building / Land Acquisition) Project Cost Project Cost Range Analysis (Due to Market Conditions) 5.00% Low Range High Range $1,550,000 $1,700,000 H Construction Cost incl. FFE Range at 5% Variance $174.00 $191.94 Cost per Gross Square Foot (Construction) $500,000 $500,000 I Soft Cost Carry-over (D+E+F+G) Range Total (Renovation / Addition) Project Budget Range (H+I) $2,050,000 $2,200,000 Item G Breakout: Printing, survey, permitting, additional site visits, misc. Notes: Est. of Probable Cost, assumes the existing building does not contain asbestos, no environmental contamination issues. February 26, 2020 15

  15. City of Anamosa, IA – Police Department Needs Evaluation Consideration – New Construction Cost Summary by Owner Construction Inflation is averaging 4% per year (So for comparison, $316 /SF in 2016 would be $384.25 /SF in 2020) Polk County Sheriff’s Parking 4-6 Stalls Office February 26, 2020 16

  16. City of Anamosa, IA – Police Department Needs Evaluation Shive-Hattery - COST OPINION for NEW CONSTRUCTION STATEMENT OF PROBABLE COST - NEW COMPARISON (Pre-Design Report) Sub-Total Building Components $2,455,000 A Site Work / Parking Improvements & Drainage $295,000 B Design & Estimating Contingency - 12.5% $340,000 C Furniture, Fixtures & Equipment - 3.1% $95,000 Project Construction Total (A+B+C) 8,362 $3,185,000 GSF Construction Cost/Square Foot (Excluding Equipment 'FFE' Line 'C') $369.53 Project Soft Costs D Building / Land Acquisition Allowance $245,000 E Basic Services A/E Professional Fees - % with Civil Eng. $270,000 F Construction Contingency - 5% $160,000 G Other - Administrative - 2% $65,000 Targeted Projected cost Total (New Building) Project Costs for a Spring 2020 Bid (Including Land Acquisition) $3,925,000 Project increase compared Cost Project Cost Range Analysis (Due to Market Conditions) with Renovated Construction option 5.00% Low Range High Range $3,035,000 $3,335,000 H Construction Cost incl. FFE Range at 5% Variance is $1.8 million. $351.59 $387.47 Cost per Gross Square Foot (Construction) $740,000 $740,000 I Soft Cost Carry-over (D+E+F+G) Range Total (Renovation / Addition) Project Budget Range (H+I) $3,775,000 $4,075,000 Item G Breakout: Printing, survey, permitting, additional site visits, misc. Notes: Estimate of Probable Cost, assumes a selected site does not have environmental contamination issues. February 26, 2020 17

Download Presentation
Download Policy: The content available on the website is offered to you 'AS IS' for your personal information and use only. It cannot be commercialized, licensed, or distributed on other websites without prior consent from the author. To download a presentation, simply click this link. If you encounter any difficulties during the download process, it's possible that the publisher has removed the file from their server.